SilverCrest Santa Elena Mine Start-Up Phase Update

06.01.2011  |  Marketwire

VANCOUVER, BRITISH COLUMBIA -- (Marketwire) -- 01/06/11 -- SilverCrest Mines Inc. (the 'Company')(TSX VENTURE: SVL) is pleased to report on start-up production and commissioning phase activities at its 100% owned Santa Elena mine located in Sonora, Mexico. The mine is expected to produce approximately 35,000 ounces of gold and 600,000 ounces of silver per full year of production at an estimated life of mine cash cost of less than US$375 per ounce of gold equivalent. The most significant production activities completed since the first metal pour on September 9, 2010 are outlined below. For more information and to view production photos, please visit the Company's website at www.silvercrestmines.com.


Production and Commissioning Activities to December. 31, 2010



-- Approximately 371,000 tonnes of lower grade ore (includes 15,000 tonnes
of old dumps) have been mined from the open pit at a strip ratio of
waste to ore of approximately 2:1. Mining of these lower grade tonnes
(average grade of 0.60 gpt Au and 40.2 gpt Ag) was necessary to provide
working space for equipment in the initial cut and to create a lower
angle for the ultimate pit high wall for safety reasons. This lower
grade material is considered pre-strip for the higher grade Main Zone
which is now being mined and will provide the bulk of the ore to be
mined in 2011.

-- The crusher is operating at near design throughput capacity of
approximately 2,500 tpd with an estimated 336.500 tonnes of ore crushed
to year end. There are currently 35,000 tonnes of ore from the open pit
in stockpile waiting to be crushed. Optimization of the various
operating parameters of the crusher is underway in order to reach a
steady state of production at design capacity and to achieve the
ultimate size reduction of ore to 100% minus 3/8'.

-- The heap leach pad currently holds an estimated 336,500 tonnes of ore
containing approximately 6,800 ounces of gold and 370,000 ounces of
silver that are under leach. In the first 30 days of the leach cycle for
current ore on the pad, recovery was estimated at 25 to 35% for gold and
15 to 25% for silver. The first ore placed on the pad has been under
leach for 130 days with estimated recoveries of 55% of the gold and 35%
of the silver. The optimum recoveries of 65 to 70% gold and 35 to 40%
silver predicted by the design metallurgical test work over a projected
300 day leach cycle appear to be achievable.

-- The Merrill Crowe recovery unit, refinery and on-site lab are all
performing as designed and expected.

-- As of December 31, approximately 2,140 ounces of gold and 54,900 ounces
of silver have been produced as dore with a significant amount of gold
and silver still in solution for processing and recovery. The Company
has received final settlement for the first two shipments of metal to
the refinery.

-- To date, no lost time accidents have occurred with over 340,000 hours
worked.

-- All production staff is in place with 68% of employees locally hired.
The goal is for 75% of mine employees to be locally hired and trained
over the next year.


Santa Elena Expansion Plan


The Company engaged a number of independent consultants in 2010 to examine the preliminary economics of expanding the current production at Santa Elena to approximately 100,000 ounces Au equivalent per year by phasing in the construction of a conventional mill facility and supplementing the ore from the open pit with the development of Santa Elena underground resources, mill feed from its nearby Cruz de Mayo deposit and re-treatment of the leach pad material to recover the residual gold and silver.


The Preliminary Assessment (PA) of the Expansion Plan for Santa Elena is nearing completion and the results of the PA as well as a NI 43-101 Technical report updating the Santa Elena reserves and resources are expected to be available shortly. It is expected that PA will demonstrate economic viability for the expansion plan which would then result in the implementation of the PA's recommendations and the commissioning of a Pre-Feasibility Study in 2011.


Exploration Update


Santa Elena Norte: Drilling is expected to begin on the Santa Elena Norte (SEN) target in January 2011. This target is conveniently located approximately one kilometre north of the current Santa Elena operations and is geologically similar to the Santa Elena Main Zone currently being mined. Mapping at SEN shows an exposed outcrop with a strike length of 200 metres with epithermal quartz banded veins, stockwork and breccias. The width at the surface of the exposed mineralized structure is estimated at 5 to 10 metres carrying grades of 0.5 gpt to 2 gpt Au and minor Ag. Projection of the mineralized zone strike length, based on intermittent vein outcrops, is approximately 500 metres. The Company plans to drill approximately 1000 metres in 8 drill holes to initially test the Santa Elena Norte mineralization.


