Gold79 Drills 21.3m of 2.0 g/t Gold at the Tyro Target at Its Gold Chain Project in Arizona
Ottawa, October 25, 2021 - Gold79 Mines Ltd. (TSXV: AUU) (OTCQB: AUSVF) ("Gold79" or the "Company") is pleased to announce preliminary results for the first four drill holes (223 meters) from its recently completed 16 hole program at the Gold Chain project in western Arizona. The four holes highlighted in this release were drilled across the northernmost exposures of the Tyro target and tested broadly mineralized surface exposures at depths from 20 to 40 meters below the surface. Results from the remaining 12 holes (852m) are pending.
Highlights
- Drilling has confirmed broad consistent gold mineralization at the Tyro target area
- Drill hole GC21-15 returned 2.0 g/t gold over 21.3m starting 12m downhole
- Drill hole GC21-14 returned 1.85 g/t over 19.8m starting 29m downhole
- Tyro is largely open at depth and on strike
Mr. Derek Macpherson, President & CEO stated, "We are pleased to see the first four drill holes at Tyro reveal strong mineralization at shallow depths supporting the gold values from our preliminary surface sampling and trenching programs. These holes only tested approximately 200m of the 1 km target area at Tyro." Mr. Macpherson continued, "Our ability to get these holes drilled a few days after signing the Tyro agreement is a testament to our team and the contractors that support us at Gold Chain."
Table 1: Summary of Drill Holes GC21-13 to 16, at the Tyro Target
Hole No. | Total Hole Depth (m) | Interval (m) | Width (m)* | Gold (g/t) | |
From | To | ||||
GC21-13 | 61.0 | 32.0 | 44.2 | 12.2 | 1.7 |
Incl. | 38.1 | 39.6 | 1.5 | 6.3 | |
GC21-14 | 61.0 | 24.4 | 53.3 | 29.0 | 1.3 |
Incl. | 29.0 | 48.8 | 19.8 | 1.9 | |
Incl. | 39.6 | 41.1 | 1.5 | 5.0 | |
GC21-15 | 54.9 | 10.7 | 32.0 | 21.3 | 2.0 |
Incl. | 13.7 | 21.3 | 7.6 | 3.7 | |
Incl. | 19.8 | 21.3 | 1.5 | 6.2 | |
GC21-16 | 45.7 | 18.3 | 30.5 | 12.2 | 1.7 |
* All widths are down hole and not corrected for true thickness. True thickness is estimated to be about 80% of the mineralized width.
Figure 1: Longitudinal section of the Tyro target showing select surface samples, approximate location of historical workings, recent drill hole results and the target area.
To view an enhanced version of Figure 1, please visit:
https://orders.newsfilecorp.com/files/5717/100727_54aac734647e6897_001full.jpg
Mr. Robert Johansing, VP Exploration stated, "These results confirm continuity of this broad zone of quartz-adularia veins and veinlets at depth. Minor workings suggest that the vein was locally exploited for high-grade veins of greater than 10 g/t Au, leaving behind notable widths of gold mineralization of greater than 1 g/t Au in both the footwall and hanging wall. The vein system is open at depth and along the one-kilometer strike. The vein system appears to widen significantly to the southwest which will guide future drilling".
Description of Drill Holes
All four RC holes in Table 1, were drilled from the hanging wall beneath surface vein exposures and limited mine workings at 50 to 60 degrees and encountered variable quartz veining over broad intervals (Figure 2). Surface exposures consist of discrete quartz-chalcedony-adularia-calcite veins up to 2 meters encompassed by a broad package of veins and veinlets. The wall rock for the entire Tyro target is a Precambrian granite which is strongly chloritized within the vein package; the vein system dips steeply to the southeast about 70 degrees.
Figure 2: Geologic section of Hole No. GC21-15 showing 2021 exploration results, NE Tyro target.
To view an enhanced version of Figure 2, please visit:
https://orders.newsfilecorp.com/files/5717/100727_54aac734647e6897_002full.jpg
Tyro Geology
The Tyro mine was developed both initially underground and then as an open pit in the 1980s along a broad zone of quartz-chalcedony veins and stockwork hosted by Pre-Cambrian granite (Figure 3). The zone trends NNE, dips steeply and can be traced for over 1 kilometer. Open pit exposures reveal a width from 30 to 60 meters. Prior to 1930, a shaft was sunken to a depth of 500 feet with workings down to the 200-foot level; underground production was minimal and production from the open pit is not currently known. The vein terminates to the SW into a few NNW-trending rhyolite dikes (Figure 1) and appears to horsetail to the northeast (Figure 4). Meaningful gold values have been identified over its entire strike length. The Tyro target is referred to as a Type B target which are north-trending transverse structures to the northwest-trending mineralized zones which parallel and define the North Oatman trend. The North Oatman trend gold mineralization, composed of quartz-calcite-adularia-fluorite veins and veinlets, is spatially associated with the rhyolite dike complex for about 10km. Type B targets tend to host discrete veins, like Sunset and Tyro.
