• Dienstag, 23 Juli 2024
  • 04:33 Uhr Frankfurt
  • 03:33 Uhr London
  • 22:33 Uhr New York
  • 22:33 Uhr Toronto
  • 19:33 Uhr Vancouver
  • 12:33 Uhr Sydney

Rubicon Reports Positive Results for New Preliminary Economic Assessment and a 111% Increase in Indicated Mineral Resources

25.06.2013  |  Marketwire

TORONTO, ONTARIO -- (Marketwired) -- 06/25/13 -- Rubicon Minerals Corporation (TSX: RMX)(NYSE MKT: RBY) ("Rubicon" or the "Company") is pleased to announce positive results and highlights from a new preliminary economic assessment ("New PEA")(1) and updated mineral resource estimate completed by SRK Consulting (Canada) Inc. ("SRK") for the F2 Gold System, which comprises part of the Company's flagship Phoenix Gold Project, located in Red Lake, Ontario. A technical report documenting the New PEA will be filed on SEDAR within 45 days in accordance with the requirements of National Instrument 43-101 Standards of Disclosure for Mineral Projects ("NI 43-101").


Readers are cautioned that the New PEA is preliminary in nature and includes inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves. There is no certainty that the inferred resources will be converted to the measured and indicated categories, that the indicated resources will be converted to the proven and probable mineral reserve categories and there is no certainty that the New PEA will be realized. Mineral resources that are not mineral reserves do not have demonstrated economic viability; the estimate of mineral resources in the New PEA and updated mineral resource statement may be materially affected by environmental, permitting, legal, title, taxation, socio-political, marketing, or other relevant issues.


All financial figures are in Canadian dollars unless otherwise specified


New PEA Highlights:



-- On a go-forward basis, the Phoenix Gold Project base case demonstrates
an after-tax internal rate of return(2) ("IRR") of 27.0% and a 5%
discounted after-tax net present value(2) ("NPV") of $531.0 million; on
a pre-tax basis, IRR and NPV are 28.7% and $650.0 million, respectively;
-- Total life of potential mine ("LOM") projected gold production of 2.19
million ounces, an 18.0% increase over the previous conceptual
production plan(3);
-- Average annual projected gold production of 165,300 ounces, expected to
peak at 242,000 ounces in year 2022;
-- The primary projected mining method(3) is intended to be longhole
stoping ("longhole"); 90% of the LOM production is planned to come from
longhole stopes and 10% from cut-and-fill mining;
-- Average grade of mill feed is 8.1 grams of gold per tonne ("g/t Au") at
a cut-off grade of 5.0 g/t Au; external dilution of 15% was applied to
the conceptual mine plan, plus internal dilution of 26%;
-- Average LOM cash operating cost is $629 per recovered ounce or $151 per
tonne; including a 1.5% royalty(4) the average LOM total cash operating
cost is $651 per recovered ounce of gold or $156 per tonne;
-- Average LOM all-in sustaining cash costs(5) are $845 per ounce or $203
per tonne;
-- Average annual post-tax cash flow from operations is $69.0 million;
-- On a go-forward basis, pre-production capital expenditure is $224.0
million (including a 20% contingency)(6); and
-- Average daily LOM throughput is approximately 1,900 tonnes per day
("tpd").


Readers are cautioned that the projected mining method, potential production profile and plan and mine plan referred to in the New PEA and this release are conceptual in nature and additional technical studies will need to be completed in order to fully assess their viability. There is no certainty that a potential mine will be realized or that a production decision will be made. A mine production decision that is made without a feasibility study carries additional potential risks which include, but are not limited to, the inclusion of inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves. Mine design and mining schedules, metallurgical flow sheets and process plant designs may require additional detailed work and economic analysis and internal studies to ensure satisfactory operational conditions and decisions regarding future targeted production.


Updated Mineral Resource Estimate Highlights:



-- Increased indicated mineral resources by 111% to 1.129 million ounces of
gold in 4.12 million tonnes grading 8.52 g/t Au using a 4.0 g/t Au cut-
off grade;
-- Block model demonstrates substantial continuity of mineralization and an
average horizontal thickness of 7.8 metres ("m") (based on 4.0 g/t Au
cut-off estimated using tonne weighted average thickness per level);
-- Reported inferred mineral resources(1) of 2.219 million ounces of gold
on 7.45 million tonnes grading 9.26 g/t Au using a 4.0 g/t Au cut-off
grade; and
-- Updated mineral resource estimate includes approximately 116,000 m of
additional drilling (90% infill) since the 2011 mineral resource
estimate.


The Company believes the new methods considered in the New PEA will potentially improve the efficiency and productivity of the Phoenix Gold Project. The implementation of the new methods will, however, increase the capital cost of developing the Project. When current working capital of $118 million is taken into account, there is a shortfall in required project capital of approximately $106 million. Rubicon is currently in negotiations with third parties in an attempt to secure non-equity funding of the shortfall. To assist in the evaluation of funding alternatives, the Company has entered into financial advisory agreements with two investment banking firms.


The New PEA summary is contained in Table 1 below(7).


Table 1: New PEA Summary



New PEA (2013)
Projected Production profile(3)
LOM from production start (years) 13
LOM projected gold production (Moz) 2.19
LOM average annual gold production (oz) 165,300

Total projected mineralized material mined (tonnes) 9,131,926
LOM average throughput (tpd) 1,900
Peak average throughput (tpd) 2,250

Average diluted grade to the mill (g/t Au) 8.06
Recovery (%) 92.5

Capital Costs (millions)
Total pre-production capital expenditure (includes 20%
contingency)(8), on a go-forward basis $224.0
Pre-production capital expenditure spent, August 2011 to-
date $117.8
Total pre-production capital expenditure from August 2011 $341.8
Total sustaining capital expenditure $425.7

Operating Costs
Cash operating costs (per tonne) $151
Cash operating costs (per recovered oz) $629
Royalty (per recovered oz, assuming US$1,385/oz gold
price) $22
Total cash cost (per recovered oz) $651 (or US$620)

LOM sustaining capital (per recovered oz) $194 (or US$185)
All-in sustaining cash cost(9) (per recovered oz) $845 (or US$805)

