• Samstag, 23 November 2024
  • 05:00 Uhr Frankfurt
  • 04:00 Uhr London
  • 23:00 Uhr New York
  • 23:00 Uhr Toronto
  • 20:00 Uhr Vancouver
  • 15:00 Uhr Sydney

Marathon Gold Announces Substantial Improvements in Updated PEA with 44% Increase in Recovered Gold, at the Valentine Lake Gold Camp, Newfoundland

30.10.2018  |  GlobeNewswire

TORONTO, Oct. 30, 2018 - Marathon Gold Corp. (“Marathon” or the “Company”) (TSX: MOZ) is pleased to announce the excellent results from an updated independent Preliminary Economic Assessment study ("PEA") on its 100% owned Valentine Lake Gold Camp that was led by John T. Boyd Company and Lycopodium Minerals Canada. The new PEA optimizes the development of the Valentine Lake Gold Camp mineral resource by open pit mining, and gold recovery by a combination of a milling circuit and heap leaching, incorporating gravity and flotation circuits with leaching of the concentrate and tails. The study is based on an initial 12-year mine life and produced an after- tax Net Present Value (“NPV”) of $493 million using a 5% discount rate. The financial model shows an after- tax Internal Rate of Return ("IRR") of 30% and a capital payback period of 2.5 years. All dollar figures are reported in US$ and after-tax unless stated otherwise.

Valentine Lake Gold Camp Annual Gold Production


Production Schedule


NPV Sensitivity, Pre-Tax


IRR Sensitivity, Pre-Tax


Table 1 - PEA Summary

October 2018 May 2018 Change
Preproduction Capital $355 Million $380 Million -$25 Million
Pre-Tax NPV (5%) $834 Million $ 597 Million +$ 237 Million
Pre-Tax IRR 44% 34% +10%
After-Tax NPV (5%) $493 Million $367 Million +$126 Million
After- Tax IRR 30% 25% +5%
Pre-Tax Payback Period 1.7 years 2.3 years -0.6 years
After-Tax Payback Period 2.5 years 2.8 years -0.3 years
Mine Life 12.2 years 10.2 years +2 years
Recovered Gold Ounces 2,723,300 1,896,300 +827,000
Average Annual Production 225,100 ounces
(12-year average)
188,500 ounces
(10-year average)
+68,000 ounces
(12 year average)
LOM Average Cash Cost $603 per ounce $557 per ounce +$46 per ounce
LOM Average AISC –
All in Sustaining Costs
$666 per ounce $595 per ounce +$71 per ounce
Throughput (tonnes per day) –
Mill and Heap Leach
9,000 tpd and
9,000 tpd
7,500 tpd and
9,000 tpd
+1,500 tpd
to the mill
Mill Grade & Recovery 2.2 g/t / 95% 2.2 g/t / 95% -
Heap Leach Grade & Recovery 0.5 g/t / 59% 0.5 g/t / 53% +6% recovery
Initial Production 2022 2022
Gold Price $1,250 / oz Au $1,250 / oz Au
FX Rate (CDN$/US$) $0.769 $0.787 -$0.018

“This updated study has benefited from 20,000 meters of additional drilling since February 2018, 9,000 metallic screen assays on historical drill core since the last PEA resource, and an internal review of the project. For example, initial and sustaining capital costs have been cut by leasing the mining fleet instead of purchasing it. The very positive improvements in production and mine life are attributable to this year’s successful drilling program to extend the open pit resources at the Marathon Deposit, a major gold deposit that continues to grow thereby driving expansion of the project. Early near-surface higher grade resources with a low strip ratio at the Marathon Deposit enable high gold production in the early years of the operation and a fast payback of capital. The PEA has capitalized on several opportunities identified in the May 18, 2018 PEA, and there is still room for further improvements to the mine plan and economics for the 2019 Preliminary Feasibility Study.

“The metallurgical program to improve recoveries is in progress. 2018 Marathon Deposit drill results has substantiated a modeled extension of the open pit to the southwest, 2019 drilling will focus on drilling at both the Marathon and Sprite Deposits to attempt to expand the extended mineralization, and because of the short haul to the mill and heap leach pad. The Marathon Deposit has the potential to develop an underground mine but for now it is more cost effective to find open pit resources at $10 per new ounce rather than more costly underground resources,” said Phillip Walford, President and CEO of Marathon.

