Kamoa-Kakula Shatters Previous Production Records, Mining 400,000 tonnes of ore Grading 5.36% Copper in March
Pre-production ore stockpiles hold 2.56 million tonnes grading 4.60% copper, containing more than 117,000 tonnes of copper
Overall progress of Kamoa-Kakula's first phase, 3.8-Mtpa mining and milling operation 92% complete; commissioning of concentrator plant underway with first copper production on track for July 2021
Kamoa-Kakula's main 220-kV substation energized with clean, renewable hydropower
Phase 2 expansion to 7.6 Mtpa progressing well toward a Q3 2022 start-up; engineering to commence for Phase 3 expansion to 11.4 Mtpa
Kolwezi, April 6, 2021 - Ivanhoe Mines (TSX: IVN; OTCQX: IVPAF) Co-Chairs Robert Friedland and Yufeng "Miles" Sun are pleased to announce that underground ore production at the Kamoa-Kakula Copper Project in the Democratic Republic of Congo (DRC) mined and stockpiled a record 400,000 tonnes of ore grading 5.36% copper from the Kakula and Kansoko mines in March. This tonnage was 18% higher than the 339,000 tonnes mined and stockpiled in February.
The 400,000 tonnes mined in March comprised 364,100 tonnes grading 5.52% copper from the Kakula Mine, including 100,000 tonnes grading 8.70% copper from the mine's high-grade centre, and 36,000 tonnes grading 3.78% copper from the Kansoko Mine.
The project's pre-production surface stockpiles now contain approximately 2.56 million tonnes of high-grade and medium-grade ore at an estimated blended average of 4.60% copper. Contained copper in the stockpiles increased by approximately 21,500 tonnes in March - to a cumulative total of more than 117,000 tonnes (the current copper price is approximately US$9,100 a tonne).
Kamoa-Kakula is on track to substantially exceed the 3.0 million tonnes of high-grade and medium-grade stockpiled ore, holding more than 125,000 tonnes of contained copper, that the 2020 pre-feasibility study projected would be stockpiled prior to the planned start of processing in July 2021.
Underground mine development continues well ahead of schedule
Kamoa-Kakula also set a fresh monthly mine development record in March, with an advancement of more than 3,100 metres, bringing total underground development to approximately 38.6 kilometres - around 13.5 kilometres ahead of schedule.
Drift-and-fill stoping operations are progressing well at the Kakula Mine, with approximately 70% of the ore production coming from stoping operations and the remainder coming from mine development activities. Drift-and-fill stoping is a highly-productive mining method of extracting underground ore, where a single tunnel, known as a stope, is extracted leaving an open void that is subsequently backfilled to allow for the extraction of the neighbouring stope in sequence.
Mark Farren, Kamoa Copper's CEO, commented: "The outstanding mining rate in March was driven by improved crew efficiencies and a higher percentage of ore coming from drift-and-fill stoping operations. We are comfortable with the mining performance as we move into final commissioning of the Phase 1, 3.8-Mtpa concentrator plant. If we consistently mine at around 400,000 tonnes per month, we will continue to add to the surface stockpiles ahead of our Phase 2, 7.6 Mtpa concentrator plant commissioning, which is expected in Q3 2022.
"We will continue to monitor the mining rate to ensure there is a balance between the number of new mining crews we add to our underground operations and the surface ore stockpiles ahead of Phase 2 commissioning. The large surface ore stockpiles will give us considerable flexibility during the ramp up of Phase 2 production."
Mr. Friedland added: "It is extremely encouraging to see how much better the project's actual mining performance has been compared to the projections presented in the 2020 independent definitive feasibility and pre-feasibility studies. This is a testament to the determination and resilience of our on-site team that has worked tirelessly over the last year to deliver the first phase of this massive project on time and on budget, despite the challenges posed by COVID-19. As we continue to ramp-up underground operations at the Kakula and Kansoko mines, and expand the processing facilities, our primary focus remains on the health, safety and well-being of our employees and contractors.
