• Dienstag, 23 Juli 2024
  • 03:36 Uhr Frankfurt
  • 02:36 Uhr London
  • 21:36 Uhr New York
  • 21:36 Uhr Toronto
  • 18:36 Uhr Vancouver
  • 11:36 Uhr Sydney

Capstone Completes Prefeasibility Study on Phase V Expansion of Minto Copper-Gold Mine

14.03.2011  |  CNW
Study extends mine life to 2020 with yearly average copper production of 43 million pounds at an average cash cost of $1.34/lb of payable copper

VANCOUVER, March 14 /CNW/ - Capstone Mining Corp. (CS: TSX) today reported the results of a Prefeasibility Study for the Phase V expansion ("Phase V PFS") of its high grade Minto copper-gold mine in the Yukon. This study recommends a ramp up in mill throughput to an average production rate of 3,750 tonnes per day ("tpd") throughput or 1.37 million tonnes per year processed in an optimized mill, with ore to be extracted from new mineralized areas discovered in 2009 to 2010 not considered in previous studies. The Phase V PFS targets 400 million pounds of copper in concentrate to be produced over a 10 year mine life, commencing January 2011. New deposits not considered in the Phase IV study, issued in December 2009, provided the basis to initiate the Phase V PFS.

"This Phase V PFS represents another significant milestone in the development of the Minto Mine," said Darren Pylot, President & CEO of Capstone. "The Phase V PFS at the Minto Mine has successfully translated recent new mineral discoveries into increases in mineral reserves that are shown to be amenable to a combination of open pit and underground mining that will increase life of mine copper production."

"Furthermore, as a result of the successful exploration in 2009 and 2010, the Phase V PFS outlines an attractive option for yet more increases in the future. We are already in the planning stage to crystallize this potential additional value, with a significant exploration campaign underway focused on recent discoveries at Wildfire and Inferno and extensions to Copper Keel. We anticipate new mineral resource models in 2011 that we expect to drive further feasibility work needed to evaluate future expansion scenarios or additional mine life. The commencement of underground mining in the second quarter of 2011 will result in an extended mine life, processing of higher grade ore earlier in the mine life, and continued improvement with respect to environmental considerations."


Highlights

(All amounts in Canadian dollars unless otherwise stated)

- Net present value, at a constant US$2.75/lb copper price for un-hedged production and a 7.5% discount rate, of $284 million before tax and $206 million after tax;

- Proven and probable Open Pit and Underground mineral reserves have increased to 12.9 million tonnes grading 1.53% copper, 0.60 g/t gold, and 5.2 g/t silver, for a contained 435 million lbs of copper, 247,000 oz of gold, and 2.2 million oz of silver;

- Mine life extended to 2020 with an average of 43 million pounds of copper production per year, with additional upside opportunities identified, as discussed below;

- Life-of-mine capital cost of $76.0 million (excluding a closure cost allowance of $16 million), primarily based on an assumption of conversion to self-mining, which decision will be subject to a cost-benefit analysis vs. remaining with contract mining; and

- Life-of-mine cash costs of US$1.34/lb* of payable copper, after by-product credits (with gold at US$300/oz and silver at US$3.90/oz, as per the agreement with Silver Wheaton).

* This is a non-GAAP performance measure and readers should refer to Non-GAAP Performance Measures note at the end of this news release for further details.


Phase V PFS

The Phase V PFS was completed by SRK Consulting (Canada) Inc. ("SRK") who were engaged by Capstone's wholly owned subsidiary, Minto Explorations Ltd. ("MintoEx") to detail new mineral resource and mineral reserve estimates for the Minto Mine property, explore plant capacity improvements based upon mineral reserve increases, design the new-life-of mine plan ("LOMP") with open pit as well as underground mining and update operating and capital cost estimates. The details of this PFS are provided in a technical report that will be filed on SEDAR within 45 days.

New mineral resource estimates were completed for Area 2/118, Minto East and Ridgetop based on exploration drilling results from 2009 and 2010. The Minto Main mineral resource estimate was updated to reflect changes due to mining, while the Minto North estimate remains unchanged. A new LOMP was generated using mineral reserves generated from the above mineral resource estimates after appropriate economic and technical considerations were applied. This new PFS incorporates underground mineral reserves and incorporates in-pit tailings disposal methodology.

