• Donnerstag, 21 November 2024
  • 23:33 Uhr Frankfurt
  • 22:33 Uhr London
  • 17:33 Uhr New York
  • 17:33 Uhr Toronto
  • 14:33 Uhr Vancouver
  • 09:33 Uhr Sydney

Anfield Resources Inc. Reports Positive Preliminary Economic Assessment on Velvet-Wood Uranium Project in Utah

27.06.2016  |  The Newswire
  • ??Pre-tax IRR up to 41%

  • ??NPV of US$63.0 million at 8% discount rate and US$65/lb uranium

VANCOUVER, BRITISH COLUMBIA / TheNewsire / June 27, 2016 -- Anfield Resources Inc. (TSX.V: ARY) (FRANKFURT: 0AD)("Anfield" or "the Company"), is pleased to report the results of its Preliminary Economic Assessment ("PEA") with regard to the Velvet-Wood Uranium Project ("Velvet-Wood"). The independent PEA was prepared in accordance with National Instrument 43-101 standards of disclosure for mineral properties. Velvet-Wood, as discussed herein, consists of two mine areas, located in Lisbon Valley, Utah and the Shootaring Canyon Uranium Mill ("Shootaring Mill"), located in Ticaboo, Utah.

In the PEA, initial mineral processing will be via conventional vat or heap leaching methods conducted at Anfield's existing mineral processing facility, the Shootaring Mill, which lies approximately 180 miles from the Velvet-Wood mine area. Under this scenario, only those portions of the Shootaring Mill necessary for the final processing of pregnant leach solutions, from either a vat or heap leach facility, will be refurbished.

The project area covers approximately 2,425 acres, including unpatented mining claims and a State of Utah mineral lease related to the Velvet and Wood mine areas, and the Shootaring Mill.

Highlights include:

  • --Using a vat leaching recovery option, the PEA shows a pre-tax project Internal Rate of Return ("IRR") of 41% and a Net Present Value ("NPV") of US$63.0 million, based on a discount rate of 8% and a uranium price of US$65 per pound.

  • --Using a heap leaching recovery option, the PEA shows a pre-tax project Internal Rate of Return ("IRR") of 37% and a Net Present Value ("NPV") of US$53.5 million, based on a discount rate of 8% and a uranium price of US$65 per pound.

  • --Under both scenarios, average production would be approximately 663,000 pounds per annum, for total production of 4.6 million pounds over a seven-year mine life.

  • --Under both scenarios, total project capex is estimated at approximately US$46 million.

  • --Direct operating costs of $10.75 per pound of uranium via vat leach and $11.39 via heap leach have been estimated.

The PEA completed for Velvet-Wood has been authored by Douglas L. Beahm, P.E., P.G. Principal Engineer, of BRS Inc., Terence P. (Terry) McNulty, P.E., D. Sc., of T.P. McNulty and Associates Inc. The purpose of the PEA is to provide an independent analysis of the potential economic viability of the mineral resources of the project.

Anfield CEO, Corey Dias, stated, "Anfield continues to add shareholder value to its undervalued story. In the past eighteen months, we completed an NI 43-101 mineral resource estimate for the Velvet-Wood mine. The Velvet-Wood Mine, located in Lisbon Valley, Utah, includes one of the most advanced conventional uranium deposits in the U.S. The past-producing, licensed and permitted Velvet deposit and the Wood deposit both boast rich uranium resources and have significant exploration upside.

Today, we are extremely satisfied with the outcome of this preliminary economic assessment as it provides Anfield with evidence of the true potential of Velvet-Wood. Since our acquisition of Uranium One's conventional uranium assets, we have been keen to highlight the economic value of this mine and mill combination. This PEA not only represents a significant milestone for Anfield but also outlines a path towards commercial development of Velvet-Wood. Anfield is clearly well-positioned to benefit from an improving uranium market".

Velvet-Wood Mine

Between 1979 and 1984, Atlas Minerals mined approximately 400,000 tons of ore from the Velvet Deposit at grades of 0.46% U3O8 and 0.64% VO5, recovering approximately 4 million pounds of U3O8 and 5 million pounds of V2O5.

The current mineral resources of the combined Velvet and Wood mines have been estimated to comprise 4.6 million pounds of U3O8 at a grade of 0.29% U3O8 (measured and indicated resource) and 552,000 pounds of U3O8 at a grade of 0.32% U3O8 (inferred resource). (Source: Velvet-Wood Mine Uranium Project, San Juan County, Utah USA 43-101 Mineral Reserve and Resource Report, Author: BRS Inc.; Date: 11/14/2014).

