• Freitag, 22 November 2024
  • 14:20 Uhr Frankfurt
  • 13:20 Uhr London
  • 08:20 Uhr New York
  • 08:20 Uhr Toronto
  • 05:20 Uhr Vancouver
  • 00:20 Uhr Sydney

Monument Announces Readiness of Selinsing Gold Plant Conversion

03.03.2019  |  GlobeNewswire

VANCOUVER, March 03, 2019 - Monument Mining Ltd. (TSX-V: MMY and FSE: D7Q1) (“Monument” or the “Company”) is pleased to announce the readiness of the Gold Plant conversion at the Selinsing Gold Mine in Malaysia, following up the recent positive Feasibility Study (Snowden 2019 NI43-101 Technical Report, refer to the News Release dated February 1, 2019) that has established the economic viability of the Selinsing Sulphide Project for a six year life of mine through the extension of the existing oxide plant to include flotation and BIOX® circuits for sulphide ore treatment.

General Manager Charlie Northfield commented, “Our operation team is excited to be moving forward with transition from Oxide Gold Production to Sulphide Gold Production at our Selinsing Gold Mine. Construction readiness is progressing well according to the Execution Plan. Our primary focus is to ensure that construction could start as soon as funding is available, and we could fast track construction and meet designed operation protocols while operation risks are well controlled.”

Progress of Readiness Work

Readiness work includes procurement, workforce planning, design of the pilot plant for operator training and inoculum build-up, operation manual preparation and TSF development.

Procurement: Technical and financial appraisal of critical flotation and BIOX® equipment has continued subsequent to the Snowden 2019 Feasibility Study. Dialogue with potential equipment suppliers has enabled critical long lead equipment to be identified; these include the flotation cells, agitators, thickeners, blowers, cooling towers and pumps. Preparation of procurement documentation has been initiated on site to minimize any administrative delays.

Potential suppliers of steel plate and structural steel worldwide have been located and price comparisons are being compiled. Suitable fabrication workshops within Peninsular Malaysia have also been contacted.

Workforce: The workforce planning and action plan has been submitted to the management for review and approval. Key positions have been identified for hiring.

Metallurgical technicians are currently being trained for controlling the flotation process and bioleach process in terms of parameters and critical aspects of running flotation and BIOX® plant, such as monitoring ORP (oxidation reduction potential), pH, DO (dissolved oxygen) and temperature. Scale-up commercial test work at the pilot plant is continuing as an aid to technician skills development.

Documentation: Documentation control systems are being investigated to determine their suitability for implementation during the sulphide plant construction phase.

Scaled up testwork: For training purpose, locally sourced bacteria are being used to test certain Buffalo Reef ore concentrates. The testwork to date shows encouraging results where CIL recovery was increased to 85% on post bioleach residue from 35%. The bacteria species used are similar to Outotec BIOX® bacteria but not identical. Further concentrate from each individual ore type will be collected according to final flotation parameters for further bioleach testwork and other concentrate characteristics testwork through the pilot plant.

Tailings Storage Facility: Detailed design of the expanded tailings storage facility was received from SRK Consulting in late 2018. Construction of the main embankment foundations has progressed well and the construction of finger drains overlying the existing downstream embankment was carried out according to the design. Engineered fill from Selinsing and Buffalo Reef pit cutbacks is hauled to the tailings storage facility and compacted to the specifications provided by SRK. Independent testing of the compacted fill is being conducted by a local geotechnical services company.

Current Open Pit Gold Mining Operations

Mining operation at Selinsing has been enhanced by recruitment of a new mining manager, who has over 20 years’ experience in Australia and South East Asia. This is to facilitate a planned production transition from oxide to sulphide ore sources including the restart of open pit operations at Buffalo Reef. In the meantime the mining and processing of transition material from the Selinsing pits has continued with good recoveries achieved in the oxide plant.

About Monument

Monument Mining Ltd. (TSX-V: MMY, FSE: D7Q1) is an established Canadian gold producer that owns and operates the Selinsing Gold Mine in Malaysia. Its experienced management team is committed to growth and is advancing several exploration and development projects including the Mengapur Copper-Iron Project, in Pahang State of Malaysia, and the Murchison Gold Projects comprising Burnakura, Gabanintha and Tuckanarra in the Murchison area of Western Australia. The Company employs approximately 195 people in both regions and is committed to the highest standards of environmental management, social responsibility, and health and safety for its employees and neighboring communities.

Cathy Zhai, President and CEO
Monument Mining Ltd.
Suite 1580 -1100 Melville Street
Vancouver, BC V6E 4A6

FOR FURTHER INFORMATION visit the company web site at www.monumentmining.com or contact:

Richard Cushing, MMY Vancouver
T: +1-604-638-1661 x102
rcushing@monumentmining.com

Wolfgang Seybold, Axino GmbH
T: +49 711-82 09 7211
wolfgang.seybold@axino.com

"Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release."

Forward-Looking Statement

This news release includes statements containing forward-looking information about Monument, its business and future plans (“forward-looking statements”). Forward-looking statements are statements that involve expectations, plans, objectives or future events that are not historical facts and include the Company’s plans with respect to its mineral projects and the timing and results of proposed programs and events referred to in this news release. Generally, forward-looking information can be identified by the use of forward-looking terminology such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or variations of such words and phrases or state that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved". The forward-looking statements in this news release are subject to various risks, uncertainties and other factors that could cause actual results or achievements to differ materially from those expressed or implied by the forward-looking statements. These risks and certain other factors include, without limitation: risks related to general business, economic, competitive, geopolitical and social uncertainties; uncertainties regarding the results of current exploration activities; uncertainties in the progress and timing of development activities; foreign operations risks; other risks inherent in the mining industry and other risks described in the management discussion and analysis of the Company and the technical reports on the Company’s projects, all of which are available under the profile of the Company on SEDAR at www.sedar.com. Material factors and assumptions used to develop forward-looking statements in this news release include: expectations regarding the estimated cash cost per ounce of gold production and the estimated cash flows which may be generated from the operations, general economic factors and other factors that may be beyond the control of Monument; assumptions and expectations regarding the results of exploration on the Company’s projects; assumptions regarding the future price of gold of other minerals; the timing and amount of estimated future production; the expected timing and results of development and exploration activities; costs of future activities; capital and operating expenditures; success of exploration activities; mining or processing issues; exchange rates; and all of the factors and assumptions described in the management discussion and analysis of the Company and the technical reports on the Company’s projects, all of which are available under the profile of the Company on SEDAR at www.sedar.com. Although the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking statements, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements. The Company does not undertake to update any forward-looking statements, except in accordance with applicable securities laws.


Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!



Mineninfo
Monument Mining Ltd.
Bergbau
A0MSJR
CA61531Y1051
Copyright © Minenportal.de 2006-2024 | MinenPortal.de ist eine Marke von GoldSeiten.de und Mitglied der GoldSeiten Mediengruppe
Alle Angaben ohne Gewähr! Es wird keinerlei Haftung für die Richtigkeit der Angaben und der Kurse übernommen!
Informationen zur Zeitverzögerung der Kursdaten und Börsenbedingungen. Kursdaten: Data Supplied by BSB-Software.