The proceeds from our recently completed US$575 million, 2.50% convertible senior note financing opens the distinct possibility of earlier development of Kamoa-Kakula's Phase 3 expansion to 11.4 Mtpa, which would bring copper production at the Tier One copper mine to approximately 530,000 tonnes, or approximately 1.2 billion pounds, per year. The funding also allows us to quickly expand our exploration program on our Western Foreland licences adjoining Kamoa-Kakula, in pursuit of our next world-scale copper discovery."
Chancelle Kabinda, Utility Vehicle Operator - one of many talented Congolese women helping to build Kamoa-Kakula into the world's next great copper mine.
To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/79508_edc9f31624e3f87c_002full.jpg
Phase 1 copper production from the Kakula Mine is scheduled to begin in July 2021. Kakula is projected to be the world's highest-grade major copper mine, with an initial mining rate of 3.8 Mtpa at an estimated early average feed grade of more than 6.0% copper, ramping up to 7.6 Mtpa in Q3 2022.
Phases 1 and 2 combined are forecast to produce up to approximately 400,000 tonnes of copper per year. Based on independent benchmarking, the project's phased expansion scenario to 19 Mtpa would position Kamoa-Kakula as the world's second-largest copper mining complex, with peak annual copper production of more than 800,000 tonnes.
Given the current copper price environment, Ivanhoe and its partner Zijin are exploring the acceleration of the Kamoa-Kakula Phase 3 concentrator expansion from 7.6 Mtpa to 11.4 Mtpa, which may be fed from expanded mining operations at Kansoko, or new mining areas at Kamoa North (including the Bonanza Zone) and Kakula West.
The Kamoa-Kakula Copper Project is a joint venture between Ivanhoe Mines (39.6%), Zijin Mining Group (39.6%), Crystal River Global Limited (0.8%) and the Government of the Democratic Republic of Congo (20%).
A 2020 independent audit of Kamoa-Kakula's greenhouse gas intensity metrics performed by Hatch Ltd. of Mississauga, Canada, confirmed that the project will be among the world's lowest greenhouse gas emitters per unit of copper produced.
March's ore production was 18% higher than February at slightly lower grades; pre-production surface ore stockpiles now total approximately 2.56 million tonnes grading 4.60% copper
Chart 1: Cumulative tonnes and grade of pre-production ore stockpiles at the Kakula and Kansoko mines - May 2020 to March 2021.
To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/79508_edc9f31624e3f87c_003full.jpg
Chart 2: Growth in contained copper in pre-production ore stockpiles at the Kakula and Kansoko mines - May 2020 to March 2021.
To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/79508_edc9f31624e3f87c_004full.jpg
Chart 3: Projected growth in contained copper in pre-production stockpiles at the Kakula and Kansoko mines up to July 2021. Dotted lines denote projections based on the 2020 pre-feasibility study.
To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/79508_edc9f31624e3f87c_005full.jpg
The ore being mined from the northern portion of the Kakula Mine is transported to surface via the conveyor system and placed on a blended surface stockpile that now contains approximately 1.44 million tonnes grading an estimated 4.86% copper.
Additional pre-production ore stockpiles are located at the Kakula southern decline (826,000 tonnes at a blended grade of 4.56% copper) and the Kansoko decline (287,000 tonnes at blended grade of 3.37% copper).
Kakula's main pre-production stockpiles at the northern declines. The blended stockpiles currently contain approximately 1.44 million tonnes grading 4.86% copper.
To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/79508_edc9f31624e3f87c_006full.jpg
Kakula southern decline blended ore stockpiles containing approximately 826,000 tonnes grading 4.56% copper (consisting of 380,000 high-grade tonnes @ 6.33% copper and 447,000 medium grade tonnes @ 3.06% copper).