The Shootaring Mill was licensed and constructed by Plateau Resources and operated in 1982 until the uranium price collapsed. U.S. Energy and Uranium One are also previous owners of the Shootaring Mill. The mill has not been decommissioned and has been under care and maintenance since cessation of operations.

Surface Stockpiles

In addition to the estimated mineral resource at Velvet-Wood, Anfield controls mineralized stockpiles from past mining at two locations: 1) one stockpile at the Patty Ann mine area near the Velvet mine; and 2) several stockpiles near the Shootaring mill. The volumes and uranium content of the stockpiles were estimated from volumetric surveys and sampling conducted by BRS in March, 2015. In total the stockpiles are estimated to contain approximately 126,090 tons of material at an average grade of 0.147% U3O8 and contain approximately 370,000 pounds of uranium. The surface stockpiles have been included as part of the feed available under both the heap and vat leach scenarios.

Project Economics - Vat Leach

The PEA provides for a two-year pre-production period. The first year's forecasted capital expenditures of $1.5 million include initial mill and mine permitting, along with vat facility design. The second year's capital expenditures, forecasted at $40.7 million (including a US$4.9 million contingency), include additional mine and mill permitting and licensing, mine engineering and design, mine facilities and equipment, plant and vat leach plant construction and engineering. Total capital for Life of Mine is estimated at $46.4 million.

Direct mine costs via vat leach for Velvet-Wood are estimated at $10.75 per pound, while total direct costs per pound of recovered uranium (including mine costs, haulage and handling, processing and other) are estimated at $29.01 per pound.

The PEA shows a return on investment with a pre-tax IRR ranging from 29% to 52% with uranium prices ranging from US$55 per pound to US$75 per pound. The NPV of the Project at an 8% discount rate ranges from US$37.3 million to US$88.9 million. After-tax IRR ranges between 24% and 43%, while after-tax NPV at an 8% discount rate ranges between US$25.3 million and US$64.5 million.

Project Economics - Heap Leach

The PEA provides for a two-year pre-production period. The first year's forecasted capital expenditures of $1.5 million include both initial mill and mine permitting, along with heap pad design. The second year's capital expenditures, forecasted at $40.9 million (including a US$4.9 million contingency), include additional mine and mill permitting and licensing, mine engineering and design, mine facilities and equipment, plant and heap leach construction and engineering. Total capital for Life of Mine is estimated at $46.6 million.

Direct mine costs via heap leach for Velvet-Wood are estimated at $11.39 per pound, while total direct costs (including mine costs, haulage and handling, processing and other) are estimated at $30.44 per pound.

The PEA shows a return on investment with a pre-tax IRR ranging from 25% to 48% with uranium prices ranging from US$55 per pound to US$75 per pound. The NPV of the Project at an 8% discount rate ranges from US$29.1 million to US$77.8 million. After-tax IRR ranges between 20% and 39%, while after-tax NPV at an 8% discount rate ranges between US$19.1 million and US$56.1 million.

Velvet-Wood Uranium Project economics at 8% discount rate and US$65 per pound uranium


Click Image To View Full Size

Source: Velvet-Wood PEA

NI 43-101 Disclosure

The PEA completed for Velvet-Wood has been authored by Douglas L. Beahm, P.E., P.G. Principal Engineer, of BRS Inc., Terence P. (Terry) McNulty, P.E., D. Sc., of T.P. McNulty and Associates Inc. The authors have reviewed and approved the technical content of this news release.

A technical report on the Preliminary Economic Assessment will be published on the System for Electronic Analysis and Retrieval ("SEDAR") and the Company's website within the 45 days permitted under NI 43-101.

Results of the PEA represent forward-looking information. This economic assessment is preliminary in nature and it includes inferred mineral resources that are considered too speculative, geologically, to have the economic considerations applies to them that would enable them to be categorized as mineral reserves. There is no certainty that the preliminary economic assessment will be realized. Conditions and parameters of the project are subject to change based on the final filing of the PEA on SEDAR within 45 days of this release. Mineral resources are not mineral reserves as they do not have demonstrated economic viability.

About Anfield Resources Inc.

Anfield is an energy metals exploration, development and near-term production company that is committed to becoming a top-tier energy-related fuels supplier by creating value through sustainable, efficient growth in its energy metals assets. Anfield is a publicly-traded corporation listed on the TSX-Venture Exchange (ARY-V) and the Frankfurt Stock Exchange (0AD).

On behalf of the Board of Directors

Anfield Resources Inc.

