Atalaya Mining PLC: Q3 Operations Update

12.10.2017  |  FSCwire

Nicosia, Cyprus (FSCwire) - Atalaya Mining plc (AIM:ATYM, TSX:AYM) is pleased to announce its operations update for the three months ended September 30, 2017.

PROYECTO RIOTINTO

 

Third Quarter

Second Quarter

Full year forecast

2017

2016

2017

2017

Ore mined

(M tonnes)

2.4

2.5

2.3

9.0 - 9.2

Waste mined

(M tonnes)

5.2

3.6

4.6

18.1 - 18.2

Ore milled

(M tonnes)

2.2

2.0

2.2

8.7 - 9.0

Cu grade

(%)

0.58

0.52

0.49

0.49 - 0.51

Cu recovery

(%)

85.95

83.60

85.09

82 - 84

Cu production

(tonnes)

10,679

8,752

9,058

36,000 - 39,000

 

Copper production at Proyecto Riotinto has increased almost 18 % to record production levels versus Q2. All other parameters were well above targets for the quarter ended September 30, 2017. The operation reported an average copper head grade of 0.58%, a throughput rate of 2.2 million tonnes of ore processed and a recovery rate of 85.95 %. Record production of 10,679 tonnes of copper contained in concentrate is the result of higher copper head grade and recovery rates than initially anticipated. Guidance for copper production has been adjusted accordingly and is now estimated to be within the range of 36,000 - 39,000 tonnes.

Mining operations are running at a consistent rate quarter-on-quarter, as a result of improved operational efficiencies and the availability of additional mining fleet. On a combined basis, ore, waste and marginal ore amounted to 2.7 Mm3 in Q3 2017 versus 2.8 Mm3 in Q2 2017. As part of the mining fleet replacement programme three new excavators and eight new trucks have been delivered, assembled and commissioned during the quarter. The processing plant was down for maintenance during the last five days of the quarter when relining of the primary mill and other maintenance activities were completed.

Contacts:

Newgate Communications

Charles Chichester / James Ash / James Browne

+44 20 7680 6550

Canaccord Genuity (NOMAD and Joint Broker)

Henry Fitzgerald-O'Connor / Martin Davison / James Asensio

+44 20 7523 8000

BMO Capital Markets (Joint Broker)

Jeffrey Couch/Neil Haycock/Tom Rider

+44 20 7236 1010

 

Click on, or paste the following link into your web browser, to view the associated PDF document.

http://www.rns-pdf.londonstockexchange.com/rns/3755T_1-2017-10-11.pdf

This information is provided by RNS

The company news service from the London Stock Exchange

END



To view this press release as a PDF file, click onto the following link:
public://news_release_pdf/Atalaya10122017_0.pdf

Source: Atalaya Mining plc (TSX:AYM, AIM:ATYM)

To follow Atalaya Mining plc on your favorite social media platform or financial websites, please click on the icons below.


Maximum News Dissemination by FSCwire. http://www.fscwire.com

Copyright © 2017 Filing Services Canada Inc.






Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!



Mineninfo
Atalaya Mining plc
Bergbau
A142QE
CY0106002112
Copyright © Minenportal.de 2006-2024 | MinenPortal.de ist eine Marke von GoldSeiten.de und Mitglied der GoldSeiten Mediengruppe
Alle Angaben ohne Gewähr! Es wird keinerlei Haftung für die Richtigkeit der Angaben und der Kurse übernommen!
Informationen zur Zeitverzögerung der Kursdaten und Börsenbedingungen. Kursdaten: Data Supplied by BSB-Software.