Northisle Copper and Gold Inc. Announces Significant Improvement in Gold and Copper Recoveries

01.09.2020  |  CNW
Highlights
  • The recently completed metallurgical tests improved the copper and gold recovery rates at the Hushamu Deposit by an average of 17% and 24% respectively, compared to the tests forming the bases for estimates used in the previously published PEA
  • Metallurgical tests also demonstrate potential to recover silver and rhenium metal content, which was previously excluded from the PEA economics
  • Similar metallurgical tests are underway for the nearby Red Dog Deposit
  • The previously published PEA is being updated to include upside potential related to higher gold and copper recovery rates, higher metal prices, and the inclusion of silver and rhenium metal recovery


VANCOUVER, Sept. 1, 2020 - Northisle Copper and Gold Inc. (TSXV: NCX) ("Northisle" or the "Company") is pleased to report that preliminary metallurgical test results demonstrate a significant improvement in recoveries of copper and gold for the Hushamu Deposit at its 100%-owned North Island Project located in British Columbia, Canada.

The test work was designed to investigate alternative flotation parameters to improve the recovery rates of copper and gold in the two mineralization types in the Hushamu Deposit. The results demonstrate that the average copper and gold recovery rates improved by 17% and 24% respectively, compared to tests used for the Preliminary Economic Assessment ("PEA") published in September 2017.

In addition, the metallurgical test work included assaying and evaluating the recoveries of rhenium and silver which were not included in earlier test work and in the PEA economics. Results demonstrate rhenium recoveries of 66.1% and 29.3% into the low pyrite mineralization concentrate ("CMG") and the high pyrite mineralization concentrate ("SCP) respectively, and silver content in the low pyrite mineralization concentrate of 29.3 g/t and 18.0 g/t in the high pyrite mineralization concentrate ("SCP").

Following the successful metallurgical results obtained for the Hushamu Deposit, a similar program is underway for the nearby Red Dog Deposit. Once these studies are completed, Northisle expects to update the PEA to incorporate upside potential related to the expected higher gold and copper recovery rates, inclusion of silver and rhenium metal recovery, and higher metal prices.

John McClintock, President and CEO stated: "These results are very positive as they are expected to significantly improve the economics of our North Island Project. Given this success, we are excited about currently underway metallurgical testing on the nearby Red Dog Deposit. Once these studies are completed, we are eager to update our PEA to reflect the upside potential of higher copper and gold recovery rates, inclusion of silver and rhenium metal recovery, and higher metal prices."

TEST PROGRAM DETAILS

The metallurgical test program was completed by SGS Canada Inc. (SGS) at their laboratory facility in Burnaby, BC. The test work was done on two approximately 100kg composites samples of core; one of the SCP and the other of CMG mineralization. The CMG composite came from drill holesH08-08, H12-03, H12-10, H12-12, H14-05 and H17-01 while the SCP sample came from drill holes H17-01 and H-08-08. The samples comprising the composites represent a range of high and lower grade mineralization. The results of the lock cycle tests for the two mineralization types are presented in the table below. For comparison, the results of the lock cycle tests used for the PEA are presented in Table 2. The composites for the earlier metallurgical work were prepared from core samples from H14-05.

Detailed test work included: sample preparation, QEMSCAN analysis, sample characterization, batch rougher batch cleaner and lock cycle test work. Modifications to the original flotation conditions of the 2016 work included, finer primary grind, a single stage regrind of the rougher concentrate, new reagent scheme and a three stage cleaner circuit.

The results of the metallurgical tests demonstrated that the copper recoveries of low pyrite mineralization improved to 86.6% from 74.5% and to 87.9% from 75.0% in the high pyrite mineralization. Gold recoveries in the low pyrite mineralization improved to 50.6% from 43.7% and to 46.4% from 34.4% in the high pyrite mineralization.

Table 1: SGS Labs Results Lockcycle Tests


Calculated Feed grade
(% or gpt)

PG (um)

Concentrate grade (% or gpt)

Recovery %


Cu

Au

Mo

Ag

Re


Cu

Au

Mo

Ag

Re

Cu

Au

Mo

Ag

Re

SCP

0.33

0.38

0.01

0.56

0.38

76

22.9

13.6

0.18

18.0

8.7

87.9

46.4

26.8

40.9

29.3

CMG

0.31

0.33

0.01

0.77

0.4

76

23.8

14.9

0.48

29.3

23.5

86.6

50.8

69.4

43.1

66.1

Table 2: 2016 Base Met Lockcycle Tests


Calculated Feed grade
(% or gpt)

PG (um)

Concentrate grade (% or gpt)

Recovery %


Cu

Au

Mo

Ag

Re

100

Cu

Au

Mo

Ag

Re

Cu

Au

Mo

Ag

Re

SCP

0.31

0.36

.014

na

na

100

19.0

10.1

0.78

na

na

75.0

34.4

69.8

na

na

CMG

0.25

0.28

0.009

na

na

100

22.0

14.4

0.41

na

na

74.5

43.7

37.6

na

na

ABOUT THE NORTH ISLAND PROJECT

The 100%-owned North Island Project consists of the Hushamu and nearby Red Dog deposits, with Mineral Resources summarized in the below table.

