• Montag, 25 November 2024
  • 03:25 Uhr Frankfurt
  • 02:25 Uhr London
  • 21:25 Uhr New York
  • 21:25 Uhr Toronto
  • 18:25 Uhr Vancouver
  • 13:25 Uhr Sydney

Heron Resources Limited: Woodlawn Zinc-Copper Project Update

12.03.2019  |  GlobeNewswire
  • First underground development ore delivered to ROM pad (shallow G2HW lens resource)
  • Underground development advance exceeding plan
  • Hydraulic mining commissioning well advanced
  • Overall process plant completion at 98% end February
  • Process plant commissioning at 63% end February
  • First concentrate production now scheduled for early Quarter 2

SYDNEY, March 12, 2019 - Heron Resources Ltd. (“Heron” or “the Company”) is pleased to provide the market with an update on its Woodlawn Zinc-Copper Project as it continues towards its production milestone.

Underground Mining Operations


First underground production - G2 HW accessed 10 March 2019. (Rock fragment is 15cm across, and is made up of high-grade banded zinc and lead sulphides with minor copper sulphides present).


Underground Monthly Development Advance


Initial slot development on Tailing Dam South.


Tailings thickener undergoing wet commissioning.


Concentrate container handler.


ICP installed on-site assay laboratory (self-contained assay capability).


Underground Mine

The underground operation has made steady progress with 913m of development completed to date (Figure 1). On 10 March 2019 development reached the shallow G2HW lens with the ore being delivered to the process plant ROM pad in readiness for processing. This represents the first underground production from the mine (see Figure 2).

Monthly development meterage has steadily ramped up since the start of underground operations in September 2018 and is now exceeding budget levels (Figure 3). Ground conditions remain as expected with no significant adverse areas. A specialist contractor is now established on site to construct a 5m diameter raise to setup the primary ventilation for the underground.

Hydraulic Mining

The hydraulic mining circuit commissioning is well advanced and ready for full production once the process plant is available. Final hand-over of the plant is in progress and expected to be complete in the coming months after a final performance test. Operator training, production readiness and ramp-up continues under the guidance of Paragon Tailings. Initial tailing mining to the base of the dam has demonstrated an extremely good level of control that provides high confidence in achieving (and possibly bettering) planned material recovery (tonnage) and dilution assumptions which underpin Ore Reserve calculations. Good progress is being made in removing a thin low-grade cap on Tailing Dam South. This cap removal project was identified by Heron’s process team and is expected to improve processing performance and recoveries.

Figure 1 http://www.globenewswire.com/NewsRoom/AttachmentNg/a9e5ff47-c4f6-43ff-8be9-ba7ba8b644e4

Figure 2 http://www.globenewswire.com/NewsRoom/AttachmentNg/6ca052d3-ef7a-403c-9b91-26725e598499

Figure 3 http://www.globenewswire.com/NewsRoom/AttachmentNg/9494012d-874f-40f2-b849-aa037abd7af0

Figure 4 http://www.globenewswire.com/NewsRoom/AttachmentNg/cadf92c7-336c-46b3-bf42-f57077d840ca

Project EPC Works: As previously announced (Process Plant Wet Commissioning Commences at Woodlawn, March 4, 2019) the Company is fast approaching the end of the project development process. Heron’s EPC contractor, Sedgman Pty Ltd, a wholly owned CIMIC Group Limited company report the Project as being 98% complete at the end of February and commissioning at 63%. Site construction activity has reduced and workforce numbers have followed accordingly. The EPC Contractor personnel are progressing Woodlawn through the wet commissioning stage to be followed by ore commissioning, ramp-up and performance testing.

Figure 5 http://www.globenewswire.com/NewsRoom/AttachmentNg/5939b258-041a-4f60-80d8-54686beae640

Operational readiness: The Company has essentially completed recruitment of operational and commissioning staff with a handful of specialist roles being covered by contractors. Supply activities are nearing completion with the store fit-out and receipt of reagents, consumables and maintenance spares to support the operations. Mobile plant (Figure 6) is operational and concentrate logistics are ready. The newly constructed site assay laboratory (Figure 7) is operational and the water treatment plant is complete with commissioning being in its final stages.

Figure 6 http://www.globenewswire.com/NewsRoom/AttachmentNg/f324b043-f1fc-4051-9b1b-8e6a93a6f101

Figure 7 http://www.globenewswire.com/NewsRoom/AttachmentNg/ca92ab8e-4c87-4fb7-8b12-3acab11c920e

Project Development Schedule: At the start of March, Heron was advised by Sedgman that the anticipated date for first ore to be fed to the process plant will be delayed. After seeking clarification on the extent of the delay, the Company now expects the start to ore processing to commence early in the second quarter with first concentrates ready for shipment in May.

Managing Director Wayne Taylor said, “Heron has been very committed to delivering on dates at every milestone of the Woodlawn Project development. As announced on March 4 2019, feeding ore through the plant is the only remaining step in commissioning the project and once completed Heron will transition to becoming Australia’s newest producer of base metal concentrates. We are naturally disappointed by this delay to our development timeline and remain committed to reaching our production milestone with our on-site team continuing to prepare for this.”

About Heron Resources Limited (ASX:HRR)

Heron Resources Ltd. (ASX:HRR) is engaged in the exploration and development of base and precious metal deposits in Australia. The Company’s primary focus is on its 100% owned, high grade Woodlawn Zinc-Copper Project located 250km southwest of Sydney, New South Wales, Australia with production due in early 2019. In addition, the Company has a number of significant high quality, base and precious metal tenements regional to the Woodlawn Project.


For further information, please visit www.heronresources.com.au or contact:
Mr. Wayne Taylor, Managing Director and Chief Executive Officer Tel: +61 2 9119 8111
Email: heron@heronresources.com.au

Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!



Mineninfo
Heron Resources Ltd.
Bergbau
-
-
Copyright © Minenportal.de 2006-2024 | MinenPortal.de ist eine Marke von GoldSeiten.de und Mitglied der GoldSeiten Mediengruppe
Alle Angaben ohne Gewähr! Es wird keinerlei Haftung für die Richtigkeit der Angaben und der Kurse übernommen!
Informationen zur Zeitverzögerung der Kursdaten und Börsenbedingungen. Kursdaten: Data Supplied by BSB-Software.