(8) The Company's present working capital is $118.0 million
(9) All-in sustaining cash costs include operating costs, royalties, and
sustaining capital and do not include pre-production capital
expenditures, any allocation of estimated corporate overhead costs or
exploration costs



New PEA (2013)
Economic Analysis (on a go-forward basis)(1,2,3)
Base case gold price assumption(10) (per oz) US$1,385
$CDN/$USD exchange rate assumption(3) 1.05

Pre-tax IRR (%) 28.7%
Pre-tax NPV @ 5% discount rate (millions) $650.0
After-tax IRR (%) 27.0%
After-tax NPV @ 5% discount rate (millions) $531.0

Payback period (years, at production start) 3.7

(10) 30-day trailing spot gold price as of June 14, 2013. Source: London PM
Fix


----------------------------------------------------------------------------
(1) The New PEA is preliminary in nature and includes inferred mineral
resources that are considered too speculative geologically to have the
economic considerations applied to them that would enable them to be
categorized as mineral reserves. There is no certainty that the
inferred resources will be converted to the measured and indicated
categories, that the indicated resources will be converted to the
proven and probable mineral reserve categories and there is no
certainty that the New PEA will be realized. Mineral resources that
are not mineral reserves do not have demonstrated economic viability;
the estimate of mineral resources in the New PEA and updated mineral
resource statement may be materially affected by environmental,
permitting, legal, title, taxation, socio-political, marketing, or
other relevant issues
(2) Based on a 30-day trailing spot gold price assumption of US$1,385 per
ounce and a $CDN/$USD consensus exchange rate of 1.05:1.00 (Source:
Bloomberg $CDN/$US FX Forecast 2013 through 2017, as of June 18, 2013)
(3) The projected mining method, potential production profile and plan and
mine plan are conceptual in nature and additional technical studies
will need to be completed in order to fully assess their viability.
There is no certainty that a potential mine will be realized or that a
production decision will be made. A mine production decision that is
made without a feasibility study carries additional potential risks
which include, but are not limited to, the inclusion of inferred
mineral resources that are considered too speculative geologically to
have the economic considerations applied to them that would enable
them to be categorized as mineral reserves. Mine design and mining
schedules, metallurgical flow sheets and process plant designs may
require additional detailed work and economic analysis and internal
studies to ensure satisfactory operational conditions and decisions
regarding future targeted production
(4) Assumes Rubicon exercises its right to purchase a 0.5% from the 2.0%
NSR that Franco-Nevada Corporation currently owns on the Phoenix Gold
Project water claims for US$675,000
(5) All-in sustaining cash costs include operating costs, royalties, and
sustaining capital and do not include any pre-production capital
expenditures, allocation of estimated corporate overhead costs or
exploration costs
(6) The Company presently has working capital totalling $118.0 million
(7) This news release should be read in conjunction with the tables and
figures included in the body and presented at the end of the release.
All references to the Company's original Preliminary Economic
Assessment and 2011 mineral resource estimates are reported in the
Company's Preliminary Economic Assessment ("2011 PEA") prepared by AMC
Mining Consultants (Canada) Ltd. with metallurgical and processing
contributions from Soutex Inc., with an effective date of August 8,
2011, available on SEDAR (http://www.sedar.com/) and EDGAR
(www.sec.gov/edgar.shtml). The Company plans to file a NI 43-101
Technical Report for both the New PEA and updated mineral resource
estimate within 45 days from today. This report will replace the 2011
PEA and previous mineral resource estimate
(8) The Company's present working capital is $118.0 million
(9) All-in sustaining cash costs include operating costs, royalties, and
sustaining capital and do not include pre-production capital
expenditures, any allocation of estimated corporate overhead costs or
exploration costs


"My primary objective when I took the leadership role at Rubicon was, and remains, building our flagship Phoenix Gold Project to be the best that it can be," said Michael A. Lalonde, Rubicon's President and Chief Executive Officer. "We are very pleased with the results of the updated mineral resource and the New PEA, which demonstrates that the Project has the ability to generate strong cash flow. The updated mineral resource estimate exhibits significant improvement in continuity and greater horizontal thickness over the previous mineral resource estimate, making it easier to plan and schedule future potential mining. We improved the confidence of the block model and increased the indicated mineral resources by 111% through our successful infill drilling program.


While the New PEA continues to demonstrate positive projected economics for the Phoenix Gold Project, potentially generating an after-tax IRR and NPV of 27% and $531 million, respectively, we believe that the New PEA and the updated mineral resource estimate are conservative and provide room for further optimization.


An estimated inherent internal dilution of 26% was included within the stope design envelopes used to develop the conceptual mine design. An additional 15% external dilution was applied to the conceptual mining model, compared to 18% in the 2011 PEA, to best ensure that the estimated grades are achievable once we commence potential production. We chose to take a cautious approach and set targets that we can confidently achieve. The development of the Phoenix Gold Project continues to progress well and we remain on schedule for projected gold production in the second half of 2014."


Mineral Resources for the Phoenix Gold Project


The 2013 Mineral Resource Statement for the Phoenix Gold Project is presented in Table 2 below. Please refer to Figure 1 at the end of this news release for a visual diagram of the Phoenix Gold Project domains.


