September 2018 Quarterly Report

30.10.2018  |  Accesswire

SUBIACO, October 30, 2018 - Gold developer West African ResourcesLimited (ASX, TSXV: WAF) is pleased to report progress on its Sanbrado GoldProject ("Sanbrado"), Burkina Faso, for the quarter ending 30 September 2018.

Highlights

M1 South DiamondDrilling

High-grade results fromstep down and infill drilling at M1 South include:

  • TAN18-DD214A: 0.5m at 520 g/t Au from 578m
  • TAN18-DD214A: 23m at 7.3 g/t Au from 617m including 4m at 24.4 g/t Au
  • TAN18-DD189-WD1: 10m at 8.1 g/t Au from 646.5m, including 0.5m at 61.7 g/t Au
  • TAN18-DD196-WD2: 10.5m at 8.8 g/t Au from 648m, including 0.5m at 138 g/t Au
  • TAN18-DD214A-WD1: 21.5m at 15.3 g/t Au from 614m, including 0.5m at 115 g/t Au
  • TAN18-DD214A-WD2: 14.5m at 19.9 g/t Au from 595.5m, including 1m at 219 g/t Au

Parallel high-grade zone at M1South intercepted 300m below surface, 180m east of main zone include:

  • TAN18-DD189-WD2: 2m at 138.4 g/t Au from 449m
  • TAN18-DD189: 5.5m at 15.5 g/t Au from 452.5m including 1.5m at 48.3 g/t Au
  • TAN18-DD214A-WD2: 8m at 6.0 g/t Au from 396m, including 1m at 30.0 g/t Au

Corporate Summary

  • Updated mining permit awarded for Sanbrado
  • Chief Development Officer appointed for Sanbrado construction
  • Strong interest received from debt financiers to fund construction, with non-binding debt offers ranging from US$160m to US$215m
  • Updated Feasibility Study NI 43-101 report filed on SEDAR
  • Presented at Diggers & Dealers conference Kalgoorlie, Precious Metals Summit and Denver Gold Forum Colorado USA

September 2018 Quarter Summary

  • 8,047.5m from 16 diamond holes and wedges drilled
  • $7.0m exploration and development expenditure
  • $0.6m administration costs
  • $35.4m cash at bank, no debt at 30 September 2018

December 2018 Quarter Plans

  • 1,000m diamond core hole targeting ultra high-grade shoot extension 200m below M1 South
  • Further key hires for WAF owners team for Sanbrado build
  • Commencement of early works, including box cut and UG portal development at M1 South
  • Further results infill and step-out drilling from M1 South and M5
  • Award of EPCM contract and mill order
  • Appointment of debt financier or syndicate for Sanbrado build

Click here to view the activitiesreport

Click here to view the cashflowreport

SOURCE: West African Resources Ltd.


Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!



Mineninfo
West African Resources Ltd.
Bergbau
A1CZBT
AU000000WAF6
Copyright © Minenportal.de 2006-2024 | MinenPortal.de ist eine Marke von GoldSeiten.de und Mitglied der GoldSeiten Mediengruppe
Alle Angaben ohne Gewähr! Es wird keinerlei Haftung für die Richtigkeit der Angaben und der Kurse übernommen!
Informationen zur Zeitverzögerung der Kursdaten und Börsenbedingungen. Kursdaten: Data Supplied by BSB-Software.