To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/79508_edc9f31624e3f87c_007full.jpg
Kansoko decline blended ore stockpiles containing 287,000 tonnes grading 3.37% copper (consisting of 50,000 high-grade tonnes @ 5.50% copper and 238,000 medium-grade tonnes @ 2.92% copper).
To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/79508_edc9f31624e3f87c_008full.jpg
Figure 1: Underground development completed at Kakula Mine to April 3, 2021 (in black).
To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/79508_edc9f31624e3f87c_009full.jpg
Construction of the initial 3.8-Mtpa concentrator plant and other surface infrastructure now 90% complete
Kamoa-Kakula's initial 3.8-Mtpa concentrator plant is nearing completion and commissioning is well underway. The foundations for the Phase 2 concentrator plant are alongside the Phase 1 plant.
To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/79508_edc9f31624e3f87c_010full.jpg
Overall progress of Kamoa-Kakula's first phase, 3.8-Mtpa mining and milling operation (covering mine infrastructure, concentrator plant and surface infrastructure) now is approximately 90% complete (as of end of March), compared to 86% at the end of February.
Watch a short fly-over video of the construction of the concentrator plant and other surface infrastructure: https://bit.ly/39LIpqm
Overall construction of the project's first phase, 3.8-Mtpa concentrator plant and associated facilities is advancing rapidly and is approximately 92% complete (as of end of March), up from 85% complete at the end of February. The concentrator plant remains on track to be mechanically complete in Q2 2021, with first copper concentrate production scheduled for July 2021.
Delivery of equipment for the first concentrator plant effectively is complete with 2,426 truckloads of equipment and material having been delivered to site. The last shipments of transformers for emergency power and some components for the sand filter plant are scheduled to arrive this month; neither will delay commissioning.
Structural steel erection, platework installation and piping and valve installation for the first concentrator plant is effectively complete, with only minor small bore piping still outstanding.
Electrical, controls and instrumentation installation is the last activity before construction completion and subsequent commissioning. Cable installation and cable termination is nearing completion with the focus now on instrument cabling and terminations. Two plant electrical substations have been energized on temporary power (milling and flotation) to allow for early C2 (second-stage) commissioning, which involves energizing motor control centers and checking drives and electrical signals. Energizing of the main concentrator plant substation on permanent medium-voltage power is scheduled for early this month.
Punch listing and C1 (first-stage) commissioning sign off is well underway with approximately half of the 1,070 C1 certificates signed off and handed over from construction to commissioning. C2 commissioning has started in the milling and flotation areas using temporary power from the two substations.
Hong Wang, Mechanical Fitter, checking the alignment of pinion and girth gears of the primary ball mill during commissioning of the Phase 1 concentrator plant.
To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/79508_edc9f31624e3f87c_011full.jpg
Electrical installation at the backfill plant is ongoing and construction completion is expected at roughly the same time as the concentrator plant. The backfill plant is scheduled to be complete well before paste backfill is required for mining operations.
The backfill plant will be used to mix tailings from the processing plant with cement to produce paste backfill. The backfill will be pumped back into the mine and used to help support mined-out areas. Approximately one half of the mine's tailings will be sent back underground, significantly reducing the surface tailings storage. Construction of the tailings storage facility is progressing well and is scheduled to be completed on time to receive tailings from the processing plant.
Kakula's Phase 1, 3.8-Mtpa flotation cells, tailings and concentrate thickeners, and concentrate storage building at night. Foundations for the Phase 2 flotation cells are on the left.
To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/79508_edc9f31624e3f87c_012full.jpg
Kakula's Phase 1 ball mills at night.
To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/79508_edc9f31624e3f87c_013full.jpg
Earthworks and civil works progressing well for the second 3.8-Mtpa concentrator plant, with the first delivery of long-lead items now on site
Construction of the second 3.8-Mtpa concentrator plant (Phase 2) is progressing well with the current focus on earthworks and civil works. Both earthworks and civil works are tracking slightly ahead of schedule. With orders for all the long-lead items of equipment for the Phase 2 concentrator placed in September 2020, procurement activities have focused on the remainder of the plant equipment. Structural steel fabrication is underway with the first batch complete and due to arrive on site in June. Contract negotiations for the steel, mechanical, piping and plate erection are expected to conclude shortly.