The Phase V PFS supersedes and replaces prior development studies, which should no longer be relied upon.


Mineral Resource Estimation

The combined mineral resource estimate generated for this Phase V PFS is shown in the table below. For additional information, including the contribution of each deposit to the overall mineral resource, the mineral resource estimates at different cut-off grades, the parameters used to conduct the estimate, and the appropriate National Instrument 43-101 ("NI 43-101") disclosure, readers should refer to the technical report.


Combined Mineral Resource Statement at 0.5% Cu Cut-off for Area 2/118, Ridgetop,
Minto Main, Minto North and Minto East Deposits. (1)


__________________________________________________________________
| |Tonnes |Copper |Gold |Silver | Copper |Gold | Silver |
| Class |(000's)| (%) |(g/t)| (g/t) |(thousands|(000s|(000s oz)|
| | | | | | lb) | oz) | |
|_________|_______|_______|_____|_______|__________|_____|_________|
|Measured | 13,136| 1.40 | 0.57| 4.71| 406,624 | 239 | 1,989 |
|(M) | | | | | | | |
|_________|_______|_______|_____|_______|__________|_____|_________|
|Indicated| 24,341| 0.93 | 0.31| 3.33| 498,917 | 240 | 2,604 |
|(I) | | | | | | | |
|_________|_______|_______|_____|_______|__________|_____|_________|
|M & I | 37,476| 1.10 | 0.40| 3.82| 905,540 | 479 | 4,592 |
|_________|_______|_______|_____|_______|__________|_____|_________|
|Inferred | 5,955| 0.83 | 0.25| 2.82| 107,879 | 48 | 540 |
|_________|_______|_______|_____|_______|__________|_____|_________|

(1) Numbers may not total due to rounding

In the opinion of SRK, the block model mineral resource estimate and mineral resource classification reported herein are a reasonable representation of the mineral resources at Area2/118, Ridgetop, Minto North and Minto East deposits at the current level of sampling. The mineral resources presented herein have been estimated in conformity with generally accepted CIM "Estimation of Mineral Resource and Mineral Reserves Best Practices" guidelines and are reported in accordance with Canadian Securities Administrators' NI 43-101. Mineral resources are not mineral reserves and do not have demonstrated economic viability. Only Measured and Indicated mineral resources have been used in the preliminary feasibility study described in this report.

The database used to estimate the Area 2/118 and Ridgetop deposits was audited by SRK and the mineralization boundaries were modelled by SRK based on lithological and structural interpretations. NI 43-101 Qualified Person Garth Kirkham, P.Geo., estimated resources for Minto North and Minto East deposits and audited the Minto North and Minto East database and modelled mineralization boundaries.

SRK is of the opinion that the current drilling information is sufficiently reliable to interpret with confidence the boundaries of the mineralized domains and that the assaying data is sufficiently reliable to support estimating mineral resources.

In order to demonstrate a reasonable expectation of economic extraction, SRK constrained the overall mineral resource with a Whittle™ pit optimization software shell using the factors shown in the table below. Only the mineral resources within the shell that met the cut-off grade were considered as resources.


Whittle Optimization Parameters for Mineral Resource Estimate Constraint

_______________________________________________
|Constraining Parameter | Unit |Value|
|_______________________|_________________|_____|
|Copper Price | US$/lb |2.85 |
| |_________________|_____|
| | C$/lb |3.17 |
|_______________________|_________________|_____|
|Gold Price | US$/oz | 900 |
| | C$/oz |1000 |
|_______________________|_________________|_____|
|Silver Price | US$/oz | 12 |
| | C$/oz |13.33|
|_______________________|_________________|_____|
|Exchange Rate | C$: US$ |1.11 |
|_______________________|_________________|_____|
|Mining Cost | C$/t mined |1.50 |
|_______________________|_________________|_____|
|Processing and G&A Cost| C$/t milled |5.00 |
|_______________________|_________________|_____|
|Royalty | % | 0.5 |
|_______________________|_________________|_____|
|Slope angles |degrees (overall)| 50 |
|_______________________|_________________|_____|


Mineral Reserves

The mine plan for the study assumes a start date of January 1, 2011. Open pit mining on the Main deposit is projected to be finished with the completion of Stage V in the second quarter of 2011. The Ridgetop and Minto North deposits are proposed to be developed exclusively as open pits following completion of mining in the Minto Main deposit. The Area 2/118 deposit is proposed to be mined using a combination of open pit and underground mining methods. The Minto East deposit is to be developed as an underground mine with access coming from an extension of the Area 2/118 decline.