Table 2: Mineral Resource Statement(1,2,3,11,12) Phoenix Gold Project, Ontario, SRK Consulting (Canada) Inc., June 24, 2013



--------------------------------------------------------------------------
--------------------------------------------------------------------------
Quantity Grade Contained Gold
Domain Resource Category(11) (000't) (g/t Au) (000'oz)

Main(13) Measured - - -

Indicated 4,120 8.52 1,129
Measured + Indicated 4,120 8.52 1,129
Inferred(1,3) 6,027 9.49 1,839
--------------------------------------------------------------------------
HW Measured - - -

Indicated - - -
Measured + Indicated - - -
Inferred(1,3) 151 5.21 25
--------------------------------------------------------------------------
External Measured - - -

Indicated - - -
Measured + Indicated - - -
Inferred(1,3) 1,274 8.66 355
--------------------------------------------------------------------------
Combined Measured - - -

Indicated 4,120 8.52 1,129
Measured + Indicated 4,120 8.52 1,129
Inferred(1,3) 7,452 9.26 2,219
--------------------------------------------------------------------------
--------------------------------------------------------------------------
Source: SRK
(11) CIM definitions were used for measured mineral resources, indicated
mineral resources and inferred mineral resources
(12) All figures have been rounded to reflect the relative accuracy of the
estimates. Reported at a cut-off grade of 4.0 g/t Au assuming an
underground extraction scenario, a gold price of US$1,500 per ounce,
and metallurgical recovery of 92.5%
(13) The Main domain includes the Main 45 domain


The Company's indicated mineral resource, at a 4.0 g/t Au cut-off grade, increased 111% to 1.129 million ounces of gold with 4.12 million tonnes grading 8.52 g/t Au, as compared to 0.54 million ounces of gold with 1.43 million tonnes grading 11.63 g/t Au reported at a 4.0 g/t Au cut-off grade as indicated material from the 2011 mineral resource model. The increase was due to the successful conversion of inferred mineral resources to the indicated category as a result of the completion of an additional 116,000 m of diamond drilling (approximately 90% infill) in 309 drill holes since the previous mineral resource. A 4.0 g/t Au cut-off grade was applied to the updated mineral resource estimate based on improved economics associated with increased continuity and horizontal thicknesses (averaging 7.8 m) of mineralized zones. The decrease in the indicated mineral resource grade compared to the previous estimate is due to the methodology and resource parameters applied to the mineral resource estimate.


The successful conversion of inferred resources to the indicated resource category resulted in the reduction of inferred mineral resources from 2.52 million ounces to 2.22 million ounces (at a 4.0 g/t Au cut-off grade). The reduction of inferred mineral resources was offset by a greater gain in the indicated mineral resource. The average grade and tonnage of the updated inferred mineral resources are 9.26 g/t Au and 7.45 million tonnes, respectively, compared to 13.83 g/t Au and 5.67 million tonnes in the 2011 PEA, using a 4.0 g/t Au cut-off grade.


Please refer to Tables 3 and 4 below for a comparison of the 2011 and 2013 classified quantity and grade estimates using 4.0 g/t Au and 5.0 g/t Au cut-off grades, respectively.


Readers are cautioned that the New PEA is preliminary in nature and includes inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves. There is no certainty that the inferred resources will be converted to the measured and indicated categories, that the indicated resources will be converted to the proven and probable mineral reserve categories and there is no certainty that the New PEA will be realized. Mineral resources that are not mineral reserves do not have demonstrated economic viability; the estimate of mineral resources in the New PEA and updated mineral resource statement may be materially affected by environmental, permitting, legal, title, taxation, socio-political, marketing, or other relevant issues.


Table 3: Comparison between 2011 and 2013 Quantities and Grades Reported at 4.0 g/t



----------------------------------------------------------------------------
Quantity Grade Contained
Classification(11) (000't) (g/t Au) Gold (000'oz)
---------------------------------------------------------
2011 2013 Change 2011 2013 Change 2011 2013 Change
----------------------------------------------------------------------------
Indicated 1,430 4,120 188% 11.63 8.52 -27% 535 1,129 111%
Inferred(1,2,3) 5,674 7,452 31% 13.83 9.26 -33% 2,523 2,219 -12%
----------------------------------------------------------------------------
Source: SRK


Table 4: Comparison between 2011 and 2013 Quantities and Grades Reported at 5.0 g/t



----------------------------------------------------------------------------
Quantity Grade Contained
Classification(11) (000't) (g/t Au) Gold (000'oz)
---------------------------------------------------------
2011 2013 Change 2011 2013 Change 2011 2013 Change
----------------------------------------------------------------------------
Indicated 1,028 3,116 203% 14.5 9.82 -32% 477 984 106%
Inferred(1,2,3) 4,230 5,604 32% 17 10.84 -36% 2,317 1,954 -16%
----------------------------------------------------------------------------
Source: SRK


The mineral resource estimate was prepared based on a total of 355,611 m of diamond drilling in 820 drill holes carried out between February 2008 and October 2012. The mineral resource estimate is defined over a strike length of approximately 1,200 m and depths of 1,500 m and remains open along strike and at depth. A summary of the 2013 Global Quantities and Grade Estimates at Various Cut-off Grades is presented in Table 5 below:


Table 5: The 2013 Global Quantities and Grade Estimates at Various Cut-off Grades(14,15,16,17)



----------------------------------------------------------------
----------------------------------------------------------------
Indicated Classification Inferred Classification(1,3)
----------------------------------------------------------------------------
------------
Cut-off Contained Contained
Grade Tonnes Grade Ounces Au Tonnes Grade Ounces Au
(g/t Au) (000s) (g/t Au) (000) (000s) (g/t Au) (000)
----------------------------------------------------------------------------
7.0 1,959 12.16 766 3,962 12.90 1,643
----------------------------------------------------------------------------
6.0 2,425 11.06 862 4,617 11.99 1,780
----------------------------------------------------------------------------
5.0 3,116 9.82 984 5,604 10.84 1,954
----------------------------------------------------------------------------
4.0 4,120 8.52 1,129 7,452 9.26 2,219
----------------------------------------------------------------------------
3.0 5,396 7.33 1,272 11,119 7.34 2,623
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Source: SRK
(14) CIM definitions were used for indicated mineral resources and inferred
mineral resources
(15) Mineral resources that are not mineral reserves do not have
demonstrated economic viability. All figures have been rounded to
reflect the relative accuracy of the estimates. Reported at cut-off
grade sensitivities ranging from 3.0 g/t Au to 7.0 g/t Au assuming an
underground extraction scenario, a gold price of US$1,500 per ounce,
and metallurgical recovery of 92.5%
(16) Capping values of 200 g/t Au, 150g/t Au, and 30 g/t Au were applied to
the composites from the Main and 45 Trend, HW, and External domains,
respectively
(17) Using drilling results to October 31, 2012


The mineral resource block model demonstrates improved continuity at the 4.0 g/t Au cut-off grade. The estimated average horizontal thickness of the gold mineralization is approximately 7.8 m (based on 4.0 g/t Au cut-off estimated using tonne weighted average thickness per level). Ordinary kriging was used as the calculation methodology, compared to the inverse distance cubed methodology used for the previous mineral resource estimate. Block model parameters applied to the current mineral resource statement are listed in Tables 6, 7, 8, and 9 at the end of this release.