Figure 1 - Valentine Lake Gold Camp Annual Gold Production
http://www.globenewswire.com/NewsRoom/AttachmentNg/b1dab561-ed2e-4b11-9f2e-932ab6f07793

Description of the Valentine Lake Project and PEA

The PEA was developed by a team of independent consultants, including Lycopodium Minerals Canada Ltd. (“Lycopodium”), John T Boyd Company (“Boyd”), Apex Geoscience Ltd. and Stantec Consulting Ltd (“Stantec”).

The Valentine Lake Project (“The Project”) is composed of four deposits: Marathon, Leprechaun, Victory and Sprite. The mineral resource estimate was updated on October 9th, 2018 and the results are shown in Table 8. The Sprite Deposit was excluded from mine development planning until additional exploration drilling has increased the resource. For the Marathon, Leprechaun and Victory deposits, standard surface mining techniques will be utilized to develop three open pit mining areas.

The ultimate pit designs developed for the Valentine Lake Project are based on the results of Whittle pit optimization work. The three mining areas will be developed using a total of 17 distinct mining phases designed to approximate the optimal extraction sequence. Pit design parameters, such as wall slope angles and bench dimensions, were provided by Stantec. A mine production schedule for the entire complex was prepared by Boyd using Maptek’s Chronos scheduling software.

The Valentine Lake Project consists of two gold recovery operations: A Milling/Flotation/Carbon in Leach plant (“Mill”) and a Heap Leach plant. The Mill will process 3.0 Mtpa of high-grade mineralized material. The plant will consist of crushing, milling, gravity recovery, flotation of gravity tails, flotation concentrate regrind, cyanidation leaching of both flotation concentrate and flotation tailings via a CIL circuit, carbon elution and gold recovery circuit. CIL tails will be treated for cyanide destruction and disposed of as tails in the tailings storage facility.

The Heap Leach pad will process 3.0 Mtpa of low-grade mineralized material from open pit operations and will consist of crushing, heap leaching and carbon-in-column gold adsorption. The loaded carbon from the Heap Leach facility will be sent to the Mill facility for gold recovery.

Table 2 – Production Schedule
http://www.globenewswire.com/NewsRoom/AttachmentNg/f75203ee-de89-4d96-93b1-5550417e4e5d

Cashflow Analysis

The results of the discounted cash flow analysis are presented in Tables 3 and 4 below. NPV, IRR and payback values for the Project are estimated on a pre-tax and after-tax basis. The base case scenario assumes a long-term gold price of US$1,250 per ounce and a discount rate of 5%. The gold price sensitivity on a pre-tax and after-tax basis demonstrates the significant potential increase in the NPV and IRR of the Project should the gold price trade in a range of US$1,300 to US$1,350 per ounce.

Table 3 – Pre-tax Cashflow and NPV Gold Price Sensitivity

October May
2018 PEA 2018 PEA Improvement
Life of Mine Years 12.2 10.2
AISC – All in Sustaining Costs $/oz. $666 $595
Pre-tax Pay-back & Cashflow
Pay-back Cashflow Cashflow Change
Years US$ Million US$ Million US$ Million
Gold Price $1,200 1.9 $1,116.5 $774.6 $341.9
Gold Price $1,250 1.7 $1,252.7 $869.4 $383.2
Gold Price $1,300 1.5 $1,388.8 $964.3 $424.6
Gold Price $1,350 1.4 $1,525.0 $1,059.1 $465.9
Pre-tax IRR & NPV @ 5%
IRR NPV @ 5% NPV @ 5% Change
US$ CDN$ US$ Million
Gold Price $1,200 39% $731.4 $522.3 $209.1
Gold Price $1,250 44% $833.7 $596.8 $236.9
Gold Price $1,300 49% $936.1 $671.3 $264.8
Gold Price $1,350 54% $1,038.4 $745.8 $292.6

Table 4 – After-tax Cashflow and NPV Gold Price Sensitivity


October
2018 PEA
May
2018 PEA
Improvement
After-tax Pay-back & Cashflow
Pay-back Cashflow Cashflow Change

