Centamin PLC: Q2 Preliminary Production Results
Open pit total material movement increased 1% on the previous quarter, to 9,861kt. Open pit ore production decreased by 23% on Q1 2014 to 1,795kt. The run of mine ore stockpile balance decreased by 400kt to 1,141kt at the end of the period. Discussions continue with government departments in relation to increasing the daily usage of ammonium nitrate in order to increase open pit mining rates to the required level to feed the expanded plant. Centamin believes government approval is in its final stages.
Record quarterly throughput at the process plant was 1,957kt, a 32% increase on Q1 2014, reflecting the commencement of ore treatment through the new Stage 4 plant circuit. Commissioning activities have proceeded well and continue to support a ramp-up to the expanded 10 million tonne per annum nameplate capacity during the second half of the year.
The underground operation delivered a record 230kt of ore, up 12% on Q1 2014 and in line with planned mining rates. Whilst grades realised from development ore were lower than the forecast annual average, good progress has been made accessing additional higher grade stoping blocks, and hence the average grade from the underground mine is expected to increase during the coming months.
Q2 2014 (estimate) Q1 2014 Q2 2013
Total Material Movement - Open Pit (kt) 9,861 9,749 11,020
Open Pit Ore Production (kt) 1,795 2,325 2,961
Underground Ore Production (kt) 230 206 142
Process Plant Throughput (kt) 1,957 1,486 1,419
Process Plant Productivity (tph) 1,230 745 699
Gold Produced (oz) 81,281 74,241 93,624
Josef El-Raghy, Chairman of Centamin, commented:
"Commissioning activities delivered the first material contribution from the Stage 4 plant expansion during the quarter, and the processing operation goes into the second half of the year at target productivity levels and on track to hit the expanded 10Mtpa nameplate capacity. Whilst underground development ore grades were below forecast, mining rates remain strong and the operation is on a solid footing having opened up key high-grade areas for stoping. Therefore, with both plant throughput and average grade set to materially increase during the remainder of the year, we maintain our full year production guidance of 420,000oz and continue to look forward to delivering Sukari's long-term target of 450,000-500,000 ounces per annum from 2015 onwards."
This information is provided by RNS
The company news service from the London Stock Exchange
For more information please contact:
Centamin plc
Josef El-Raghy, Chairman
Andy Davidson, Head of Business Development and Investor Relations
andy.davidson@centamin.je
+44 (0) 1534 828708
Buchanan
Bobby Morse / Gordon Poole
+ 44 (0) 20 7466 5000