Capping values of 200 g/t Au, 150 g/t Au and 30 g/t Au were applied to the composites from the Main and 45 Trend, HW, and External wireframes, respectively, representing a lower capping grade compared to the previous mineral resource estimate of 270 g/t Au.


During 2011, Rubicon collected two approximately 1,000-tonne gold mineralized bulk samples from underground stoping on the 305-metre level (please refer to the Rubicon June 29, 2011 news release for more details). The bulk samples were coarse crushed and a 10 tonne sub-sample split from each. The 10 tonne sub-samples were further crushed to approximately minus 1/2 inch and shipped to G&T Metallurgical Services ("G&T") in Kamloops, BC for metallurgical test work. G&T reported the average gold contents of the head samples collected from the two bulk samples to be 7.6 and 8.6 g/t Au, respectively. SRK has estimated the grades for the areas where the bulk sample was taken for comparative purposes, by reporting block model grades within wireframes representing the two bulk samples. Although the bulk samples are limited in size they represent the best reconciliation against the resource estimate currently available. The reconciled grade of the bulk sample is notably higher than the estimated resource grade for this area. Once development resumes within the F2 zone, there will be an opportunity to take additional bulk samples to assist with grade reconciliation against the resource model. See Table 10 below for more details.


Table 10 - Comparison of Bulk Sample results (Average Head Grade Samples Reported by G&T) Versus the Bulk Sample Area Estimated by SRK 2013 (Mineral Resource Model)



----------------------------------------------------------------------------
Volume Tonnage Grade
Bulk Sample Source Domain (m(3)) (t) Density (g/t Au)
----------------------------------------------------------------------------
----------------------------------------------------------------------------
A SRK Main 189 560 2.96 17.91

45 Trend 462 1,327 2.87 0.76
External 7 20 2.87 0.02
--------------------------------------------------
--------------------------------------------------
Total 658 1,906 2.90 5.79
G&T 976 7.60
----------------------------------------------------------------------------
----------------------------------------------------------------------------
B SRK Main 540 1,574 2.91 3.47

45 Trend - - - -
External 71 203 2.87 0.02
--------------------------------------------------
--------------------------------------------------
Total 611 1,777 2.91 3.08
G&T 1,107 8.60
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Combined SRK Main 729 2,134 2.93 7.26
A and B

45 Trend 462 1,327 2.87 0.76
External 78 223 2.87 0.02
--------------------------------------------------
--------------------------------------------------
Total 1,269 3,683 2.90 4.48
G&T 2,083 8.13
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Source: SRK


Conceptual Mining Model(1,2,3) for the New PEA (diluted)


The conceptual mining model uses a design cut-off grade of 5.0 g/t Au and will potentially extract 78% (by ounces) of the mineral resources reported in Table 2. The stope outlines (greater than 5.0 g/t Au) include inherent internal dilution of approximately 26% derived from areas contained within the block models. An average external dilution of 15% grading 0.68 g/t Au was applied with higher than typical external dilution grade resulting from the disseminated nature of the gold mineralization. The resulting tonnes delivered to the mill, after application of dilution and appropriate conceptual mining losses, are 9.13 million grading at 8.1 g/t Au for a total of 2.37 million ounces (an increase in total ounces of 18% compared to the 2011 PEA).


Conceptual Mining(1,2,3)


The New PEA considers the development of the F2 Gold System as a potential underground mine using methods that are significantly different to those modeled in the 2011 PEA. The new primary planned method is longhole stoping utilizing paste backfill. It is intended that the longhole method will comprise 90% of the total mining with 10% cut-and-fill. Approximately 76% of the longhole tonnage will come from stope widths greater than 5 m (56% of LOM tonnage). Please see Figure 2 at the end of this release for a cross section of the conceptual mine plan. Please see Figure 3 at the end of this release for the potential production and cash flow schedule.


Readers are cautioned that the mining model, projected mining method, potential production profile and plan and mine plan referred to in the New PEA and this release are conceptual in nature and additional technical studies will need to be completed in order to fully assess their viability. There is no certainty that a potential mine will be realized or that a production decision will be made. A mine production decision that is made without a feasibility study carries additional potential risks which include, but are not limited to, the inclusion of inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves. Mine design and mining schedules, metallurgical flow sheets and process plant designs may require additional detailed work and economic analysis and internal studies to ensure satisfactory operational conditions and decisions regarding future targeted production.


Development and Infrastructure


The main underground levels are planned to be spaced nominally 60 m apart with sublevel spacings between 15 m and 30 m depending on width of target gold mineralization and access method selected. The main levels are planned to be connected by a series of ramps for the efficient movement of equipment, material, and personnel between levels. Material is planned to be transferred between levels by gravity through internal ore passes to the 610-metre level, where rail units are planned to haul this material to an ore pass dump. From here, the material is planned to be crushed and conveyed to the loading pocket at the 680-metre elevation. The crushed material will then be hoisted to surface via 10-tonne skip for processing at the mill.


The current shaft will be deepened to the 710-metre level. The shaft will later be extended from the 710-metre level to the 1,400-metre elevation (shaft bottom) utilizing a concrete circular configuration which is designed to best address a wide range of ground conditions. The 1285-metre level will be the main haulageway for material mined below the 610-metre level. Hoisting will be via 16-tonne skips from a loading pocket on the 1360-metre level. There is no planned interruption to mining activities in the upper levels. The second phase of sinking is planned to be separated from the rest of the mine by installing a substantial concrete bulkhead between operating shaft and the shaft extension.


Additional delineation drilling is planned to provide further definition required for detailed stope planning. As well, an exploration platform is planned for the 610-metre level allowing for deep expansion drilling.


