Deep Yellow Limited: December Quarterly Activities Report

16.01.2018  |  ABN Newswire
Perth - Deep Yellow Ltd. (ASX:DYL) (OTCMKTS:DYLLF) provides December Quarterly Activities Report.

In the December quarter work continued on the Namibian projects with a dual effort focussed on both uranium resource upgrade activities on the Reptile Project at Tumas 3 and completion of the first pass target drilling on selected exploration targets that have been identified on the Nova JV Project (see Figure 1 in link below).

HIGHLIGHTS

- Two drilling campaigns completed during quarter on adjacent Namibian projects with successful results.

- Reptile Project - Tumas 3 deposit extended from 4.4km to 7.2km with 1,878m of broad drilling on 400m x 100m spacing.

o drill assays indicate extension area will add to current Tumas 3 inferred resource base.

o work to date confirming high prospectivity of the 100km of palaeochannel remaining to be tested.

- Nova JV Project - first pass drilling targeting mineralisation associated with surficial palaeochannels and alaskite/skarn type basement rocks completed involving 7,490m of RC and diamond drilling.

o promising results on the newly defined Namaqua palaeochannel target (formerly Speke's East) where uranium mineralisation was intersected in three adjacent holes.

o majority of drillholes testing basement targets intersected narrow uranium mineralisation requiring follow-up investigations.

- Increased confidence that the existing uranium resource base of the Company for Langer Heinrich-style deposits can continue to be expanded.

To view the full report with figures, please visit:
http://abnnewswire.net/lnk/85A8EQ87



About Deep Yellow Limited:

Deep Yellow Ltd. (ASX:DYL) (OTCMKTS:DYLLF) is a specialist uranium company implementing a new strategy to grow shareholder wealth. This strategy is founded upon growing the existing uranium resources across the Company's uranium projects in Namibia and the pursuit of accretive, counter-cyclical acquisitions to build a geographically diverse asset portfolio.

In parallel to its expansion objectives, the Company has a cornerstone suite of projects in Namibia, a top-ranked African mining destination with a long, well regarded history of safely and effectively developing and regulating its considerable uranium mining industry.



Contact:

Deep Yellow Ltd.
John Borshoff Managing Director/CEO
T: +61-8-9286-6999
F: +61-8-9286-6969
Email: john.borshoff@deepyellow.com.au
www.deepyellow.com.au

Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!



Mineninfo
Deep Yellow Ltd.
Bergbau
481592
AU000000DYL4
Copyright © Minenportal.de 2006-2024 | MinenPortal.de ist eine Marke von GoldSeiten.de und Mitglied der GoldSeiten Mediengruppe
Alle Angaben ohne Gewähr! Es wird keinerlei Haftung für die Richtigkeit der Angaben und der Kurse übernommen!
Informationen zur Zeitverzögerung der Kursdaten und Börsenbedingungen. Kursdaten: Data Supplied by BSB-Software.