The current NI 43-101 compliant reserves and resources for the Santa Elena mine and Cruz de Mayo satellite deposit are presented below;



---------------------
CONTAINED CONTAINED
----------------------------------------------------------------------------
OPEN PIT
RESERVES AU AG AU AG
(i) TONNES GPT GPT TONS OPT OPT AU OZ AG OZ
----------------------------------------------------------------------------
----------------------------------------------------------------------------
PROBABLE 6,541,950 1.61 56.7 7,211,250 0.047 1.68 339,600 11,927,100
----------------------------------------------------------------------------
UNDERGROUND RESOURCES(ii)
----------------------------------------------------------------------------
INDICATED 1,084,390 2.10 127.6 1,195,000 0.061 3.72 73,235 4,448,800
----------------------------------------------------------------------------
INFERRED 1,350,080 1.94 121.5 1,487,790 0.056 3.55 84,057 5,276,300
----------------------------------------------------------------------------
CRUZ DE MAYO (CM) RESOURCES(iii)
----------------------------------------------------------------------------
INDICATED 1,141,000 0.10 64.2 1,257,700 0.003 1.87 3,800 2,353,400
----------------------------------------------------------------------------
INFERRED 6,065,000 0.10 66.5 6,685,500 0.003 1.94 20,000 12,967,100
----------------------------------------------------------------------------
TOTALS
----------------------------------------------------------------------------
----------------------------------------------------------------------------
TOTAL
PROBABLE 6,541,950 1.61 56.7 7,211,250 0.047 1.68 339,600 11,927,100
----------------------------------------------------------------------------
TOTAL
INDICATED 2,225,390 1.08 95.1 2,452,700 0.031 2.77 77,035 6,802,200
----------------------------------------------------------------------------
TOTAL
INFERRED 7,415,080 0.44 76.5 8,173,290 0.013 2.23 104,057 18,243,400
----------------------------------------------------------------------------
(i)based on US$765 gold and $11.95 silver, cut-off grade of 0.5 gpt gold
equivalent at a ratio of 64:1 silver to gold
(ii)based on US$850 gold and $12 silver, cut-off grade is 1.75 gpt gold
equivalent at a ratio of 83:1 (Au: Ag) using 94% recovery of Au and 80%
recovery of Ag
(iii)satellite deposit based on US$750 gold and $11 silver, cut-off grade is
30 gpt silver


J. Scott Drever, President stated; 'We are certainly pleased at this time as to how the commissioning phase for the Santa Elena operations is progressing. Our supervisory personnel are working diligently to assure that the normal start-up challenges are resolved and the project reaches a steady state, design capacity as soon as possible. We are beginning to see the high grade ore of the Main Zone that convinced us that the low strip ratio and higher grades in the initial years of mining would provide accelerated payback, begin to be stacked on the pads. The receipt of revenues from the sale of our gold and silver will set the stage for early, free cash flow that will be utilized to implement the Company's strategy for corporate growth.'


N. Eric Fier, CPG, P.Eng. and Chief Operating Officer for SilverCrest Mines Inc. and Qualified Person for this news release has reviewed and approved its contents.


SilverCrest Mines Inc. is a 'Precious Metals Focused' exploration and development company with a portfolio of gold and silver deposits and high grade exploration properties located in Mexico and El Salvador. This property portfolio, which includes reported, probable reserves as well as indicated and inferred gold and silver resources and substantial exploration potential, provides an important base from which SilverCrest can develop its corporate objective of becoming a significant precious metals asset based company. The Company's immediate initiative is to acquire and develop substantial mineral resources and ultimately to operate multiple low cost, high grade precious metals mines.


This news release contains forward-looking statements, which address future events and conditions, which are subject to various risks and uncertainties. The Company's actual results, programs and financial position could differ materially from those anticipated in such forward-looking statements as a result of numerous factors, some of which may be beyond the Company's control. These factors include: the availability of funds; the timing and content of work programs; results of exploration activities and development of mineral properties, the interpretation of drilling results and other geological data, the uncertainties of resource and reserve estimations, receipt and security of mineral property titles; project cost overruns or unanticipated costs and expenses, fluctuations in metal prices; currency fluctuations; and general market and industry conditions.


Forward-looking statements are based on the expectations and opinions of the Company's management on the date the statements are made. The assumptions used in the preparation of such statements, although considered reasonable at the time of preparation, may prove to be imprecise and, as such, undue reliance should not be placed on forward-looking statements.


J. Scott Drever, President


SILVERCREST MINES INC.


Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

Contacts:

SilverCrest Mines Inc.

Fred Cooper

(604) 694-1730 or Toll Free: 1-866-691-1730

(604) 694-1761 (FAX)
info@silvercrestmines.com
www.silvercrestmines.com



Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!



Mineninfo
Silvercrest Mines Inc.
Bergbau
-
-
Copyright © Minenportal.de 2006-2024 | MinenPortal.de ist eine Marke von GoldSeiten.de und Mitglied der GoldSeiten Mediengruppe
Alle Angaben ohne Gewähr! Es wird keinerlei Haftung für die Richtigkeit der Angaben und der Kurse übernommen!
Informationen zur Zeitverzögerung der Kursdaten und Börsenbedingungen. Kursdaten: Data Supplied by BSB-Software.