• Sonntag, 22 Dezember 2024
  • 16:05 Uhr Frankfurt
  • 15:05 Uhr London
  • 10:05 Uhr New York
  • 10:05 Uhr Toronto
  • 07:05 Uhr Vancouver
  • 02:05 Uhr Sydney

Alphamin Resources Corp.: Bisie Tin Project Development Update

01.03.2019  |  GlobeNewswire
GRAND BAIE, March 01, 2019 - Alphamin Resources Corp. (AFM: TSXV, “Alphamin”, or the “Company”) is pleased to announce an update to the development status of its flagship tin project in the DRC.

The processing plant front-end crushing circuit commissioning has been completed and has run at nameplate capacity of sixty tonnes per hour. To date, some six thousand, five hundred tons of ore has been crushed and stockpiled for feeding into the gravity separation circuit.

Cold commissioning on the gravity concentration section has also commenced and is progressing well.

In connection with the previously announced change of mining method to a cut and fill method, a detailed mine schedule for 2019 and 2020 has been received. Production of ore from the cut and fill stoping operation has now commenced. A life of mine schedule is expected during Q2 2019 following which the Company plans to update its NI 43-101 and announce updated project economics. Initial analysis indicates the unit costs per ton will be higher in 2019 and 2020 than had been anticipated in the Company’s most recent feasibility study.

Full commissioning and ramp up is scheduled to occur during Q2 2019. Production at planned through put is planned to commence in Q3, 2019.

The Company has reviewed the working capital requirements to achieve planned production volumes . The current cashflow projections indicate a likely short term working capital shortfall. Factors impacting the projected working capital shortfall include a delayed response to a request to partially export concentrates by airfreight, requiring the company to truck all export material, which has impacted delivery times and related revenue receipts; a delay in VAT refunds and the delayed manufacture and delivery of certain components to finalise plant commisioning. In addition to this, the change in the mining method has resulted in a slower ramp up of material to the ROM stockpile.

The Company estimates that up to $9m may be required to bridge this expected working capital deficit and enables the Company to acquire certain sustaining capital and critical spares.

Management considers it prudent to seek a working capital facility of up to US$12m, which exceeds the projected shortfall of $9m but provides a buffer for any additional unforseen events or challenges. The Company is in discussion with its lenders to provide this facility.

FOR MORE INFORMATION, PLEASE CONTACT:

Boris Kamstra
Chief Executive Officer
Alphamin Resources Corp.
Tel: +230 269 4166
E-mail: boris.kamstra@alphaminresources.com
Grand Baie, Mauritius

CAUTION REGARDING FORWARD LOOKING STATEMENTS

Information in this news release that is not a statement of historical fact constitutes forward-looking information. Forward-looking statements contained herein include, without limitation, statements relating to the terms and intended completion of the Private Placement, the anticipated use of funds from the Private Placement, the anticipated additional debt drawdown, the participation of the IDC and other stakeholders, costs of production, success of mining operations, the ranking of the project in terms of cash cost and production, economic return estimates, social, community and environmental impacts, and continued positive discussions and relationships with local communities and stakeholders. Forward-looking statements are based on assumptions management believes to be reasonable at the time such statements are made. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements. Although Alphamin has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking statements, there may be other factors that cause results not to be as anticipated, estimated or intended. Factors that may cause actual results to differ materially from expected results described in forward-looking statements include, but are not limited to: Alphamin’s ability to secure sufficient financing to advance and complete the Project, uncertainties associated with Alphamin’s resource and reserve estimates, uncertainties regarding global supply and demand for tin and market and sales prices, uncertainties associated with securing off-take agreements and customer contracts, uncertainties with respect to social, community and environmental impacts, adverse political events, uncertainties with respect to optimization opportunities for the Project, as well as those risk factors set out in the Company’s Management Discussion and Analysis and other disclosure documents available under the Company’s profile at www.sedar.com. Forward-looking statements contained herein are made as of the date of this news release and Alphamin disclaims any obligation to update any forward-looking statements, whether as a result of new information, future events or results or otherwise, except as required by applicable securities laws.

Neither the TSX Venture Exchange nor its regulation services provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this news release.

Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!



Mineninfo
Alphamin Resources Corp.
Bergbau
A12GSG
MU0456S00006
Copyright © Minenportal.de 2006-2024 | MinenPortal.de ist eine Marke von GoldSeiten.de und Mitglied der GoldSeiten Mediengruppe
Alle Angaben ohne Gewähr! Es wird keinerlei Haftung für die Richtigkeit der Angaben und der Kurse übernommen!
Informationen zur Zeitverzögerung der Kursdaten und Börsenbedingungen. Kursdaten: Data Supplied by BSB-Software.