Foundations for the second 3.8-Mtpa concentrator plant advancing quickly.
To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/79508_edc9f31624e3f87c_014full.jpg
A 3D illustration of Kakula's initial 3.8-Mtpa concentrator plant, with the Phase 2, 3.8-Mtpa processing plant shown in magenta. The picture immediately below shows the current construction progress.
To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/79508_edc9f31624e3f87c_016full.jpg
To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/79508_edc9f31624e3f87c_017full.jpg
A 3D illustration of the finished ball mills area for the Phase 1, 3.8 Mtpa concentrator, with the next two ball mills for the Phase 2 concentrator plant shown in magenta. The picture immediately below shows the current construction progress.
To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/79508_edc9f31624e3f87c_018full.jpg
To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/79508_edc9f31624e3f87c_019full.jpg
A 3D illustration of Kakula's first phase, finished backfill plant, with the current construction and the initial 3.8-Mtpa concentrator plant in the background shown immediately below.
To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/79508_edc9f31624e3f87c_020full.jpg
To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/79508_edc9f31624e3f87c_021full.jpg
Contractors installing metal sheeting on the concentrate storage building.
To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/79508_edc9f31624e3f87c_022full.jpg
By-pass stockpile feed conveyor system, with the run-of-mine stockpile in the upper right corner.
To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/79508_edc9f31624e3f87c_023full.jpg
Kakula's mine water settling ponds that receive surplus water pumped from underground. Some of the water will be used in the concentrator plant.
To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/79508_edc9f31624e3f87c_024full.jpg
Negotiations for the marketing of Kakula's copper concentrates expected to conclude in April
Kamoa-Kakula is nearing completion of agreements with respect to the sale of its copper concentrates during Phase 1 operations. Kakula is expected to produce an extremely high-grade, clean copper concentrate (containing over 55% copper) that will be highly coveted by smelters around the world. Metallurgical test work indicates that the Kakula concentrates contain extremely low arsenic levels by world standards - approximately 0.01%.
Kamoa-Kakula's main 220-kV substation energized with clean, renewable hydropower; upgrading work at the Mwadingusha hydropower plant nearing completion
In December 2020, the 35-kilometre-long double circuit 220-kilovolt (kV) power line to Kamoa-Kakula was connected to the national electrical grid through the New Western Dispatch substation in Kolwezi. Kamoa-Kakula's main 220-kV substation was energized with 220-kV power from the national power grid on March 25 and the first of two 33-kV transformers on March 29th. The next milestone is to energize the main plant 33-kV substation, which will then allow power reticulation to all of the plant's lower-voltage substations.
Two of the six new turbines at the Mwadingusha hydropower plant now have been synchronized to the national electrical grid, with each generating unit producing approximately 13 megawatts of power. The completion and commissioning of the hydropower plant's remaining four generating units, in sequence, is in progress. This will ensure that Kamoa-Kakula's power requirements are secured ahead of the commissioning of the concentrator plant.
The fully-refurbished Mwadingusha hydropower plant is expected to deliver approximately 78 megawatts of power to the national electrical grid.
Electrical engineers from Andritz Hydro of Switzerland, CEGELEC of France, and the DRC's Société Nationale d'Electricité (SNEL), monitoring the commissioning of Mwadingusha's turbines 2 and 3 from the control room. Commissioning of turbine 6, the fourth in the sequence of commissioning, is scheduled to start in mid-April.
To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/79508_edc9f31624e3f87c_025full.jpg
Yves Tshivuadi, Cherry Picker Operator, and Idriss Bibwe, Mechanic Fitter, connecting a surge arrestor and voltage transformer at Kamoa-Kakula's main 220-kV substation.
