• Montag, 22 Juli 2024
  • 21:29 Uhr Frankfurt
  • 20:29 Uhr London
  • 15:29 Uhr New York
  • 15:29 Uhr Toronto
  • 12:29 Uhr Vancouver
  • 05:29 Uhr Sydney

Allied Nevada Announces Hycroft Mill Expansion Feasibility Results Highlighted by Improved Projected Returns

15.10.2014  |  Marketwire

RENO, NEVADA--(Marketwired - Oct 15, 2014) - Allied Nevada Gold Corp. ("Allied Nevada", "us", "we", "our" or the "Company") (TSX:ANV) (NYSE MKT:ANV) is pleased to provide a summary of the Hycroft mill expansion feasibility study results, completed by M3 Engineering and Technology ("M3") in association with the Company. M3 developed the process flow sheet, capital cost estimate, operating cost estimate and financial model, while Allied Nevada developed the heap leach metrics, taxes, mineral reserves and mine plan. The feasibility study assumptions are largely the same as in the prefeasibility study issued in May, 2014, and continue to assume a two-phase construction plan for the mill expansion.

A summary of the significant changes from prefeasibility to feasibility are highlighted below. Consistent with the prefeasibility study, the base case metal price assumptions of $1,300 per ounce gold and $21.67 per ounce silver have been utilized in the feasibility study. The feasibility is presented on a January 1, 2015, go-forward basis and the comparative prefeasibility results have been adjusted to reflect the same start time. We intend to file a National Instrument 43-101 Technical Report within the 45-day regulatory timeframe.

A table is available at the following address: http://media3.marketwire.com/docs/973172a.pdf

Randy Buffington, President & CEO, stated, "this project is one of the only economic, permitted large projects in the gold space today and has the potential to become a significant, low-cost producer with a long reserve life and large open resource behind that."

Overview

The feasibility study is based on a nominal 120,000 ton per day ("tpd") mill for oxide, transition and sulfide ore and the associated heap leach for lower grade oxide and transition ore as presented in the prefeasibility study in May 2014. The mill is designed and scheduled to be constructed in two phases of 60,000 tpd each. Throughput varies based on ore hardness. The mill flow sheet components include crushing, grinding, flotation, concentrate regrind, concentrate oxidation and leaching, tails leaching, Merrill-Crowe extraction and refining. Our projections are based on detailed engineering, which we expect to begin in early 2015, and construction of Phase 1 anticipated commencing in the second quarter of 2015, subject to our ability to secure the necessary financing. Phase 1 is scheduled to be completed within 24 months, which would result in commissioning in the second quarter of 2017. The feasibility study projects commissioning of Phase 2 to be at the end of the second quarter of 2018, 12 months following completion of Phase 1.

The following summarizes feasibility LOM assumptions, compared with the same prefeasibility assumptions, for the mill expansion project:

LOM (2015-2033) Feasibility
(October 2014)
Prefeasibility
(May 2014; adjusted)
Total tons of ore processed (000s) - heap leach and mill 949,201 897,241
Grade - Au (ounces per ton) - heap leach and mill 0.011 0.011
Grade - Ag (ounces per ton) - heap leach and mill 0.49 0.50
Total gold ounces sold (000s) 7,437 7,122
Total silver ounces sold (000s) 340,111 326,419
Total gold equivalent ounces sold (000s) 13,106 12,562
Total revenue at $1,300/oz Au and $21.67/oz Ag (millions) $17,037 $16,332
Revenue per ton processed $17.95 $18.20
Mining cost per ton mined $1.37 $1.39
Milling cost per ton of ore milled $9.14 $8.83
Heap leach cost per ton of ore heap leached (includes crushing) $2.45 $2.47
G&A cost per ton of ore processed $0.32 $0.34
Nevada Net Proceeds Tax and refining cost per ton of ore processed $0.48 $0.47

Capital Estimate

The capital has increased to $1.39 billion (up $66 million) primarily resulting from the following: the change in construction of two 120kV power lines to one 345kV line to ensure reliable power availability; additional conveyors and crushed ore storage for the crushing/pre-crush and pebble crushing circuits; increased site general costs and confirmation of geotechnical analysis on required earthworks; and increased sizing for the thickener tanks. These increases were partially offset by a decrease in contingency reflecting the improved confidence level of the capital estimate with 88% of the estimated equipment capital costs now associated with vendor quotes.

Mining and processing

We completed an optimized mine plan that resulted in an additional 52 million ore tons that will be processed during the LOM and a reduced strip ratio of 1.50 (from 1.56). Mining unit costs have decreased slightly resulting from improved haul profiles and a reduction in mining equipment fleet requirements.