Throughput


The LOM average throughput rate is estimated to be 1,900 tpd, with a peak throughput rate of 2,250 tpd. The mineralized material is planned to be crushed underground by a jaw crusher. Hoisting capacity is 3,000 tonnes from the upper pocket, based on 12-hours of hoisting per day, and 3,000 tonnes from the lower pocket, based on 10-hours of hoisting per day. A ball mill and pebble mill will be added to the current SAG mill and ball mill configuration to achieve higher throughput rates. The current mill building has enough capacity to add the extra ball mill and pebble mill.


Equipment


A mix of battery-operated, electric, and diesel powered 3.5 cubic yard scoops and trucks are planned to be utilized to provide a cleaner work environment for personnel.


Metallurgy and Processing


Soutex Inc. had confirmed that processing of the material will be a combination of gravity separation followed by a conventional carbon-in-leach ("CIL") process. Total gold recovery is estimated at 92.5%. 50.0% of the gold will be recovered through gravity separation.


Capital Cost Summary


The capital cost estimates, on a go-forward basis, for the Phoenix Gold Project are summarized in Table 11 below.


Table 11: Capital Cost Summary



----------------------------------------------------------------------------
$millions
Pre-production capital
Mill $94.5
Surface infrastructure $42.7
Underground development $42.7
Shaft, underground infrastructure, and mobile equipment $15.7
Other development (pre-production stope development) $27.7
Royalty purchase of 0.5% NSR(4) $0.7
----------------------------------------------------------------------------
Total pre-production capital, on a go-forward
basis(including 20% contingency)(8) $224.0

Sustaining capital $425.7

Total project capital $649.7

----------------------------------------------------------------------------


Operating Cost Summary


The cash operating cost for the project is $629 per recovered ounce of gold or $151 per tonne of mineralized material. Total cash cost is $651 per ounce of recovered gold, including a 1.5% royalty and assuming a US$1,385/oz gold price and 1.05 exchange rate. If sustaining capital of $194 per recovered ounce is added to the total cash cost, the resulting all-in sustaining cost is $845 per recovered ounce (US$805/oz). See Table 12 below for more details.


Table 12: Operating Cost Summary



----------------------------------------------------------------------------
Per ounce Per tonne
Cash operating cost components
In stope mining cost $113 $27
Underground utilities $52 $13
Underground services $24 $6
Material handling $37 $9
Surface, general and administrative $128 $30
Processing $84 $20
Lateral operating development $76 $18
Vertical operating development $7 $2
Pre-production lateral development $85 $20
Pre-production vertical development $23 $6
----------------------------------------------------------------------------
Total cash operating cost before royalties $629 $151
Royalty (1.5%) $22 $5
----------------------------------------------------------------------------
Total cash costs $651 $156
Sustaining capital cost $194 $47
----------------------------------------------------------------------------
All-in sustaining cash cost(9) $845 $203
(or US$805)
----------------------------------------------------------------------------


Royalties and Taxes


The Phoenix Gold Project mineral claims that comprise the F2 Gold System are subject to a 2.0% royalty payable to Franco-Nevada Corporation. The Company has the option to purchase a 0.5% royalty for US$675,000, which the Company intends to purchase and is factored into the New PEA.


The Company estimates that it will have approximately $355 million of tax deductible pools, tax losses and tax credits available for deduction at the potential commencement of commercial production. Application of these pools and deductions is estimated to result in the payment of no income taxes in the first eight years of production and no Ontario Mineral Tax in the first seven years of production. Any Ontario Alternate Minimum Tax charged is expected to be recovered in ensuing years and is not expected to have a material effect on the economic model.


Economic Analysis and Sensitivities


The economic analysis of the New PEA assumed a base case 30-day average of the London PM fix spot gold price of US$1,385 per ounce (as of June 14, 2013) and a discount rate of 5%. Cost escalation was not used in the financial model. Under these parameters, on an after-tax basis, the base case go-forward NPV and IRR calculated on a mid-year cash flow basis for the project are $531.0 million and 27.0%, respectively. See sensitivities in Tables 13, 14, and 15 below for more details. Readers should note that mineral resources that are not mineral reserves do not have demonstrated economic viability.


Table 13: After-Tax NPV(2) ($millions) Sensitivity, go-forward basis



----------------------------------------------------------------------------
Discount Rate Gold Price Assumption
------------------------------------------------
US$1,385/oz
US$1,100/oz (base case) US$1,700/oz
----------------------------------------------------------------------------
3.0% $275.3 $655.1 $1,061.3
----------------------------------------------------------------------------
5.0% $193.8 $531.0 $888.2
----------------------------------------------------------------------------
7.0% $128.4 $429.6 $745.9
----------------------------------------------------------------------------


Table 14: After-Tax IRR(2) (%) Sensitivity, go-forward basis



----------------------------------------------------------------------------
Gold Price Assumption
----------------------------------------------------------------------------
US$1,385/oz
US$1,100/oz (base case) US$1,700/oz
----------------------------------------------------------------------------
12.8% 27.0% 42.0%
----------------------------------------------------------------------------


Table 15: After-Tax NPV(2) ($millions) and IRR (%) on Grade Sensitivity, go-forward basis



------------------------------------------------------------
Average Diluted Grade to the Mill +/- 10%
------------------------------------------------------------
8.1 g/t Au
7.3 g/t Au (base case) 8.9 g/t Au
----------------------------------------------------------------------------
NPV $371.5 $531.0 $689.5
(5% discount
rate)
----------------------------------------------------------------------------
IRR 20.3% 27.2% 33.7%
----------------------------------------------------------------------------


Opportunities in the New PEA and Mineral Resource Estimate


The Company has identified several opportunities in the New PEA and updated mineral resource estimate to improve upon the economics of the project.


The Rubicon exploration team and SRK have invested a considerable amount of effort into improving the geological model and the boundaries for the mineralized zones that form the basis of the updated mineral resource estimate. The Company has identified numerous areas adjacent to the reported mineral resource blocks where, although drill holes are present with elevated gold grades, drill hole density is insufficient to satisfy the mineral resource criteria as applied by SRK. The Company believes these areas represent opportunities to expand the current mineral resource.