To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/79508_edc9f31624e3f87c_026full.jpg
Ben Munanga, newly appointed Chairman of Kamoa Copper, monitoring the energizing of the main 220-kV substation along with members of senior management of SNEL and Kamoa Copper.
To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/79508_edc9f31624e3f87c_027full.jpg
Members of SNEL's senior management and senior members of Kamoa Copper at the energized Kakula 220-Kv substation. From left to right: Kayembe Bukasa Cedric, Divisional Head, Communications, SNEL; Johan Nortje, Engineering Manager, Kamoa Copper; Doudou Bakutu, Divisional Head of Protection & Metering, SNEL; Chris Kabongo, Senior Engineer, Kamoa Copper; and Gilbert Tshilumba, Divisional Head of High Voltage Customers, SNEL.
To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/79508_edc9f31624e3f87c_028full.jpg
COVID-19 prevention and treatment initiatives enhanced while maintaining risk management strategy
Kamoa-Kakula continues to focus on prevention, preparation and mitigation in managing the risks associated with COVID-19. Large-scale testing, combined with focused preventative measures, ensures that positive cases are quickly identified, isolated and treated, with cross contamination kept to a minimum.
The project has a well-established COVID-19 isolation facility at the Kamoa Camp. Suspected cases and positive patients are moved to this facility, where they are isolated and treated. Once patients have recovered and are deemed no longer infectious, they can return to work only after an additional quarantine period determined by the project's medical staff.
Kamoa-Kakula has successfully treated a number of symptomatic patients in the Kamoa Hospital, where highly-experienced doctors and nurses apply the latest medical treatments in a world-class facility.
As the pandemic evolves, the medical team at Kamoa-Kakula continues to review and update its risk mitigation protocols, while ensuring that new medical advances are investigated and applied to protect the health and safety of the workforce and community members.
Fabrice Mitonga, Process instructor (right), with a class of new recruits that will be operating the Phase 1 concentrator plant.
To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/79508_edc9f31624e3f87c_029full.jpg
Jerome Mangenda, Miner trainee, practices explosives wiring procedures at the Kamoa-Kakula training centre.
To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/79508_edc9f31624e3f87c_030full.jpg
Jean Kamwang, Headmaster and teacher, with some of his students at the newly renovated Agronomist Technical Institute in the local village of Musokantanda, a Kamoa-Kakula Livelihoods education initiative.
To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/79508_edc9f31624e3f87c_031full.jpg
Marie Kapepa, a student at the Musokantanda Agronomist Technical Institute.
To view an enhanced version of this graphic, please visit:
https://orders.newsfilecorp.com/files/3396/79508_edc9f31624e3f87c_032full.jpg
Qualified Persons
Disclosures of a scientific or technical nature regarding development scenarios at the Kamoa-Kakula Project in this news release have been reviewed and approved by Steve Amos, who is considered, by virtue of his education, experience and professional association, a Qualified Person under the terms of NI 43-101. Mr. Amos is not considered independent under NI 43-101 as he is the Head of the Kamoa Project. Mr. Amos has verified the technical data disclosed in this news release.
Other disclosures of a scientific or technical nature regarding the stockpiles in this news release have been reviewed and approved by George Gilchrist, who is considered, by virtue of his education, experience and professional association, a Qualified Person under the terms of NI 43-101. Mr. Gilchrist is not considered independent under NI 43-101 as he is the Vice President, Resources of Ivanhoe Mines. Mr. Gilchrist has verified the other technical data disclosed in this news release.
The stockpile grade estimates contained in this release are based upon bulk ore sampling from earlier underground headings, and vertical channel sample profiles from recent development. Bulk ore sampling was done on each heading every second blast and three 5-kilogram samples were taken. Since the beginning of October 2020, channel sample profiles are the primary data informing the stockpile grade estimates. These are cut approximately 15 metres apart in 1-metre vertical increments across the full vertical exposure using a handheld grinder, with a 100-to-150-gram sample collected. The samples are pulverized at the project's onsite laboratory and analyzed using a portable XRF (pXRF) instrument. Kamoa Copper has routinely analyzed its exploration drill core for copper using pXRF, in addition to analysis at a commercial laboratory using four acid digest and ICP-OES. This data has demonstrated that pXRF results can be relied upon for grade control and run-of-mine sampling.