Years US$ Million US$ Million US$ Million
Gold Price $1,200 2.8 $691.3 $467.6 $223.7
Gold Price $1,250 2.5 $772.8 $562.5 $210.4
Gold Price $1,300 2.2 $854.3 $616.0 $238.3
Gold Price $1,350 2.0 $935.8 $671.8 $264.0
Post-tax IRR & NPV @ 5%
IRR NPV@5% NPV@5% Change
US$ Million US$ Million US$ Million
Gold Price $1,200 27% $ 431.9 $ 292.2 $ 139.7
Gold Price $1,250 30% $ 493.2 $ 366.7 $ 126.4
Gold Price $1,300 33% $ 554.4 $ 408.9 $ 145.5
Gold Price $1,350 36% $ 615.6 $ 452.7 $ 162.9

After-tax cash flows reflect the impact of the Newfoundland Mining Tax, calculated based on 15% of net income from mine operations and a combined Federal and Provincial income tax rate of 30%.

Operating Cost

The PEA estimates that the Project will produce approximately 2,723,000 ounces of gold during the life of the Project, or an average of 225,100 ounces per year for years 1 to 12.

Mine operating costs were calculated from first principles using vendor-supplied estimates and Boyd’s experience with similar mining operations. Fuel costs were calculated based on vendor-provided fuel consumption and a vendor quote for diesel of US$0.94/l. Over the life of the Project, overall mining operating costs, excluding rehandle, are estimated to be US$2.10/tonne of waste plus processed mineralized material or $14.45 per tonne of processed mineralized material. Mine operating costs increased by 27% compared to the May 2018 PEA due to increase in haul distance and an additional allowance for winter hauling conditions.

The process plant operating costs were developed by Lycopodium based on a design processing rate of 3.0 Mtpa of material for the milling circuit and 3.0 Mtpa of material for the heap leach circuit. Both circuits will normally operate 24 hours/day, and 365 days/year with 75% (6,570 hours/year) crushing plant availability and 91.3% plant utilization (nominal 8,000 hours/year operation). The process operating costs for the Project have been developed in detail according to typical industry standards applicable to gold ore processing plants.

The operating cost estimates are expressed in US$ in Q3 2018 terms and have an overall accuracy of +/-25%.

Contingency

No contingency was specified for the operating cost estimate as most costs were derived from first principles, based on metallurgical test work, reagent and consumable pricing, and industry standards.

Details of the estimated operating costs and other charges are presented in Table 5 below.

Table 5 – Operating Cost

Cost Centre Total Operating Cost Proportion of
Operating
Cost
US$/year US$/tonne
Mineralized
Material
Plant: Milling (1)
Operating Consumables (3) $22,368,000 $7.46 16.6%
Plant Maintenance $1,649,000 $0.55 1.2%
Power (4) $5,514,000 $1.84 4.1%
Laboratory $82,000 $0.03 0.1%
Labour (O & M) $3,444,000 $1.15 2.6%
Subtotal Milling $33,057,000 $11.02 24.5%
Plant: Heap Leach (2)
Operating Consumables $3,746,000 $1.25 2.8%
Plant Maintenance $788,000 $0.26 0.6%
Power $592,000 $0.20 0.4%
Laboratory $21,000 $0.01 0.0%
Labour (O & M) $2,899,000 $0.97 2.1%
Subtotal Heap Leach $8,046,000 $2.68 6.0%
Common
Labour (G & A) $1,000,000 $0.17 0.7%
G&A - Expenses $1,947,000 $0.32 1.4%
Plant Maintenance $686,000 $0.11 0.5%
Permanent Camp Catering $2,363,000 $0.39 1.8%
Permanent Camp Power $98,000 $0.02 0.1%
Subtotal Common Plant $6,094,000 $1.02 4.5%
Subtotal Plant Operating Cost $47,197,000 $7.87 35.0%


Mining
Average of years 1 to 12 $86,683,000 $14.45 64.2%
Subtotal Mine Operating Section Cost $86,683,000 $14.45 64.2%
Water Treatment Plant
Plant Maintenance $100,000 $0.02 0.1%
Labour (O & M) $237,000 $0.04 0.2%
Power $4,000 $0.00 0.0%
Others including power and Consumables $722,000 $0.12 0.5%
Subtotal Water Treatment Plant $1,063,000 $0.18 0.8%
Grand Total Operating Cost $134,942,000 $22.49 100.0%