The process flow sheet has not changed and still considers a process plant capable of processing three streams: Mill 1 - whole ore; Mill 2 - Atmospheric Alkaline Oxidation ("AAO"); and Mill 3 - AAO with tails leach. A reevaluation of the economic benefit of processing an additional 440 million tons through the tails leach (Mill 3 scenario) as compared with the Mill 2 scenario resulted in additional overall ounces and improved economics.

Mill process costs did not change materially on a per unit basis. Total ton weighted costs increased $0.31/ton to $9.14/ton resulting from the processing of the additional 440 million tons through the Mill 3 scenario, which are more than offset by the revenue from additional ounces recovered. The 440 million tons were assumed to be processed through Mill 2 without the benefit of the additional recovery from tails leaching in the prefeasibility study.

GOLD SILVER
Contained Ounces
(000s)
Recovered Ounces (000s) Recovery (%) Contained Ounces
(000s)
Recovered Ounces
(000s)
Recovery (%)
Heap Leach 1,940 1,084 55.9 68,732 10,252 14.9
Mill stream 1 845 509 60.2 35,315 24,323 68.9
Mill stream 2 1,225 849 69.3 19,530 11,682 59.8
Mill stream 3 6,541 4,774 73.0 341,698 296,888 86.9
TOTAL 10,551 7,216 68.4 465,275 343,145 73.8

Recovered ounces differ in the table above as compared to the ounces sold in the life of mine economics. The table above shows the ounces placed and recovered on a going-forward basis only to calculate recovery. The life-of-mine model includes 266,000 recoverable ounces of gold and 2,127,000 ounces of recoverable silver in the heap leach inventory at January 1, 2015, and also accounts for ounce reductions due to melt loss and non-payable ounces from the refinery.

Economic Analysis

As noted above, the results of the revised prefeasibility study indicate an IRR projected to be 28.6% and a NPV projected to be $1.81 billion at a discount rate of 5%, assuming gold and silver prices of $1,300 per ounce and $21.67 per ounce, respectively, and based on the additional assumptions set forth in the table titled "Assumptions used in the feasibility study estimate" at the end of this press release. The initial capital to construct the mill and associated infrastructure is on a go-forward basis and does not include capital spent to date on the mill expansion such as the crushing system, Merrill-Crowe plant, mills, motors and excavation. The cash flow model considers the current heap leach revenue and costs as part of the project, which was developed by Allied Nevada.

The Hycroft mill expansion is projected to generate a significant amount of gold and silver at relatively low adjusted cash costs per ounce(4). The project, however, is extremely sensitive to metal prices. The following table illustrates the sensitivity of changes to calculated IRR and NPV(5) at 0% and 5% discount rates at various gold and silver prices and based on a constant ratio of the silver price to the gold price of 60:1. Additional sensitivity would result from changes to this ratio.

Metal Prices After tax NPV2(0%) After tax NPV2(5%) After tax IRR2
Au Ag Billions Billions %
$1,200 $20.00 $ 2.26 $ 1.16 19.5
$1,300 $21.67 $ 3.22 $ 1.81 28.6
$1,400 $23.33 $ 4.25 $ 2.48 38.5
(1). The term "adjusted cash costs per ounce" is a non-GAAP financial measure. Non-GAAP financial measures do not have any standardized meaning prescribed by GAAP and, therefore, should not be considered in isolation or as a substitute for measures of performance prepared in accordance with GAAP. See the section at the end of this press release and in the most recently filed Annual Report on Form 10-K titled "Non-GAAP Financial Measures" for further information on adjusted cash costs per ounce.
(2). No assurance or guarantee is provided that the calculated IRR or NPV values will be achieved. Actual results may differ materially.

Financing update

We continue to work with interested parties towards establishing a financing plan for the first phase of construction.

Conference Call Information

Allied Nevada will host a conference call to discuss the feasibility study results on October 16, 2014 at 8:00 am PT (11:00 am ET), which will be followed by a question and answer session. To listen in to the audio webcast, visit www.alliednevada.com.

To access the call, please dial:

Toll‐free in North America - 1‐866-233-4585

Outside of Canada & US - 1‐416-640-5946

An audio recording of the call will be archived on our website following the meeting.