Ivanhoe has prepared an independent, NI 43-101-compliant technical report for the Kamoa-Kakula Project, which is available on the company's website and under the company's SEDAR profile at www.sedar.com:
- Kamoa-Kakula Integrated Development Plan 2020 dated October 13, 2020, prepared by OreWin Pty Ltd., China Nerin Engineering Co., Ltd., DRA Global, Epoch Resources, Golder Associates Africa, KGHM Cuprum R&D Centre Ltd., Outotec Oyj, Paterson and Cooke, Stantec Consulting International LLC, SRK Consulting Inc., and Wood plc.
The technical report includes relevant information regarding the assumptions, parameters and methods of the mineral resource estimates on the Kamoa-Kakula Project cited in this news release, as well as information regarding data verification, exploration procedures and other matters relevant to the scientific and technical disclosure contained in this news release.
About Ivanhoe Mines
Ivanhoe Mines is a Canadian mining company focused on advancing its three principal joint-venture projects in Southern Africa: the development of major new, mechanized, underground mines at the Kamoa-Kakula copper discoveries in the DRC and at the Platreef palladium-platinum-nickel-copper-rhodium-gold discovery in South Africa; and the extensive redevelopment and upgrading of the historic Kipushi zinc-copper-germanium-silver mine, also in the DRC.
Kamoa-Kakula is expected to begin producing copper in July 2021 and, through phased expansions, is positioned to become one of the world's largest copper producers. Kamoa-Kakula and Kipushi will be powered by clean, renewable hydro-generated electricity and will be among the world's lowest greenhouse gas emitters per unit of metal produced. Ivanhoe also is exploring for new copper discoveries on its wholly-owned Western Foreland exploration licences in the DRC, near the Kamoa-Kakula Project.
Information contacts
Investors: Bill Trenaman +1.604.331.9834 / Media: Matthew Keevil +1.604.558.1034
Forward-looking statements
Certain statements in this release constitute "forward-looking statements" or "forward-looking information" within the meaning of applicable securities laws. Such statements and information involve known and unknown risks, uncertainties and other factors that may cause the actual results, performance or achievements of the company, its projects, or industry results, to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements or information. Such statements can be identified by the use of words such as "may", "would", "could", "will", "intend", "expect", "believe", "plan", "anticipate", "estimate", "scheduled", "forecast", "predict" and other similar terminology, or state that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved. These statements reflect the company's current expectations regarding future events, performance and results and speak only as of the date of this release.