Notes:

  1. $/t is based on mill throughput of 3.0 Mtpa.
  2. $/t is based on heap leach throughput of 3.0 Mtpa.
  3. Includes consumables for common elution, carbon regeneration & gold room areas.
  4. Includes power for elution and carbon regeneration of carbon from heap leach and mill, gold room, and mine surface loads
  5. Figures are rounded, and totals may not add correctly

Capital Cost

The capital cost estimate was based on an engineering, procurement and construction management (“EPCM”) implementation approach and typical construction contract packaging.

Equipment pricing was based on quotations and actual equipment costs from recent similar Lycopodium projects considered representative of the Project.

All costs are expressed in US$ unless otherwise stated and are based on the Q3 2018 pricing. The estimate is deemed to have an accuracy of +/- 35%. The capital cost estimate conforms to AACEI (Association for the Advancement of Cost Engineering International) Class 4 estimate standards as prescribed in recommended practice 47R11.

Contingency

Contingencies were applied to the capital cost estimate on a line-by-line basis as an allowance by assessing the level of confidence in the engineering, estimate basis and vendor or contractor information. The contingencies do not cover scope changes, design growth, or the listed qualifications and exclusions. The resultant contingency for the capital estimate is 15% before taxes and duties.

Table 6 – Capital Estimate Summary by Area

Area Total Inc. Project Contingency
USD
Construction Indirects $ 21,257,000
Treatment Plant Costs - Heap Leach Circuit $ 47,626,000
Treatment Plant Costs - Milling Circuit $ 92,739,000
Reagents & Plant Services - Heap Leach Circuit $ 4,030,000
Reagents & Plant Services - Milling Circuit $ 21,355,000
Infrastructure $ 73,192,000
Mining Equipment (Leased) and Facilities $ 39,108,000
Mining Preproduction $ 17,123,000
Management Costs $ 22,434,000
Owners Project Costs $ 16,440,000
Total Capex $ 355,303,000

Sensitivities

As indicated in Figures 2 and 3 and Table 7, project cashflow and NPV are particularly sensitive to changes in the price of gold and operating costs, while relatively less sensitive to changes in recovery and capital expenditures. The table below shows the effect on the pre-tax economics of the Project increasing or decreasing the price of gold, closure costs and mill and heap leach recovery estimates by up to +/- 10%. Capital and operating costs were varied by +/-35%.

Figure 2 – NPV Sensitivity, Pre-Tax
http://www.globenewswire.com/NewsRoom/AttachmentNg/d411e0c4-d254-4b9f-bdb0-46725bbb4f92

Figure 3 – IRR Sensitivity, Pre-Tax
http://www.globenewswire.com/NewsRoom/AttachmentNg/6d0c861a-52aa-45d9-bbaf-a505e79541db

Table 7 – Sensitivities, Pre-Tax

Gold Price NPV IRR Payback
(Years)
-10 % $ 577,820,000 32 % 2.40
0 % $ 833,706,000 44 % 1.68
10 % $ 1,089,591,000 56 % 1.34
CAPEX NPV IRR Payback
(Years)
-35 % $ 996,492,000 80 % 0.92
0 % $ 833,706,000 44 % 1.68
35 % $ 670,920,000 28 % 3.00
OPEX NPV IRR Payback
(Years)
-35 % $ 1,267,486,000 64 % 1.24
0 % $ 833,706,000 44 % 1.68
35 % $ 399,925,000 24 % 3.27
Mill Recovery NPV IRR Payback
(Years)
-2 % $ 788,963,000 42 % 1.76
0 % $ 833,706,000 44 % 1.68
2 % $ 878,449,000 46 % 1.61

Heap Leach
Recovery
NPV IRR Payback
(Years)
-10 % $ 801,905,000 43 % 1.72
0 % $ 833,706,000 44 % 1.68
10 % $ 865,506,000 45 % 1.65
Closure Costs NPV IRR Payback
(Years)
-10 % $ 835,773,000 44 % 1.68
0 % $ 833,706,000 44 % 1.68
10 % $ 831,639,000 44 % 1.69