Assumptions used in the feasibility study estimate:
Parameter Assumption Description
Mining years 16 years 150 million tons per year ("mtpy") by 2017, 200 mtpy by 2021
Processing years 19 years Last 3 years are from stockpiles
Inflation None - real basis All projected revenue and costs were assumed to be in January 1, 2015 real terms, with no inflation applied.
Starting basis January 1, 2015 go-forward All economic analyses were done on a January 1, 2015, "go-forward" basis.
Capital structure Unlevered No debt financing or interest payments were assumed.
Discount rate 5% real All the NPVs shown in this report were calculated using a discount rate of 5%. Sensitivity analysis has been completed for 0% and 10% discount rates.
Metal prices (base case) $1,300/oz Au, $21.67/oz Ag (60:1) Commodity prices were assumed to be constant over the DCF timeframe.
Refining charge $ 0.75 per Au and Ag oz Applied a refining charge of $0.50/oz and a deleterious elements charge of $0.25/oz.
Melt loss 0.5% Au and Ag Applied to account for melt losses during the refining process.
Payable metal 99.9% Au and 99.0% Ag Assumptions to arrive at payable metal are based on the current contract with Johnson Matthey.
Feasibility Study Economic Analysis Summary:
First 5 Years Average
(2018-2022)
Life of Project Average
(2018-2029)
LOM Totals
(2015-2033)
Production Information:
Total tons of ore processed - heap leach (000's) 12,945 8,710 213,032
Tons of ore processed - mill (000's) 44,238 45,108 736,169
Tons of waste mined (000's) 106,645 101,232 1,427,214
Total tons (000's) 163,828 156,050 2,376,415
Contained gold 603,818 614,664 10,550,586
Contained silver 29,516,518 28,838,685 465,274,777
Ounces sold - gold 458,737 447,866 7,437,167
Ounces sold - silver 22,956,625 23,209,316 340,110,809
Ounces sold - gold equivalent 841,347 834,688 13,105,681
Cash Flow Information:
Cash inflows:
Revenue from metal sales ($ 000's) 1,093,751 1,085,094 17,037,385
Cash outflows:
Operating costs ($ 000's) 710,149 675,225 11,552,453
Income taxes ($ 000's) 15,074 39,360 483,492
Inventory adjustments ($ 000's) 2,792 21,742 (283,746)
Reclamation spending & salvage ($ 000's) - - 77,413
Capital spending ($ 000's) 87,137 51,245 1,985,680
Total Cash Outflows ($ 000's) 815,152 787,572 13,815,292
Net Cash Flow ($ 000's) 278,599 297,522 3,222,093
After-tax NPV @ 5% ($ 000's) 1,807,961
After-tax NPV @ 10% ($ 000's) 1,017,763
After-tax Internal Rate of Return % 28.6
Adjusted cash costs per ounce(6) of gold sold:
With silver as byproduct credit ($ / Oz) $ 464 $ 385 $ 562
Gold equivalent ($ / Oz) $ 844 $ 809 $ 881
From a silver production and sales point of view:
Silver equivalent production (ounces Ag) 50,480,824 50,081,261 786,340,836
Adjusted cash costs with gold as a byproduct credit ($/silver ounce sold) $ 5 $ 4 $ 6
(1). The term "adjusted cash costs per ounce" is a non-GAAP financial measure. Non-GAAP financial measures do not have any standardized meaning prescribed by GAAP and, therefore, should not be considered in isolation or as a substitute for measures of performance prepared in accordance with GAAP. See the section at the end of this press release and in the most recently filed Annual Report on Form 10-K titled "Non-GAAP Financial Measures" for further information on adjusted cash costs per ounce.

Metal selling prices used in determining the economics for the project were $1,300 per ounce of gold and $21.67 per ounce of silver. Gold equivalent is calculated using a 60:1 silver to gold ounce ratio.
No assurance or guarantee is provided that the calculated IRR or NPV values will be achieved. Actual results may differ materially.

Cautionary Statement Regarding Forward Looking Information

This press release contains forward-looking statements within the meaning of Section 27A of the U.S. Securities Act of 1933, as amended (the "Securities Act"), Section 21E of the U.S. Securities Exchange Act of 1934, as amended (the"Exchange Act") (and the equivalent under Canadian securities laws) and the Private Securities Litigation Reform Act (the "PSLRA") or in releases made by the U.S. Securities and Exchange Commission (the "SEC"), all as may be amended from time to time. This cautionary statement is being made pursuant to the Securities Act, the Exchange Act and the PSLRA with the intention of obtaining the benefit of the "safe harbor" provisions of such laws.

All statements, other than statements of historical fact, included herein or incorporated by reference, that address activities, events or developments that we expect or anticipate will or may occur in the future, are forward-looking statements. Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as "estimate", "plan", "anticipate", "expect", "intend", "believe", "project", "target", "budget", "may", "can", "will", "would", "could", "should", "seeks", or "scheduled to", or other similar words, or negatives of these terms or other variations of these terms or comparable language or any discussion of strategy or intentions. Such forward-looking statements include, without limitation, statements regarding our future business strategy, plans and goals; future gold and silver prices; delays in processing gold and silver; the potential for confirming, upgrading and expanding gold and silver mineralized material at Hycroft; reserve and resource estimates and the timing of the release of updated estimates; estimates of gold and silver grades; future prices for gold and silver; recovery rates for gold and silver; anticipated operating, capital and construction costs, ; anticipated sales, project economics, net present values and expected rates of return; the realization of expansion and construction activities and the costs and timing thereof; availability and cost of financing; production estimates and other statements that are not historical facts.