Such statements include without limitation, the timing and results of: (i) statements regarding Kamoa-Kakula is on track to substantially exceed the 3.0 million tonnes of high-grade and medium-grade stockpiled ore, holding more than 125,000 tonnes of contained copper, that the 2020 pre-feasibility study projected would be stockpiled prior to the planned start of processing in July 2021; (ii) statements regarding the Phase 1 concentrator plant remains on track to be mechanically complete in Q2 2021, with first copper concentrate production scheduled for July 202; (iii) statements that the risk of the risk of spreading or cross-contamination of COVID-19 at the Kamoa-Kakula Project is considered to be very low; (iv) statements regarding the expectation that Phase 2 of the project's development when the Kakula concentrator processing capacity doubles to 7.6 Mtpa is to be commissioned in Q3 2022; (v) statements regarding Kakula is projected to be the world's highest-grade major copper mine, with an initial mining rate of 3.8 Mtpa at an estimated average feed grade of more than 6.0% copper over the first five years of operation; (vi) statements regarding Phases 1 and 2 combined are forecast to produce up to approximately 400,000 tonnes of copper per year; (vii) statements regarding based on independent benchmarking, the project's phased expansion scenario to 19 Mtpa would position Kamoa-Kakula as the world's second largest copper mining complex, with peak annual copper production of more than 800,000 tonnes; (viii) statements regarding Kamoa-Kakula will be among the world's lowest greenhouse gas emitters per unit of copper produced; (ix) statements regarding Kamoa-Kakula should have more than sufficient stockpiles ahead of the Phase 2 concentrator commissioning; (x) statements regarding approximately one half of the mine's tailings will be sent back underground; (xi) statements regarding Kakula is expected to produce an extremely high grade and clean copper concentrate (containing over 55% copper and extremely low arsenic levels by world standards - approximately 0.01%) that will be highly coveted by copper smelters around the world; (xii) statements regarding the fully-refurbished Mwadingusha hydropower plant is expected to deliver approximately 78 megawatts of power to the national grid; (xiii) statements regarding Phase 2 structural steel fabrication is underway with the first batch complete and due to arrive on site in June and contract negotiations for the steel, mechanical, piping and plate erection are expected to conclude shortly; (ix) statements regarding energizing of the main concentrator plant substation on permanent medium-voltage power is scheduled for early in April; and (x) statements regarding Kamoa-Kakula's Phase 3 expansion would bring copper production at the Tier One copper mine to approximately 530,000 tonnes, or approximately 1.2 billion pounds, per year.
As well, all of the results of the Kakula definitive feasibility study, the Kakula-Kansoko pre-feasibility study and the Kamoa-Kakula preliminary economic assessment, constitute forward-looking statements or information, and include future estimates of internal rates of return, net present value, future production, estimates of cash cost, proposed mining plans and methods, mine life estimates, cash flow forecasts, metal recoveries, estimates of capital and operating costs and the size and timing of phased development of the projects. Furthermore, with respect to this specific forward-looking information concerning the development of the Kamoa-Kakula Project, the company has based its assumptions and analysis on certain factors that are inherently uncertain. Uncertainties include: (i) the adequacy of infrastructure; (ii) geological characteristics; (iii) metallurgical characteristics of the mineralization; (iv) the ability to develop adequate processing capacity; (v) the price of copper; (vi) the availability of equipment and facilities necessary to complete development; (vii) the cost of consumables and mining and processing equipment; (viii) unforeseen technological and engineering problems; (ix) accidents or acts of sabotage or terrorism; (x) currency fluctuations; (xi) changes in regulations; (xii) the compliance by joint venture partners with terms of agreements; (xiii) the availability and productivity of skilled labour; (xiv) the regulation of the mining industry by various governmental agencies; (xv) the ability to raise sufficient capital to develop such projects; (xvi) changes in project scope or design; and (xvii) political factors.
Forward-looking statements and information involve significant risks and uncertainties, should not be read as guarantees of future performance or results and will not necessarily be accurate indicators of whether or not such results will be achieved. A number of factors could cause actual results to differ materially from the results discussed in the forward-looking statements or information, including, but not limited to, the factors discussed below and under "Risk Factors", and elsewhere in this release, as well as unexpected changes in laws, rules or regulations, or their enforcement by applicable authorities; the failure of parties to contracts with the company to perform as agreed; social or labour unrest; changes in commodity prices; and the failure of exploration programs or studies to deliver anticipated results or results that would justify and support continued exploration, studies, development or operations.
Although the forward-looking statements contained in this release are based upon what management of the company believes are reasonable assumptions, the company cannot assure investors that actual results will be consistent with these forward-looking statements. These forward-looking statements are made as of the date of this release and are expressly qualified in their entirety by this cautionary statement. Subject to applicable securities laws, the company does not assume any obligation to update or revise the forward-looking statements contained herein to reflect events or circumstances occurring after the date of this release.
The company's actual results could differ materially from those anticipated in these forward-looking statements as a result of the factors set forth below in the "Risk Factors" section in the company's Q3 2020 MD&A and its current annual information form.