Based on a start date of January 2011, the Minto Phase V open pit and underground mines will produce a total of 12.9 million tonnes ("Mt") of ore (includes the Main pit stockpile balance at the end of 2010) and 58.5 Mt of waste to be placed in dumps or back-filled into open pits. Mining takes place over 7.5 years ending in mid-2018. Mill operations will continue processing stockpiled ore for an additional two years to mid-2020. In order to attain the proposed LOMP schedule, amendments to the current mining permits and water licence are required in the third quarter of 2012. Mineral reserves by deposit are detailed below.

Detailed mine design, planning and scheduling was then conducted on the optimal pit shells to produce the current pit designs. The Whittle parameters for open pit mine design are shown in the following table.


Summary of Whittle™ Parameters Used for Pit Design

____________________________________________
|Item | Unit| Value|
|______________________________|______|______|
|Metal Prices and Exchange Rate |
|____________________________________________|
|Copper |US$/lb| 2.25|
|______________________________|______|______|
|Gold* |US$/oz|300.00|
|______________________________|______|______|
|Silver* |US$/oz| 3.90|
|______________________________|______|______|
|Exchange rate |US$/C$| 0.86|
|______________________________|______|______|
|Processing |
|____________________________________________|
|Copper recovery to concentrate| max| 92%|
|______________________________|______|______|
|Gold recovery to concentrate | max| 70%|
|______________________________|______|______|
|Silver recovery to concentrate| max| 80%|
|______________________________|______|______|

*Based on terms of royalty stream agreement with Silver Wheaton.

Underground mine planning also started with the Net Smelter Return ('NSR') block model and then assumed a 1.2% Cu equivalent cut-off grade ('COG').  Datamine™ MRO software was utilized to determine economic mining shapes for underground extraction. Small mineralized zones distant from any proposed access were excluded from the mine plan.

Mineral Reserves by Class for Phase V

________________________________________________________________
| | | | Diluted grade | Contained Metal |
| Deposit | Mineral | |________________|_________________|
| | Reserve |Tonnes| Cu | Au | Ag | Cu | Au | Ag |
| | Class | (Mt) |(%) |(g/t)|(g/t)|(Mlb)|(koz)|(koz)|
|____________|_________|______|____|_____|_____|_____|_____|_____|
| | Proven | 2.25 |1.35| 0.46| 4.79| 67 | 33 | 346|
| |_________|______|____|_____|_____|_____|_____|_____|
| Main* |Probable | | | | | | | |
| |_________|______|____|_____|_____|_____|_____|_____|
| |Sub-total| 2.25 |1.35|0.46 | 4.79| 67 | 33 | 346 |
|____________|_________|______|____|_____|_____|_____|_____|_____|
| | Proven | 1.52 |2.36| 1.28| 8.55| 79 | 63 | 419 |
| |_________|______|____|_____|_____|_____|_____|_____|
| North |Probable | 0.01 |2.25|0.81 | 9.38| 0 | 0 | 2 |
| |_________|______|____|_____|_____|_____|_____|_____|
| |Sub-total| 1.53 |2.36|1.27 | 8.56| 79 | 63 | 421 |
|____________|_________|______|____|_____|_____|_____|_____|_____|
| | Proven | 0.63 |1.10| 0.25| 2.05| 15 | 5 | 41 |
| |_________|______|____|_____|_____|_____|_____|_____|
| Ridgetop |Probable | 0.71 |1.11|0.37 | 3.55| 17 | 9 | 81 |
| |_________|______|____|_____|_____|_____|_____|_____|
| |Sub-total| 1.34 |1.11|0.32 | 2.85| 33 | 14 | 122 |
|____________|_________|______|____|_____|_____|_____|_____|_____|
| | Proven | 3.37 |1.41| 0.53| 4.94| 105 | 58 | 536 |
| |_________|______|____|_____|_____|_____|_____|_____|
| Area 2 |Probable | 1.45 |1.08|0.31 | 3.59| 35 | 15 | 167 |
| |_________|______|____|_____|_____|_____|_____|_____|
| |Sub-total| 4.82 |1.32|0.47 | 4.53| 140 | 72 | 703 |
|____________|_________|______|____|_____|_____|_____|_____|_____|
| | Proven | | | | | | | |
| |_________|______|____|_____|_____|_____|_____|_____|
| 118 |Probable | 0.49 |1.29|0.09 | 1.73| 14 | 1 | 27 |
| |_________|______|____|_____|_____|_____|_____|_____|
| |Sub-total| 0.49 |1.29|0.09 | 1.73| 14 | 1 | 27 |
|____________|_________|______|____|_____|_____|_____|_____|_____|
| | Proven | | | | | | | |
| |_________|______|____|_____|_____|_____|_____|_____|
|Under-ground|Probable | 2.44 |1.90|0.82 | 6.71| 102 | 64 | 527 |
| |_________|______|____|_____|_____|_____|_____|_____|
| |Sub-total| 2.44 |1.90|0.82 | 6.71| 102 | 64 | 527 |
|____________|_________|______|____|_____|_____|_____|_____|_____|
| | Proven | 7.77 |1.56| 0.63| 5.37| 266 | 158 |1,343|
| |_________|______|____|_____|_____|_____|_____|_____|
| Total |Probable | 5.09 |1.50|0.54 | 4.91| 169 | 89 | 804 |
| |_________|______|____|_____|_____|_____|_____|_____|
| |Total |12.87 |1.53|0.60 | 5.19| 435 | 247 |2,146|
|____________|_________|______|____|_____|_____|_____|_____|_____|