Forward-looking statements address activities, events or developments that Allied Nevada expects or anticipates will or may occur in the future, and are based on current expectations and assumptions. These statements involve known and unknown risks, uncertainties, assumptions and other factors which may cause our actual results, performance or achievements to be materially different from any results, performance or achievements expressed or implied by such forward-looking statements. Important factors that could cause actual results, performance or achievements to differ materially from those in the forward-looking statements include, among others, risks that Allied Nevada's exploration and property advancement efforts will not be successful; risks relating to fluctuations in the price of gold and silver; an increase in the cost of or a delay or deferral timing of new projects, including construction or expansion projects; the inherently hazardous nature of mining-related activities; uncertainties concerning reserve, resource and grade estimates; uncertainties relating to obtaining approvals and permits from governmental regulatory authorities; and availability and timing of capital for financing the Company's exploration, development and expansion activities, including the uncertainty of being able to raise capital on favorable terms or at all; as well as those factors discussed in Allied Nevada's filings with the SEC including Allied Nevada's latest Annual Report on Form 10-K and its other SEC filings (and Canadian filings) including, without limitation, its latest Quarterly Report on Form 10-Q (which may be secured from us, either directly or from our website at www.alliednevada.com or at the SEC website www.sec.gov). Although Allied Nevada has attempted to identify important factors that could cause actual results, performance or achievements to differ materially from those described in forward-looking statements, there may be other factors that cause results, performance or achievements not to be as anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate, as actual results, performance and achievements and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements. The Company does not intend to publicly update any forward-looking statements, whether as a result of new information, future events, or otherwise, except as may be required under applicable securities laws.

The technical contents of this news release have been prepared under the supervision of Daniel Roth, Project Manager at M3 Engineering and Technology, and Tony Peterson, Corporate Mine Engineer at Allied Nevada Gold Corp., a Registered Professional Engineer in the State of Colorado #43867 who are Qualified Persons as defined by National Instrument 43-101. For further information regarding the quality assurance program and the quality control measures applied, as well as other relevant technical information, please see technical report titled "Hycroft Mine, NI 43-101 Technical Report, Mill Expansion Prefeasibility Study, Winnemucca, Nevada, USA" and dated May 21, 2014 on www.sedar.com.

Non-GAAP Financial Measure

Adjusted Cash Costs Per Ounce

Adjusted cash costs per ounce is a non-GAAP financial measure, calculated on a per ounce of gold sold basis, and includes all direct and indirect operating cash costs related to the physical activities of producing gold, including mining, processing, cash portions of production costs written-down, the effective portion of any cash flow hedges, third party refining expenses, on-site administrative and support costs, royalties, and mining production taxes, net of revenue earned from silver sales. Because we are a primary gold producer and our operations focus on maximizing profits and cash flows from the extraction and sale of gold, we believe that silver revenue is peripheral and not material to our key performance measures or our Hycroft Mine operating segment and, as such, adjusted cash costs per ounce is reduced by the benefit received from silver sales.

Adjusted cash costs per ounce provides management and investors with a further measure, in addition to conventional measures prepared in accordance with GAAP, to assess the performance of our mining operations and ability to generate cash flows over multiple periods from the sale of gold. Non-GAAP financial measures do not have any standardized meaning prescribed by GAAP and, therefore, may not be comparable to similar measures presented by other mining companies. Accordingly, the above measures are intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with GAAP.



Contact

Allied Nevada
Randy Buffington
President & CEO
(775) 358-4455
Allied Nevada
Tracey Thom
Vice President, Investor Relations
(775) 789-0119
www.alliednevada.com


Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!



Mineninfo
Hycroft Mining Holding Corp.
Bergbau
A2P7MN
US44862P1093

Copyright © Minenportal.de 2006-2024 | MinenPortal.de ist eine Marke von GoldSeiten.de und Mitglied der GoldSeiten Mediengruppe
Alle Angaben ohne Gewähr! Es wird keinerlei Haftung für die Richtigkeit der Angaben und der Kurse übernommen!
Informationen zur Zeitverzögerung der Kursdaten und Börsenbedingungen. Kursdaten: Data Supplied by BSB-Software.