Table 3: North Island Project Resources as at December 31, 2018


Tonnes,
'000

Grade

Contained Metal

Cu, %

Au, g/t

Mo, %

Re, ppm

Cu Eq, %

Cu, B lb

Au, Moz

Mo, M lb

Re, Kg x 1000

Cu eq, B lb

Au eq, Moz

Red Dog













Indicated

36,568

0.27

0.38

0.005


0.52

0.22

0.45

4.0


0.42

0.99

Inferred

1,774

0.20

0.30

0.003


0.39

0.01

0.02

0.1


0.02

0.04

Hushamu













Indicated

305,180

0.24

0.28

0.008

0.54

0.43

1.62

2.75

53.8

165

2.92

6.97

Inferred

189,640

0.19

0.24

0.007

0.35

0.36

0.79

1.46

29.3

66

1.49

3.56

Total













Indicated

341,743

0.24

0.29

0.008

0.48

0.44

1.83

3.2

57.8

165

3.34

7.96

Inferred

190,788

0.19

0.24

0.007

0.35

0.36

0.80

1.48

29.4

66

1.51

3.60

Mineral Resource estimates follow the Canadian Institute of Mining, Metallurgy and Petroleum ("CIM") definitions standards for Mineral Resources and Reserves and have been completed in accordance with the Standards of Disclosure for Mineral Projects as defined by National Instrument 43-101. The NI 43-101 reports co-authored by P Burt PGeo and B Game PGeo documenting the resource estimate available on the company's website and filed on SEDAR. Reported tonnage and grade figures have been rounded from raw estimates to reflect the relative accuracy of the estimate. Minor variations may occur during the addition of rounded numbers. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. Copper and gold equivalent calculated using US$3.10/lb Cu, US$1300/oz Au and US$9.00/lb Mo and is not adjusted for mining and metallurgical recoveries as these remain uncertain. The formula used is as follows: CuEQ = (Cu% x 22.0462 x 3.10) + (Au g/t x 1300.00/ 31.1035) + (Mo% x 22.0462 x 9.00)/22.046x3.1. AuEQ =(Cu% x 22.0462 x 3.10) + (Au g/t x 1300.00/ 31.1035) + (Mo% x 22.0462 x 9.00)/(1300/31.1035). Rhenium values have not been used in the cut-off grade or Cu or gold Equivalent calculations.

In September 2017, Northisle published the results of a PEA which demonstrated the potential technical and economic viability of the project constructed as an open-pit mine, with a concentrator processing nominally 75,000 tonnes/day (27Mtpa) with the results summarized in the below table. This PEA is expected to be updated to reflect the results from the metallurgical tests described in the sections above.

Table 4: North Island Project PEA Summary

LIFE OF MINE PHYSICALS





Mine life, years

22 years




Strip ratio, w:o

0.72




Throughput

27.4Mtpa




Resource inventory tonnes

460Mt

140Mt



Category

Indicated

Inferred



Copper grade

0.18%

0.14%



Gold grade

0.24g/t

0.25%



Molybdenum grade

0.01%

0.10%



Pyrite grade

9%

9%



LOM production





Copper

1.9B lb




Gold

1.8Moz




Molybdenum

55M lb




Pyrite

17B lb




Copper equivalent, M lb pa

3.1B lb




Gold equivalent, koz

7.4Moz




AVERAGE ANNUAL PRODUCTION





Copper, M lb

82M lb




Gold, koz

79koz




Molybdenum, M lb

3M lb




Pyrite, kt

0.64Kt




Copper equivalent, M lb

141M lb




Gold equivalent, koz

335koz




AVERAGE ANNUAL PRODUCTION COSTS





Copper C1 Cash Costs net of by-products, US$/lb

$0.88/lb




Copper AISC net of by-products, US$/lb

$1.22/lb




Copper equivalent AISC, US$/lb Cu eq

$2.00/lb




Gold equivalent AISC, US$/oz Au eq

$840/oz




ECONOMICS





After-tax NPV5%, US$m

$757m




After-tax NPV8%, US$m

$413m




After-tax IRR, %

14%




The commodity prices used are as follows: US$ 3.10/lb Cu, US$ 1,300/oz Au, US$ 9.00/lb Mo, US$ 9/t Py with a CAD/USD of 0.75. For more information, please consult the 2017 PEA available on SEDAR under the Company's profile or on Northisle's website.

For more information on Northisle please visit the Company's website at www.Northisle.ca.

John McClintock, P. Eng is the Qualified Person who reviewed and approved the scientific and technical disclosure in this news release.

On behalf of Northisle Copper and Gold Inc.

"John McClintock"

John McClintock, P. Eng
President, CEO and Director
www.northisle.ca

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this news release.

This news release contains forward-looking statements. These forward-looking statements are based upon the reasonable beliefs of Northisle and its management as of the date of this news release; however, forward-looking statements involve risks and uncertainties and are based upon factors that may change and assumptions that may prove, with the passage of time, to be incorrect as a result of exploration and other risk factors associated with mineral exploration and development that are beyond the control of Northisle. Accordingly, undue reliance should not be placed upon such statements. If factors materially change or assumptions are materially incorrect, the actual results, performance or achievements of Northisle may be materially different from any future results, performances or achievements expressed or implied by such forward-looking statements. Northisle does not undertake any obligation to update or revise any forward-looking statements to reflect new information, future events or otherwise, except as required by applicable law.

SOURCE Northisle Copper and Gold Inc.

Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!



Mineninfo
Northisle Copper and Gold Inc.
Bergbau
A1JMCQ
CA66644R1038
Copyright © Minenportal.de 2006-2024 | MinenPortal.de ist eine Marke von GoldSeiten.de und Mitglied der GoldSeiten Mediengruppe
Alle Angaben ohne Gewähr! Es wird keinerlei Haftung für die Richtigkeit der Angaben und der Kurse übernommen!
Informationen zur Zeitverzögerung der Kursdaten und Börsenbedingungen. Kursdaten: Data Supplied by BSB-Software.