Corey Dias, Chief Executive Officer

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Contact:

Anfield Resources Inc.
Clive Mostert
Corporate Communications
780-920-5044
info@anfieldresources.com
www.anfieldresources.com

608, 1199 West Pender Street

Vancouver, BC V6E 2R1

Tel: (604) 687-0300

Fax: (604) 687-0151

Safe Harbor Statement

THIS NEWS RELEASE CONTAINS "FORWARD-LOOKING STATEMENTS". STATEMENTS IN THIS NEWS RELEASE THAT ARE NOT PURELY HISTORICAL ARE FORWARD-LOOKING STATEMENTS AND INCLUDE ANY STATEMENTS REGARDING BELIEFS, PLANS, EXPECTATIONS OR INTENTIONS REGARDING THE FUTURE.

EXCEPT FOR THE HISTORICAL INFORMATION PRESENTED HEREIN, MATTERS DISCUSSED IN THIS NEWS RELEASE CONTAIN FORWARD-LOOKING STATEMENTS THAT ARE SUBJECT TO CERTAIN RISKS AND UNCERTAINTIES THAT COULD CAUSE ACTUAL RESULTS TO DIFFER MATERIALLY FROM ANY FUTURE RESULTS, PERFORMANCE OR ACHIEVEMENTS EXPRESSED OR IMPLIED BY SUCH STATEMENTS. STATEMENTS THAT ARE NOT HISTORICAL FACTS, INCLUDING STATEMENTS THAT ARE PRECEDED BY, FOLLOWED BY, OR THAT INCLUDE SUCH WORDS AS "ESTIMATE," "ANTICIPATE," "BELIEVE," "PLAN" OR "EXPECT" OR SIMILAR STATEMENTS ARE FORWARD-LOOKING STATEMENTS. RISKS AND UNCERTAINTIES FOR THE COMPANY INCLUDE, BUT ARE NOT LIMITED TO, THE RISKS ASSOCIATED WITH MINERAL EXPLORATION AND FUNDING AS WELL AS THE RISKS SHOWN IN THE COMPANY'S MOST RECENT ANNUAL AND QUARTERLY REPORTS AND FROM TIME-TO-TIME IN OTHER PUBLICLY AVAILABLE INFORMATION REGARDING THE COMPANY. OTHER RISKS INCLUDE RISKS ASSOCIATED WITH SEEKING THE CAPITAL NECESSARY TO COMPLETE THE PROPOSED TRANSACTION, THE REGULATORY APPROVAL PROCESS, COMPETITIVE COMPANIES, FUTURE CAPITAL REQUIREMENTS AND THE COMPANY'S ABILITY AND LEVEL OF SUPPORT FOR ITS EXPLORATION AND DEVELOPMENT ACTIVITIES. THERE CAN BE NO ASSURANCE THAT THE COMPANY WILL BE ABLE TO COMPLETE THE PROPOSED TRANSACTION, THAT THE COMPANY'S EXPLORATION EFFORTS WILL SUCCEED OR THE COMPANY WILL ULTIMATELY ACHIEVE COMMERCIAL SUCCESS. THESE FORWARD-LOOKING STATEMENTS ARE MADE AS OF THE DATE OF THIS NEWS RELEASE, AND THE COMPANY ASSUMES NO OBLIGATION TO UPDATE THE FORWARD-LOOKING STATEMENTS, OR TO UPDATE THE REASONS WHY ACTUAL RESULTS COULD DIFFER FROM THOSE PROJECTED IN THE FORWARD-LOOKING STATEMENTS. ALTHOUGH THE COMPANY BELIEVES THAT THE BELIEFS, PLANS, EXPECTATIONS AND INTENTIONS CONTAINED IN THIS NEWS RELEASE ARE REASONABLE, THERE CAN BE NO ASSURANCE THOSE BELIEFS, PLANS, EXPECTATIONS OR INTENTIONS WILL PROVE TO BE ACCURATE. INVESTORS SHOULD CONSIDER ALL OF THE INFORMATION SET FORTH HEREIN AND SHOULD ALSO REFER TO THE RISK FACTORS DISCLOSED IN THE COMPANY'S PERIODIC REPORTS FILED FROM TIME-TO-TIME.

THIS NEWS RELEASE HAS BEEN PREPARED BY MANAGEMENT OF THE COMPANY WHO TAKES FULL RESPONSIBILITY FOR ITS CONTENTS.

Copyright (c) 2016 TheNewswire - All rights reserved.


Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!



Mineninfo
Anfield Energy Inc.
Bergbau
A2JSG9
CA03464C1068
Copyright © Minenportal.de 2006-2024 | MinenPortal.de ist eine Marke von GoldSeiten.de und Mitglied der GoldSeiten Mediengruppe
Alle Angaben ohne Gewähr! Es wird keinerlei Haftung für die Richtigkeit der Angaben und der Kurse übernommen!
Informationen zur Zeitverzögerung der Kursdaten und Börsenbedingungen. Kursdaten: Data Supplied by BSB-Software.