Figure 3: Geology of the Tyro Target Plan View Showing Surface Assays, Drill Hole Locations, Proposed Drill Sites and Section A-A'-A" (Figure 1).
To view an enhanced version of Figure 3, please visit:
https://orders.newsfilecorp.com/files/5717/100727_54aac734647e6897_003full.jpg
Vein from the Tyro target strongly resembles vein from the gold-rich, epithermal Oatman district, about 15 to 20 km to the south. At Oatman, several veins have been exploited to depths greater than 200 to 400 meters at 10 to 20 g/t Au with average widths ranging from 3 to 10 meters. The Tyro target, which ranges from 20 to 50 meters, is likely an upper-level manifestation of an Oatman-type vein with broad, sheeted vein complexes coalescing into a discrete, high-grade vein at depth. It is reported that the historical shaft on the Tyro target, about 350 meters to the southwest of these drill holes, was developed to a depth of about 150 meters and was likely developed on vein.
Figure 4. Geologic sketch (see Figure 3 inset) showing reported drill holes, surface trenches and Section GS21-15 (Figure 2).
To view an enhanced version of Figure 4, please visit:
https://orders.newsfilecorp.com/files/5717/100727_54aac734647e6897_004full.jpg
Qualified Person / Quality Control and Quality Assurance
Robert Johansing, M.Sc. Econ. Geol., P. Geo., the Company's Vice President, Exploration is a qualified person ("QP") as defined by NI 43-101 and has reviewed and approved the technical content of this press release. Mr. Johansing has also been responsible for all phases of drilling, sample collection, labelling, bagging and transport from the project to American Assay Laboratories of Sparks, Nevada. Samples were then dried, crushed and split, and pulp samples were prepared for analysis. Gold was determined by fire assay with an ICP finish, over limit samples were determined by fire assay and gravimetric finish. Silver plus 24 other elements were determined by Aqua Regia ICP-AES, over limit samples were determined by fire assay and gravimetric finish. Standard sample chain of custody procedures were employed during drilling until delivery to the analytical facility.
About Gold79 Mines Ltd.
Gold79 Mines Ltd. is a TSX Venture listed company focused on building ounces in the Southwest USA. Gold79 holds 100% earn-in option to purchase agreements on three gold projects: the Jefferson Canyon Gold Project and the Tip Top Gold Project both located in Nevada, USA, and, the Gold Chain Project located in Arizona, USA. In addition, Gold79 holds two projects with minority interest being a 36.6% interest in the Greyhound Project, Nunavut, Canada under JV by Agnico Eagle Mines Ltd. and a 20% carried interest in the Taviche Project in Oaxaca, Mexico now under option to Fortuna Silver Mines Inc.
For further information regarding this press release contact: Derek Macpherson, President and Chief Executive Officer by email at dm@gold79mines.com or by phone at 416-294-6713. Gold79's website is located at www.gold79mines.com.
FORWARD-LOOKING STATEMENTS:
This press release may contain forward looking statements that are made as of the date hereof and are based on current expectations, forecasts and assumptions which involve risks and uncertainties associated with our business including any private placement financings, the uncertainty as to whether further exploration will result in the target(s) being delineated as a mineral resource, capital expenditures, operating costs, mineral resources, recovery rates, grades and prices, estimated goals, expansion and growth of the business and operations, plans and references to the Company's future successes with its business and the economic environment in which the business operates. All such statements are made pursuant to the 'safe harbour' provisions of, and are intended to be forward-looking statements under, applicable Canadian securities legislation. Any statements contained herein that are statements of historical facts may be deemed to be forward-looking statements. By their nature, forward-looking statements require us to make assumptions and are subject to inherent risks and uncertainties. We caution readers of this news release not to place undue reliance on our forward-looking statements as a number of factors could cause actual results or conditions to differ materially from current expectations. Please refer to the risks set forth in the Company's most recent annual MD&A and the Company's continuous disclosure documents that can be found on SEDAR at www.sedar.com. Gold79 does not intend, and disclaims any obligation, except as required by law, to update or revise any forward-looking statements whether as a result of new information, future events or otherwise.
Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.
To view the source version of this press release, please visit https://www.newsfilecorp.com/release/100727