• Montag, 23 Dezember 2024
  • 06:29 Uhr Frankfurt
  • 05:29 Uhr London
  • 00:29 Uhr New York
  • 00:29 Uhr Toronto
  • 21:29 Uhr Vancouver
  • 16:29 Uhr Sydney

Katanga Mining Announces 2017 Second Quarter Production Results and Date for Release of 2017 Second Quarter Financial Results

26.07.2017  |  CNW

ZUG, Switzerland, July 26, 2017 /CNW/ - Katanga Mining Limited (TSX: KAT) ("Katanga" or the "Company") today announces its 2017 second quarter production results and date for release of 2017 second quarter financial results.

Highlights during the three and six months ended June 30, 2017, and Outlook







Three months ended

Six months ended



Jun 30,

Mar 31,

Jun 30,

Jun 30,



2017

2017

2016

2017

2016

Mining







Waste mined

tonnes

12,195,990

7,547,604

1,583,434

19,743,594

2,726,106

Ore mined

tonnes

-

-

-

-

-

Average copper grade

%

-

-

-

-

-

Contained copper in ore mined

tonnes

-

-

-

-

-

Processing







Ore milled

tonnes

342,562

348,045

-

690,608

-

Finished copper metal and concentrate to be fed into WOL

tonnes

2,396

2,484

-

4,880

-

Finished cobalt

tonnes

-

-

-

-

-

 

Ongoing suspension of production

  • On September 11, 2015, the Company announced the decision to suspend the processing of copper and cobalt during the construction phase of the Whole Ore Leach Project ("WOL Project"). The suspension continued through the first half of 2017 and production is not expected to resume until the WOL Project is commissioned, which is expected to commence in Q4 2017.
  • Mining operations continued during 2017 and 2016 at KOV and Mashamba East Open Pits with a focus on waste mining.

Mining

  • Waste mined in H1 2017 was 17,017,488 tonnes (624.2%) higher than in H1 2016 due to increased waste mining activities in 2017 in preparation for the commissioning of the WOL Project, which is expected to commence in Q4 2017;
  • There was no ore mined in H1 2017 and H1 2016 due to the revised waste mining plan (pre-strip) in the open pits which was put in place following the suspension of copper and cobalt processing at the end of Q3 2015. The revised waste mining plan aims to secure sufficient ore availability for processing once the suspension of copper and cobalt processing ends, while minimizing costs during the suspension period; and
  • In H1 2017, the Company commissioned:
    • 6 CAT 793 haul trucks at the KOV Open Pit mine.

Processing

  • Reprocessing of the Kamoto Interim Tailings Dam ("KITD") material commenced in January 2017. The concentrate produced is expected to be used to load the WOL Project commissioning circuits in Q4 2017. Concentrate produced from the KITD reprocessing amounted to 33,785 tonnes in H1 2017, with a copper grade of 14.44% (4,880 tonnes of contained copper).
  • During H1 2017 work continued on the WOL Project:
    • Significant progress continues on the 'Structural, Mechanical, Platework and Piping' (SMPP) activities on the acid tanks, Preleach, Leach and CCD trains. The Platework has been completed on all the phase 1 CCD's and the bridges are installed. The SCADA and control system Factory Acceptance Testing (FAT) is expected for the last week of July, following which the servers and PLC's (Programmable Logic Controller) are planned to be dispatched to site for installation. The final design packages and the 3D model were completed on June 17, 2017;
    • Related capital expenditures amounted to $69.5 million in H1 2017, which principally related to  installation of the SMPP, electrical, control and instrumentation equipment; and
    • Concurrent with the construction of the WOL Project plant and infrastructure, the current Life of Mine Plan continues to be optimized to ensure the appropriate blend will be supplied to the WOL process when complete in order to maximize copper and cobalt recovery and to minimize operating cost per unit.

Outlook

  • During Q3 2017:
    • Open pit mining operations are expected to continue with a focus on waste mining following the revised mine plan, which aims to secure sufficient ore availability for processing once the suspension of copper and cobalt processing ends, while minimizing costs during the suspension period;
    • Backfill operations at KTO are expected to continue to ensure underground stability;
    • Care and maintenance activities in the underground mine, KTC and Luilu are expected to continue;
    • Work is expected to continue on construction of Phase 1 of the WOL Project according to the defined project plan. Commissioning of the WOL Project is expected to commence in Q4 2017; and
    • Various initiatives relating to cost reductions, consumable inventory reductions, staff training and process improvements are expected to continue to be developed and implemented.

The Company expects to release its 2017 second quarter financial results on or about August 9, 2017.

