• Samstag, 23 November 2024
  • 13:50 Uhr Frankfurt
  • 12:50 Uhr London
  • 07:50 Uhr New York
  • 07:50 Uhr Toronto
  • 04:50 Uhr Vancouver
  • 23:50 Uhr Sydney

Nevsun Resources Ltd.: Bisha Mine Reaches 70% Completion & Q4 Commissioning on Track

12.08.2010  |  Marketwire

VANCOUVER, BRITISH COLUMBIA -- (Marketwire) -- 08/12/10 -- Nevsun Resources Ltd. (TSX: NSU) (NYSE Amex: NSU) is pleased to provide a brief update on the Bisha project and the second quarter results.


The Bisha Project is positioned to be Eritrea's first modern day mine, with production anticipated to yield 1.06M oz gold, 734M lb copper, 1B lb zinc and 9.4M oz silver. Gold will be produced at an operating cost of less than $250/oz, with copper operating costs ranging from $0.54-$0.67/lb, and zinc operating costs at $0.50/lb. Bisha benefits from the continued support of the Eritrean government.


Mine construction continues as scheduled and as at the date of this release the Bisha project is now over 70% complete. During the course of Q2 2010, the following was achieved:



-- Completion of the majority of structural steel, plate work and
mechanical elements of the project;
-- Installation of the Ball and SAG mills;
-- Installation of the liner in the tailings management facility commenced;
and
-- Pre-strip mining continued per plan.


Cost expenditures over the quarter were incurred as planned and the project remains on track to come within the targeted $260 million total cost. As at June 30, 2010, approximately $168 million had been spent and a further $32 million had been ordered or arranged.


The Company is working effectively towards the following targets for remainder of 2010:


Q3



-- Completion of plant electrical and piping installation; and
-- Installation of the electrical power plant.


Q4



-- Commencement of ore extraction and stockpiling;
-- Completion of the tailings management facility;
-- Plant commissioning; and
-- First gold pour.

Pictures of the construction progress are updated regularly and can be found on the Company website.


QUARTERLY RESULTS


The Company's end of quarter financial position includes a healthy $82.1 million cash position that, together with the financial contribution by the State of Eritrea, should carry the project through to positive cash flow in Q1 2011. The estimated Bisha Project cash flow under various metals price assumptions is included in the annual MD&A and posted on the Nevsun website.


The Company's second quarter loss of $2,434,312 increased by $1,850,361 from Q2 2009's IFRS adjusted loss of $583,951 and was due primarily to an increase in share-based payments expense resulting from issuing options earlier in the year than in the prior year and increasing the number of stock options issued. The majority of the options issued in the quarter vest only if the Bisha project is successfully producing gold within a specified time and capital cost.


As noted in our press release on February 23, 2010, the decision to finance the project by equity instead of debt has significantly enhanced the estimated cash flow through the elimination of finance costs and debt repayment.


Complete details of the Q2 2010 Financial Statements and Management's Discussion and Analysis can be found on the Nevsun website at www.nevsun.com as well as on Sedar at www.sedar.com and EDGAR at http://www.sec.gov/edgar/searchedgar/webusers.htm.


Forward Looking Statements: The above contains forward-looking statements concerning cash position, construction progress, reserves, mine planning and project economics. Forward-looking statements are frequently, but not always, identified by words such as 'expects', 'anticipates', 'believes', 'intends', 'estimates', 'potential', 'possible' and similar expressions, or statements that events, conditions or results 'will', 'may', 'could' or 'should' occur or be achieved. Forward-looking statements are statements about the future and are inherently uncertain, and actual achievements of the Company or other future events or conditions may differ materially from those reflected in the forward-looking statements due to a variety of risks, uncertainties and other factors, including, without limitation, those described in the Management Discussion and Analysis of the Company. The Company's forward-looking statements are based on the beliefs, expectations and opinions of management on the date the statements are made and the Company assumes no obligation to update such forward-looking statements in the future. For the reasons set forth above, investors should not place undue reliance on forward-looking statements.


NEVSUN RESOURCES LTD.


Cliff T. Davis, President & Chief Executive Officer

Contacts:

Kin Communications

604 684 6730

Toll Free: 1 866 684 6730
ir@kincommunications.com
www.nevsun.com



Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!



Mineninfo
Nevsun Resources Ltd.
Bergbau
-
-
Copyright © Minenportal.de 2006-2024 | MinenPortal.de ist eine Marke von GoldSeiten.de und Mitglied der GoldSeiten Mediengruppe
Alle Angaben ohne Gewähr! Es wird keinerlei Haftung für die Richtigkeit der Angaben und der Kurse übernommen!
Informationen zur Zeitverzögerung der Kursdaten und Börsenbedingungen. Kursdaten: Data Supplied by BSB-Software.