Opportunities for Project Enhancement

The PEA identified several areas where additional work will advance the Project and reduce risk. The major focus of the work planned for 2019 is summarized below:

  • The drilling program at the Marathon Deposit will involve step-out drilling to expand open pit resource along strike to the southwest and infill drilling to reduce inferred resources in the pit shell. Exploration drilling at the Sprite Deposit with continue to extend the mineralized zone northeast towards the Marathon Deposit.
  • The underground resource has not been utilized in the PEA. Infill drilling will improve the continuity of the underground mineralization. This could contribute an additional ounces to be extracted using underground mining methods.
  • Additional hydrogeological and geotechnical work will enable better open pit and underground designs.
  • Extensive metallurgical testing for the mill and the heap leach started in September 2018 at SGS-Lakefield. Early results from crushed ore bottle role (COBR) and column tests are encouraging and confirm results of test work conducted by Thibault & Associates in 2015 and 2016. The results of the test work by SGS may improve recoveries and will be included in the pre-feasibility study scheduled for 2019.
  • Options such as high-pressure grinding rolls (“HPGR”) ahead of the heap leach and a coarser grind in the mill could also have the potential to reduce operating costs.
  • Ongoing engineering studies and permitting will continue to de-risk the Project in the future. A Pre-Feasibility is scheduled to be completed in 2019. This work will include a detailed permitting plan which includes environmental work for an Environmental Assessment study.

Mineral Resource Estimate October 30, 2018

The project resources have increased from the previous PEA, May 18, 2019 as a result of 20,000 m of additional drilling and as a result of the addition of 9,000 metallic screen assays that are used for better measurement of coarse gold which is common on the property. Overall, all classes of resource increased significantly.

The Measured and Indicated resource tonnes increased by 35% to 45,146,000 tonnes, the grade declined by 7% to 1.854 grams per tonne and the total contained ounces Au increased by 26% to 2,691,400 ounces Au. The Inferred resource tonnes increased by 55 % to 26,856,000 tonnes, the grade decreased by 11% to 1.774 and the contained ounces Au increased by 30% to 1,531,600 ounces Au.

The slight decline in grade is not attributed to any one factor. There is a slight decrease in the bottom cut for heap leach material, there is slight reduction in the variography of the higher-grade material and we are adding slight lower grade material on the fringes of the Marathon deposit.

The increase in Inferred resource is coming from infill holes at the Marathon Deposit and step out holes to the southwest of the Marathon Deposit which are extending the resource towards the Sprite Deposit.

Additional drilling in 2019 will focus on extending the higher-grade zones in the pit shells as well as infilling open material to move Inferred resources into Indicated and Measured resources.

Table 8 - Mineral Resource Estimate

Material/
Category
Open Pit Underground Total
Tonnes Grade Gold Tonnes Grade Gold Tonnes Grade Gold
(t) (g/t) (oz) (t) (g/t) (oz) (t) (g/t) (oz)
Leprechaun Deposit
Measured 5,760,000 2.381 440,800 81,000 3.910 10,200 5,841,000 2.402 451,000
Indicated 3,010,000 1.916 185,500 64,000 3.460 7,100 3,074,000 1.949 192,600
M+I 8,770,000 2.221 626,300 145,000 3.711 17,300 8,915,000 2.246 643,600
Inferred 7,533,000 1.476 357,400 388,000 4.274 53,300 7,921,000 1.613 410,700
Sprite Deposit
Measured 0 0.000 0 0 0.000 0 0 0.000 0
Indicated 708,000 1.703 38,800 9,000 2.403 700 717,000 1.712 39,500
M+I 708,000 1.703 38,800 9,000 2.403 700 717,000 1.712 39,500
Inferred 1,291,000 1.173 48,700 46,000 2.702 4,000 1,337,000 1.226 52,700
Marathon Deposit
Measured 10,637,000 1.985 679,000 142,000 7.990 36,500 10,779,000 2.064 715,500
Indicated 23,211,000 1.559 1,163,700 513,000 4.797 79,100 23,724,000 1.629 1,242,800
M+I 33,848,000 1.693 1,842,700 655,000 5.489 115,600 34,503,000 1.765 1,958,300
Inferred 13,784,000 1.693 750,100 1,839,000 3.862 228,300 15,623,000 1.948 978,400
Victory Deposit
Measured 0 0.000 0 0 0.000 0 0 0.000 0
Indicated 1,009,000 1.537 49,900 2,000 1.848 100 1,011,000 1.538 50,000
M+I 1,009,000 1.537 49,900 2,000 1.848 100 1,011,000 1.538 50,000
Inferred 1,821,000 1.264 74,000 155,000 3.174 15,800 1,976,000 1.414 89,800
All Deposits
Measured 16,397,000 2.124 1,119,800 223,000 6.508 46,700 16,620,000 2.183 1,166,500
Indicated 27,938,000 1.601 1,437,900 588,000 4.605 87,000 28,526,000 1.663 1,524,900
M+I 44,335,000 1.794 2,557,700 811,000 5.128 133,700 45,146,000 1.854 2,691,400
Inferred 24,429,000 1.566 1,230,200 2,428,000 3.862 301,400 26,857,000 1.774 1,531,600