This press release was prepared under the supervision of Tim Henderson, Technical Consultant and Director of Katanga and a "qualified person" as such term is defined in NI 43-101. Mr. Henderson has reviewed and approved the contents of this press release.

Unless otherwise specified, all $ amounts referred to in this press release are U.S. dollars.

About Katanga Mining Limited
Katanga Mining Ltd. operates a major mine complex in the Democratic Republic of Congo producing refined copper and cobalt. The Company has the potential to become Africa's largest copper producer and the world's largest cobalt producer. Katanga is listed on the Toronto Stock Exchange under the symbol KAT.

Forward Looking Statements
This press release may contain forward-looking statements, including, but not limited to, the ongoing suspension of copper and cobalt processing, the resumption of production following the commissioning of the WOL Project, installation and commissioning of various instrumentation and equipment related to the WOL Project, Open Pit waste mining activities, remediation activities, high-pressure backfill operations, care and maintenance activities, ongoing design optimization, construction and commissioning of the WOL Project, and other cost-base reduction initiatives, consumable inventory reductions, staff training and process improvements. Often, but not always, forward-looking statements can be identified by the use of words such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or describes a "goal", or variation of such words and phrases or state that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved.

All forward-looking statements reflect the Company's beliefs and assumptions based on information available at the time the statements were made. Actual results or events may differ from those predicted in these forward-looking statements. All of the Company's forward-looking statements are qualified by the assumptions that are stated or inherent in such forward-looking statements, including the assumptions listed below. Although the Company believes that these assumptions are reasonable, this list is not exhaustive of factors that may affect any of the forward-looking statements. The key assumptions that have been made in connection with the forward-looking statements include the following: the operations of the Company during the production suspension and timeline for the recommencement of operations remaining consistent with management's expectations, there being no significant disruptions affecting the operations of the Company whether due to labour disruptions, supply disruptions, power disruptions, rollout of new equipment, damage to equipment or otherwise; permitting, development, operations, expansion and acquisitions at the Project being consistent with the Company's current expectations; continued recognition of the Company's mining concessions and other assets, rights, titles and interests in the DRC; political and legal developments in the DRC being consistent with its current expectations; the continued provision or procurement of additional funding from Glencore for operations, the completion of the T17 Underground Mine, the WOL Project and the Power Project (as defined in the Annual Information Form of the Company for the year ended December 31, 2016 dated March 31, 2016); that new equipment performs to expectations; the exchange rate between the US dollar, South African rand, British pounds, Canadian dollar, Swiss franc, Congolese franc and Euro being approximately consistent with current levels; certain price assumptions for copper and cobalt; prices for diesel, natural gas, fuel oil, electricity and other key supplies being approximately consistent with current levels; production, operating expenses and cost of sales forecasts for the Company meeting expectations; the accuracy of the current ore reserve and mineral resource estimates of the Company (including but not limited to ore tonnage and ore grade estimates); and labour and material costs increasing on a basis consistent with the Company's current expectations.

Forward-looking statements involve known and unknown risks, future events, conditions, uncertainties and other factors which may cause the actual results, performance or achievements to be materially different from any future results, prediction, projection, forecast, performance or achievements expressed or implied by the forward-looking statements. Such factors include, among others, the unforeseen delays or changes to the WOL Project; actual results of current exploration activities; actual results and interpretation of current reclamation activities; conclusions of economic evaluations; changes in project parameters as plans continue to be refined; future prices of copper and cobalt; possible variations in ore grade or recovery rates; failure of plant, equipment or processes to operate as anticipated; accidents, labour disputes and other risks of the mining industry; delays in obtaining governmental approvals or financing or in the completion of exploration, development or construction activities, delays due to strikes or other work stoppage, both internal and external to the Company as well as those factors disclosed in the Company's current annual information form and other publicly filed documents. Although Katanga has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking statements, there may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements.

The Company disclaims any intention or obligation to update or revise any forward-looking statements whether as a result of new information, future events, or otherwise, except in accordance with applicable securities laws.

SOURCE Katanga Mining Ltd.



Contact
Johnny Blizzard, CEO, Tel: +41 (041) 766 71 10; Jacques Lubbe, CFO, Tel:+41 (041) 766 71 10
Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!



Mineninfo
Katanga Mining Ltd.
Bergbau
-
-
Copyright © Minenportal.de 2006-2024 | MinenPortal.de ist eine Marke von GoldSeiten.de und Mitglied der GoldSeiten Mediengruppe
Alle Angaben ohne Gewähr! Es wird keinerlei Haftung für die Richtigkeit der Angaben und der Kurse übernommen!
Informationen zur Zeitverzögerung der Kursdaten und Börsenbedingungen. Kursdaten: Data Supplied by BSB-Software.