The deposit is also open on strike and at depth. Additional exploration could potentially add more ounces to the financial model, which would improve the project economics. Improved economics may support a new high capacity circular concrete shaft capable of reaching greater depths than contemplated in the New PEA.


The economic model is very sensitive to grade. A small increase in grade would be very significant (as Table 15 shows, a 10% increase in grade leads to a 29.8% increase in after-tax NPV in the base case). The Company regards the criteria applied by SRK to the mineral resource model as conservative given that the initial bulk samples returned grades higher than those reported by SRK in the current block model (please see Table 10 in this release). Accordingly, the Company believes there are further potential upside opportunities with respect to grade.


The Alimak horizontal breasting, longhole stoping method should be investigated for possible reduction in operating costs. This method has the potential to reduce or eliminate a portion of the operating sublevel development and, as result, increase projected productivity by improving stope cycle time.


Tailings Management Facility ("TMF")


The TMF incorporates engineered features to manage the chemical and physical stability of the deposited tailings in accordance with current best-in-class practices. Approximately 50% of the tailings will be converted to paste fill and deposited underground to minimize the amount of tailings that will be deposited on surface and also to provide a suitable backfill for the underground mine. The remaining tailings will be thickened prior to deposition in the TMF. The TMF can accommodate the tailings generated by the proposed mine plan in the New PEA, with engineering studies planned to gather empirical data and evaluate further expansion.


Closure and Rehabilitation Costs


Rehabilitation measures have been designed using a precautionary approach to ensure the long-term physical and chemical stability of the site in accordance with Ontario's Mining Act and the associated Aboriginal consultation process. The rehabilitation measures are intended to return the site to a productive land use that will not require long-term care and maintenance. The rehabilitation cost is estimated to be equivalent to the salvage value of material site assets at closure.


Permitting and Consultation


The Company has been granted the material permits required for an average production rate of 1,250 tpd and is evaluating the permit amendments required for the increased projected production rate. The increased production rate contemplated in the New PEA will not increase the surface area of the site, simplifying the permit amendments and associated consultation process.


The Company is continuing consultations with First Nations and the Metis Nation of Ontario and local municipalities.


Recommendation from SRK and Continuing Studies


SRK has determined that the results of the New PEA support the continued development of the Phoenix Gold Project and work related to further technical studies. No production decision has been made at this time. Such a decision, if reached, will require such additional technical studies and ongoing evaluation by Rubicon of the construction and development of the Phoenix Gold Project and would not be based solely on the New PEA(1).


Project Development Update and Timeline


Shaft sinking continues on the Phoenix Gold Project, with the current shaft depth at 670 m below surface. Key project milestones include:


SAG and ball mill delivery - Q3-2013


Shaft loading pocket at 680-metre elevation - Q3-2013


Mill commissioning and projected gold production(1) - H2-2014


Conference Call Details


The Company's senior management team will host a conference call today, Tuesday, June 25, 2013 at 8:30 am ET to discuss the New PEA and updated mineral resource.


Participants in Canada and the United States may join the conference call by dialing toll free 1 (800) 319-4610 or +1 (604) 638-5340 for calls outside Canada and the United States or via webcast on the Company's website at www.rubiconminerals.com.


A recorded playback of the conference call can be accessed after the event by dialing 1 (800) 319-6413 or +1 (604) 638-9010 for calls outside Canada and the United States. The pass code for the conference call playback is 7856#. The archived audio webcast will also be available on the Company's website at www.rubiconminerals.com.


About Rubicon Minerals Corporation


Rubicon Minerals Corporation is an advanced stage gold development company, focused on responsible and environmentally sustainable development of its Phoenix Gold Project in Red Lake, Ontario towards projected gold production in 2014. Rubicon's flagship Phoenix Gold Project is fully permitted for initial production at 1,250 tpd. In addition, Rubicon controls over 100 square miles of prime exploration ground in the prolific Red Lake gold district which hosts Goldcorp's high-grade, world class Red Lake Mine. Rubicon's shares are listed on the NYSE.MKT (RBY) and the TSX (RMX) Exchanges. Rubicon's shares are included in the S&P/TSX Composite Index.


RUBICON MINERALS CORPORATION


Mike Lalonde, President and Chief Executive Officer


Mineral Resources


Mineral resources that are not mineral reserves do not have demonstrated economic viability. The estimate of mineral resources may be materially affected by environmental, permitting, legal, title, taxation, socio-political, marketing, or other relevant issues. The quantity and grade of reported inferred resources in this estimation are uncertain in nature and there has been insufficient exploration to define these inferred resources as an indicated or measured mineral resource and it is uncertain if further exploration will result in upgrading them to an indicated or measured mineral resource category. The mineral resources in this press release were reported using CIM Standards.


Qualified Persons


Phoenix Gold Project exploration drill programs and all related drill data forming the basis of the resource update were supervised and verified by Terry Bursey, B.Sc., P.Geo., Regional Exploration Manager for Rubicon, through 2011 and by Matthew Wunder B.Sc., P.Geo., and Vice President Exploration for Rubicon, from January 2012 to present. Both are Qualified Persons under the definition of NI 43-101. Drill core assays were conducted on sawn NQ-sized half core sections. The saw blade is routinely cleaned between samples when visible gold is noted during logging and sampling of the drill core. All assays were conducted by SGS Minerals Services using standard fire assay procedures with a gravimetric finish. Standards, blanks and check assays were included at regular intervals in each sample batch. Check assays on 5% of samples are carried out at a third party independent laboratory. Gold standards were prepared by CDN Resource Laboratories Ltd. Daniel Labine, P.Eng., Vice President Operations for Rubicon, is the Qualified Person, under the definition of NI 43-101, responsible for the Phoenix Gold Project construction and development.