Notes:

1. The effective date for this mineral resource estimate for Sprite, and Victory is November 27, 2017 and is reported on a 100% ownership basis. The effective date for the mineral resource estimate for Marathon is October 9, 2018. The effective date for the mineral resource estimate for Leprechaun Pond is October 5, 2018. The resources have been restated using the updated PEA economics. All material tonnes and gold values are undiluted.

  1. Mineral Resources are calculated at a gold price of US$1,250 per troy ounce.
  1. The open pit mineral resources presented above use an economic pit shell to determine material available for open pit mining. The underground mineral resources are that material outside of the in-pit mineral resources above the stated underground cutoff grade.
  1. Mineral resources which are not mineral reserves do not have demonstrated economic viability. The estimate of mineral resources may be materially affected by environmental, permitting, legal, title, socio-political, marketing, or other relevant issues.
  1. The mineral resources presented here were estimated using a block model with a block size of 6 m by 6 m by 6 m sub-blocked to a minimum block size of 2 m by 2 m by 2 m using ID3 methods for grade estimation. Mineral resources for the Leprechaun and Sprite deposits are reported using an open pit gold cut-off of 0.281 g/t Au and an underground gold cut-off of 1.767 g/t Au. Material between a 0.281 Au g/t value and 1.142 Au g/t is assumed to be processed on a heap leach. Material above a 1.142 Au g/t is assumed to be processed in a mill. Higher gold grades were given a limited area of influence which was applied during grade estimation by mineralized domain. Mineral resources for the Marathon and Victory deposits are reported using an open pit gold cut-off of 0.328 g/t Au and an underground gold cut-off of 1.731 g/t Au. Material between a 0.328 Au g/t value and 0.700 Au g/t is assumed to be processed on a heap leach. Material above a 0.700 Au g/t is assumed to be processed in a mill. Higher gold grades were given a limited area of influence which was applied during grade estimation by mineralized domain.
  1. The mineral resources presented here were estimated using the Canadian Institute of Mining, Metallurgy and Petroleum (CIM), CIM Standards on Mineral Resources and Reserves, Definitions and Guidelines prepared by the CIM Standing Committee on Reserve Definitions and adopted by CIM Council May 10, 2014.
  1. Figures are rounded, and totals may not add correctly.

Report Filing

The technical report prepared in accordance with National Instrument 43-101 will be filed on SEDAR and the Company’s website within two weeks of this news release.

Qualified Persons

This news release has been reviewed and approved by the Qualified Persons noted below. The Qualified Persons have reviewed or verified all information for which they are individually responsible, including sampling, analytical, and test results underlying the information or opinions contained herein.

  • Neil Lincoln, P.Eng. - Lycopodium Minerals Canada Ltd.: processing, infrastructure, capital and operating cost estimates, economic evaluation and report compilation.
  • Robert Farmer, P.Eng. - John T Boyd Company: mineral resource estimates, mining methods, mining capital and mining operating costs.
  • Roy Eccles, P.Geo. - Apex Geoscience Ltd.: geology, exploration, drilling, sample preparation and data verification.
  • Paul Deering, P.Eng. - Stantec Consulting Ltd. – environmental & social studies, geotechnical, tailings storage facility and heap leach pad design.

Cautionary Statement

The PEA was prepared in accordance with National Instrument 43-101 Standards of Disclosure for Mineral Projects ("NI 43-101"). Readers are cautioned that the PEA is preliminary in nature. It includes inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves, and there is no certainty that the PEA will be realized. Mineral resources that are not mineral reserves do not have demonstrated economic viability.

Conference Call Details

Marathon Gold is hosting a Management Information Call on Tuesday, October 30,2018 at 10:00 am Eastern time (11:30 pm Newfoundland time and 7:00 am Pacific time) with the Marathon Gold executive team to discuss the results of the PEA and the way forward.

Participants:
Toll-free dial-in number (Canada/US): 1-800-952-5114
Local dial-in number: 416-641-6104
International dial-in numbers: https://www.confsolutions.ca/ILT?oss=7P1R8009525114
Participant passcode: 3598476#

About Marathon

Marathon is a Toronto based gold exploration company rapidly advancing its 100% owned Valentine Lake Gold Camp located in Newfoundland, one of the top mining jurisdictions in the world. The Valentine Lake Gold Camp currently hosts four near-surface, mainly pit-shell constrained, deposits with measured and indicated resources totaling 2,691,400 oz. of gold at 1.85 g/t and inferred resources totaling 1,531,600 oz. of gold at 1.77 g/t. The majority of the resources occur in the Marathon and Leprechaun deposits, which also have resources below the pit shell. Both deposits are open to depth and on strike. Gold mineralization has been traced down over 350 metres vertically at Leprechaun and almost a kilometer at Marathon. The four deposits outlined to date occur over a 20-kilometer system of gold bearing veins, with much of the 24,000-hectare property having had little detailed exploration activity to date.

The Valentine Lake Gold Camp is accessible by year-round road and is located in close proximity to Newfoundland’s electrical grid. Marathon maintains a 50-person all-season camp at the property. Recent metallurgical tests have demonstrated 93% to 98% recoveries via conventional milling and 50% to 70% recoveries via low cost heap leaching at both the Leprechaun and Marathon Deposits.

To find out more information on the Valentine Lake Gold Camp please visit www.marathon-gold.com.

For more information, please contact:
Christopher Haldane
Investor Relations Manager
Tel: 1-416-987-0714
E-mail: chaldane@marathon-gold.com
Phillip Walford
President and Chief Executive Officer
Tel: 1-416-987-0711
E-mail: pwalford@marathon-gold.com


CAUTIONARY STATEMENT REGARDING FORWARD-LOOKING INFORMATION

Except for statements of historical fact relating to Marathon Gold Corp., certain information contained herein constitutes "forward-looking statements". Forward-looking statements include statements that are predictive in nature, depend upon or refer to future events or conditions, or include words such as "expects", "anticipates", "plans", "believes", "considers", "intends", "targets", or negative versions thereof and other similar expressions, or future or conditional verbs such as "may", "will", "should", "would" and "could". We provide forward-looking statements for the purpose of conveying information about our current expectations and plans relating to the future and readers are cautioned that such statements may not be appropriate for other purposes. By its nature, this information is subject to inherent risks and uncertainties that may be general or specific and which give rise to the possibility that expectations, forecasts, predictions, projections or conclusions will not prove to be accurate, that assumptions may not be correct, and that objectives, strategic goals and priorities will not be achieved. These risks and uncertainties include but are not limited to those identified and reported in Marathon Gold Corp.'s public filings, which may be accessed at www.sedar.com. Other than as specifically required by law, we undertake no obligation to update any forward-looking statement to reflect events or circumstances after the date on which such statement is made, or to reflect the occurrence of unanticipated events, whether as a result of new information, future events, results or otherwise.


Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!



Mineninfo
Marathon Gold Corp.
Bergbau
-
-
Copyright © Minenportal.de 2006-2024 | MinenPortal.de ist eine Marke von GoldSeiten.de und Mitglied der GoldSeiten Mediengruppe
Alle Angaben ohne Gewähr! Es wird keinerlei Haftung für die Richtigkeit der Angaben und der Kurse übernommen!
Informationen zur Zeitverzögerung der Kursdaten und Börsenbedingungen. Kursdaten: Data Supplied by BSB-Software.