The content of this news release, other than that pertaining to metallurgy and processing, has been read and approved by SRK staff including Mr. Sebastien Bernier, P.Geo, Principal Consultant Resource Geology, Mr. Glen Cole, P.Geo., Principal Consultant (Resource Geology), Mr. Dan Hewitt, P. Eng., Principal Consultant (Mining), Mr. Stephen Taylor P. Eng, Principal Consultant (Mining) and Mr. Gary Poxleitner P. Eng, Principal Consultant (Mining), all independent Qualified Persons as defined by NI 43-101. Exploration drill programs and all related drill data forming the basis of the inferred and indicated resource estimate described in this release were supervised and verified by Terry Bursey, P.Geo., Regional Exploration Manager for Rubicon, through 2011 and Matthew Wunder B.Sc., P.Geo., and Vice President Exploration for Rubicon, from January 2012 to present. The New PEA has been prepared by SRK Consulting with metallurgical and processing contributions from Soutex Inc. Individual contributing authors are Mr. Sebastien Bernier, Mr. Glen Cole, Mr. Stephen Taylor, and Mr. Dan Hewitt of SRK Consulting and Mr. S. Caron, ing. of Soutex Inc. All are independent Qualified Persons as defined by NI 43-101.


Forward-Looking Statements


This news release contains statements that constitute "forward-looking statements" within the meaning of Section 21E of the United States Securities Exchange Act of 1934 and "forward looking information" within the meaning of applicable Canadian provincial securities legislation (collectively, "forward-looking statements"). Forward-looking statements often, but not always, are identified by the use of words such as "seek", "anticipate", "believe", "plan", "estimate", "expect", "targeting", "look forward" and "intend" and statements that an event or result "may", "will", "would", "should", "could", or "might" occur or be achieved and other similar expressions.


Forward-looking statements are based on the opinions and estimates of management as of the date such statements are made and represent management's best judgment based on facts and assumptions that management considers reasonable. The material assumptions upon which such forward-looking statements are based include, among others: that the demand for gold and base metal deposits will develop as anticipated; that the price of gold will remain at levels that will render the Phoenix Gold Project economic; that operating and capital plans will not be disrupted by issues such as mechanical failure, unavailability of parts and supplies, labour disturbances, disturbances by Aboriginal communities, interruption in transportation or utilities, or adverse weather conditions; that Rubicon will meet its estimated timeline for the development of the Phoenix Gold Project; that Rubicon will continue to have the ability to attract and retain skilled staff; that the mineral resource estimate as disclosed in the New PEA will be realized; that Rubicon will be able to obtain additional financing for its development, construction and other needs; and that there are no material unanticipated variations in the cost of energy or supplies, or in the pre-production capital and operating cost estimate as disclosed in the New PEA. Rubicon makes no representation that reasonable business people in possession of the same information would reach the same conclusions.


Capital expenditures and time required to develop new mines are considerable and changes in cost or construction schedules can significantly increase both the time and capital required to build and complete a development project. Additional capital costs may have to be incurred in respect of the Phoenix Gold Project.


The New PEA is preliminary in nature as it includes inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves and there is no certainty that the New PEA will be realized. Mineral resources that are not mineral reserves do not have demonstrated economic viability. The estimate of mineral resources may be materially affected by environmental, permitting, legal, title, taxation, socio-political, marketing, or other relevant issues. The quantity and grade of reported inferred resources referred to in the New PEA are uncertain in nature and there has been insufficient exploration to define these inferred resources as an indicated or measured mineral resource category.


Forward-looking statements in this news release include, but are not limited to statements regarding estimates of mineral resources, estimates of gold grades and ounces, estimates of costs, estimates of mine development and production, estimates of economic potential and returns, the potential result of current negotiations of different funding alternatives, and the projected gold production in 2014. The Company believes that the new methods being considered in the New PEA and optimization studies will potentially improve the efficiency and productivity of the Phoenix Gold Project. However, the implementation of the new methods will increase the capital cost of developing the Phoenix Gold Project. Management is in negotiations regarding various funding alternatives and plans to continue evaluating such alternatives, to address the increase in the capital cost of the Phoenix Gold Project.


Forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of Rubicon to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements. Such factors include, among others: future prices of gold and other metals; possible variations in mineralization, grade or recovery rates; actual results of current exploration activities; actual results of reclamation activities; conclusions of future economic evaluations and studies; changes in new mineral resource models and revised geological interpretations; changes in project parameters as plans continue to be refined; failure of equipment or processes to operate as anticipated; accidents, labour disputes and other risks of the mining industry; delays and other risks related to joint venture operations; timing and receipt of regulatory approvals of operations; the ability of Rubicon and other relevant parties to satisfy regulatory requirements; the availability of financing for proposed transactions and programs on reasonable terms; the ability of third-party service providers to deliver services on reasonable terms and in a timely manner; and delays in the completion of development or construction activities due to poor ground conditions or other factors. Other factors that could cause the actual results to differ include market prices, results of exploration, availability of capital and financing on acceptable terms, inability to obtain required regulatory approvals, unanticipated difficulties or costs in any rehabilitation which may be necessary, market conditions and general business, economic, competitive, political and social conditions.


Forward-looking statements contained herein are made as of the date of this news release and Rubicon disclaims any obligation to update any forward-looking statements, whether as a result of new information, future events or results or otherwise, except as required by applicable securities laws. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements.


It is important to note that the information provided in the New PEA and in the summary of the New PEA contained in this news release is preliminary in nature. There is no certainty that a potential mine will be realized or that a production decision will be made. A mine production decision that is made without a feasibility study carries additional potential risks which include, but are not limited to, the inclusion of inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves. Mine design and mining schedules, metallurgical flow sheets and process plant designs may require additional detailed work and economic analysis and internal studies to ensure satisfactory operational conditions and decisions regarding future targeted production.


Cautionary Note to U.S. Readers Regarding Estimates of Indicated and Inferred Resources


This news release uses the terms "indicated mineral resources" and "inferred resources". The Company advises U.S. investors that while these terms are recognized and required by Canadian securities administrators, they are not recognized by the SEC. "Inferred resources" have a great amount of uncertainty as to their existence, and great uncertainty as to their economic and legal feasibility. It cannot be assumed that all or any part of an "inferred" or "indicated mineral resource" will ever be upgraded to a higher category.


Under Canadian rules, estimates of "inferred mineral resources" may not form the basis of feasibility studies, pre-feasibility studies or other economic studies, except in prescribed cases, such as in a preliminary economic assessment under certain circumstances. The SEC normally only permits issuers to report mineralization that does not constitute "reserves" as in-place tonnage and grade without reference to unit measures. Under U.S. standards, mineralization may not be classified as a "reserve" unless the determination has been made that the mineralization could be economically and legally produced or extracted at the time the reserve determination is made. U.S. investors are cautioned not to assume that any part or all of an indicated or inferred resource exists or is economically or legally mineable. Information concerning descriptions of mineralization and resources contained herein may not be comparable to information made public by U.S. companies subject to the reporting and disclosure requirements of the SEC.


Figure 1: Vertical Section Looking Northwest Showing the Gold Mineralization Domains of the Phoenix Project


To view Figure 1, click on the following link: http://media3.marketwire.com/docs/r624a.pdf


Figure 2: Cross Section of the Conceptual Mine Plan, Phoenix Gold Project


To view Figure 2, click on the following link: http://media3.marketwire.com/docs/r624b.pdf


Figure 3: Projected Production Schedule and Cash Flow Model


To view Figure 3, click on the following link: http://media3.marketwire.com/docs/r624c.pdf


Table 6: Phoenix Project Block Models Specification



----------------------------------------------------------------------------
Block Number Rotation Rotation
Domain Axis Size (m) Origin(1) of Cells Angles Axis
--------------------
Parent Sub cell
----------------------------------------------------------------------------
X 5.0 0.1250 9,000 460 165 3
----------------------------------------------------------------------------
Main Y 10.0 0.2500 50,700 250 65 1
----------------------------------------------------------------------------
Z 2.5 0.0625 5,100 500 95 2
----------------------------------------------------------------------------
X 10.0 0.2500 10,000 196 210 3
----------------------------------------------------------------------------
45 Trend Y 5.0 0.1250 49,800 132 165 1
----------------------------------------------------------------------------
Z 2.5 0.1250 5,400 280 90 2
----------------------------------------------------------------------------
X 20.0 0.5000 9,984 92 260 3
----------------------------------------------------------------------------
HW Y 10.0 0.2500 48,698 37 -60 1
----------------------------------------------------------------------------
Z 20.0 0.5000 4,872 39 0 -
----------------------------------------------------------------------------
X 10.0 1.0000 8,905 286 165 3
----------------------------------------------------------------------------
External Y 20.0 1.0000 51,361 151 65 1
----------------------------------------------------------------------------
Z 5.0 1.0000 5,075 336 95 2
----------------------------------------------------------------------------
Source: SRK
(1) Expressed as mine grid coordinates converted from the local UTM grid
(Nad83 datum)


Table 7: Gold Variogram Parameters for the Phoenix Gold Project



----------------------------------------------------------------------------
Domain Structure Contribution Model R1x R1y R1z Angle(1) Axis
---------------------------------------
(m) (m) (m) 1 2 3 1 2 3
----------------------------------------------------------------------------
C0 0.10 Nugget - - - 165 65 95 3 1 2
Main C1 0.60 Exp 15 25 15 165 65 95 3 1 2
C2 0.30 Sph 200 600 150 165 65 95 3 1 2
----------------------------------------------------------------------------
C0 0.10 Nugget - - - 210 75 90 3 1 2
45 Trend C1 0.55 Exp 75 10 80 210 75 90 3 1 2
C2 0.35 Sph 80 150 85 210 75 90 3 1 2
----------------------------------------------------------------------------
C0 0.10 Nugget - - - 260 30 0 3 1 2
HW C1 0.70 Exp 35 10 35 260 30 0 3 1 2
C2 0.20 Sph 150 120 60 260 30 0 3 1 2
----------------------------------------------------------------------------
C0 0.10 Nugget - - - 165 65 95 3 1 2
External C1 0.60 Exp 15 25 15 165 65 95 3 1 2
C2 0.30 Sph 200 600 150 165 65 95 3 1 2
----------------------------------------------------------------------------
Source: SRK
(1) The rotation angles are shown in CAE Studio 3 convention


Table 8: Summary of Gold Estimation Search Parameters for the Main, 45 Trend, and HW Domains



----------------------------------------------------------------------------
Parameter 1st Pass 2nd Pass 3rd Pass
Element estimated Au Au Au
Interpolation method Ordinary kriging Ordinary kriging Ordinary kriging
Search range X 80% Var range 90% Var range 90% Var range
Search range Y 80% Var range 90% Var range 90% Var range
Search range Z 80% Var range 90% Var range 90% Var range
Minimum number of
composites 8 8 6
Maximum number of
composites 16 24 24
Octant search Yes Yes No
Minimum number of
octant 3 3 -
Minimum number of
composites per octant 3 3 -
Maximum number of
composites per octant 12 12 -
Maximum number of
composites per
borehole 5 5 5
----------------------------------------------------------------------------
Source: SRK


Table 9: Summary of Estimation Search Parameters for Gold in the External Domain



----------------------------------------------------------------------------
Parameter 1st Pass
Element estimated Au
Interpolation method Ordinary kriging
Search range X 95 m
Search range Y 290 m
Search range Z 75 m
Minimum number of composites 6
Maximum number of composites 24
Octant search No
Minimum number of octant -
Minimum number of composites per octant -
Maximum number of composites per octant -
Maximum number of composites per borehole 5
----------------------------------------------------------------------------
Source: SRK


The Toronto Stock Exchange has not reviewed and does not accept responsibility for the adequacy or accuracy of this release

Contacts:

Rubicon Minerals Corporation

Allan Candelario

Director of Investor Relations

+1 (416) 766-2804
ir@rubiconminerals.com
www.rubiconminerals.com


Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!



Mineninfo
Battle North Gold Corp.
Bergbau
-
-

Copyright © Minenportal.de 2006-2024 | MinenPortal.de ist eine Marke von GoldSeiten.de und Mitglied der GoldSeiten Mediengruppe
Alle Angaben ohne Gewähr! Es wird keinerlei Haftung für die Richtigkeit der Angaben und der Kurse übernommen!
Informationen zur Zeitverzögerung der Kursdaten und Börsenbedingungen. Kursdaten: Data Supplied by BSB-Software.