*includes stockpile balance of 1,631 kt at beginning of 2011 for Main pit but excludes approximately 0.25Mt of partially oxidized material from stockpile.


Life of Mine Production Schedule

The mining sequence was divided into various stages. The first stage sees the completion of mining in the Main Pit (Stage 5) followed by the first stage of Area 2 (contractor mined), followed by mining of Minto North, Area 118, second stage of Area 2, then two stages in Ridgetop, and finally the last two stages in Area 2. As noted in the table below, underground production supplements the open pit mine ore feed. The stages were designed to provide the required mill feed per period, to process higher grade ore sooner, to defer stripping of waste as long as possible and to accommodate in-pit tailings storage.


Life-Of-Mine Production Schedule (excluding existing stockpiles)

_______________________________________________________________
| Area |Unit|2011|2012 |2013 |2014 |2015 |2016 |2017 |2018|
|____________|____|____|_____|_____|_____|_____|_____|_____|____|
|Main Stage 5| Kt |618 | | | | | | | |
|____________|____|____|_____|_____|_____|_____|_____|_____|____|
| UG | Kt | 13 | 630 | 730 | 730 | 338 | | | |
|____________|____|____|_____|_____|_____|_____|_____|_____|____|
|Minto North | Kt | | | 281 |1,248| | | | |
|____________|____|____|_____|_____|_____|_____|_____|_____|____|
| Ridgetop | Kt | | | | | | 773 | 564 | |
|____________|____|____|_____|_____|_____|_____|_____|_____|____|
|A2 Stage 1&2| Kt |188 |1,338| | 65 |1,217| 742 | | |
|____________|____|____|_____|_____|_____|_____|_____|_____|____|
| 118 | Kt | | | | 491 | | | | |
|____________|____|____|_____|_____|_____|_____|_____|_____|____|
|A2 Stage 3&4| Kt | | | | | | | 449 |822 |
|____________|____|____|_____|_____|_____|_____|_____|_____|____|
| Total | Kt |819 |1,968|1,011|2,534|1,555|1,515|1,013|822 |
|____________|____|____|_____|_____|_____|_____|_____|_____|____|


Processing

The mill processing profile used in the Phase V PFS is based upon a combination of three years of operating experience of the Minto Mill, combined with new metallurgical and comminution test work undertaken on each of the deposits comprising the Phase V PFS mineral reserves. Metal recoveries were averaged over all deposits but concentrate grades were individually determined for each deposit.  The LOM processing schedule is shown below:


Life-Of-Mine Mill Processing Schedule

_______________________________________________________________________________________________________
| | | 2011- | Y E A R |
|Parameter |UNIT| 2020 |_____________________________________________________________________________|
| | | Total | '11 | '12 | '13 | '14 | '15 | '16 | '17 | '18 | '19 | '20 |
|__________|____|_________|_______|_______|_______|_______|_______|_______|_______|_______|______|______|
|Mill Feed |tpd | 3,718 | 3,442| 3,750| 3,750| 3,750| 3,750| 3,750| 3,750| 3,750| 3,750| 3,750|
| Rate | | | | | | | | | | | | |
|__________|____|_________|_______|_______|_______|_______|_______|_______|_______|_______|______|______|
|Mill Feed | Mt | 12.9 | 1.256| 1.373| 1.369| 1.369| 1.369| 1.373| 1.369| 1.369| 1.369| 0.653|
| Total | | | | | | | | | | | | |
|__________|____|_________|_______|_______|_______|_______|_______|_______|_______|_______|______|______|
| |Cu %| 1.53 | 1.60| 1.86| 1.70| 2.86| 1.62| 1.68| 1.11| 0.96| 0.78| 0.78|
| |____|_________|_______|_______|_______|_______|_______|_______|_______|_______|______|______|
| | Au | 0.6 | 0.6| 0.7| 0.7| 1.5| 0.6| 0.7| 0.3| 0.3| 0.2| 0.2|
|Feed Grade|g/t | | | | | | | | | | | |
| |____|_________|_______|_______|_______|_______|_______|_______|_______|_______|______|______|
| | Ag | 5.2 | 6.0| 7.2| 5.4| 10.0| 5.8| 5.7| 2.9| 3.2| 2.2| 2.2|
| |g/t | | | | | | | | | | | |
|__________|____|_________|_______|_______|_______|_______|_______|_______|_______|_______|______|______|
| |% Cu| 92 | 92| 92| 92| 92| 92| 92| 92| 92| 92| 92|
| Recovery |____|_________|_______|_______|_______|_______|_______|_______|_______|_______|______|______|
| to Conc. |% Au| 70 | 70| 70| 70| 70| 70| 70| 70| 70| 70| 70|
| |____|_________|_______|_______|_______|_______|_______|_______|_______|_______|______|______|
| |% Ag| 78 | 78| 78| 78| 78| 78| 78| 78| 78| 78| 78|
|__________|____|_________|_______|_______|_______|_______|_______|_______|_______|_______|______|______|
| Conc. |% Cu| 39 | 41.5| 38.0| 39.0| 38.0| 38.0| 38.0| 38.6| 38.6| 38.7| 38.7|
| Grade | | | | | | | | | | | | |
|__________|____|_________|_______|_______|_______|_______|_______|_______|_______|_______|______|______|
| Conc. |dmt | 470,478 | 44,633| 61,728| 54,846| 94,937| 53,519| 55,956| 36,066| 31,201|25,449|12,134|
|Production| | | | | | | | | | | | |
|__________|____|_________|_______|_______|_______|_______|_______|_______|_______|_______|______|______|
| |Mlb | 400.4 | 40.8| 51.7| 47.2| 79.5| 44.8| 46.9| 30.7| 26.6| 21.7| 10.4|
| | Cu | | | | | | | | | | | |
| |____|_________|_______|_______|_______|_______|_______|_______|_______|_______|______|______|
| Conc. | oz | 173,146 | 16,807| 22,531| 22,259| 45,118| 19,488| 20,538| 9,375| 8,246| 5,948| 2,836|
| Metal | Au | | | | | | | | | | | |
| |____|_________|_______|_______|_______|_______|_______|_______|_______|_______|______|______|
| | oz |1,673,940|188,612|246,680|184,654|341,791|197,647|194,509|100,627|110,290|73,897|35,234|
| | Ag | | | | | | | | | | | |
|__________|____|_________|_______|_______|_______|_______|_______|_______|_______|_______|______|______|


Capital Cost Estimate

Life-of-mine capital costs are estimated at $76.0 million, of which $32.0 million is primarily related to the conversion to self-mining in 2012 and $34.1 million is related to the commencement of underground mining; the balance is contingency and sustaining capital incurred over the remaining mine life. An additional closure cost allowance of $16M was used in the cash flow analysis, as per an estimation completed in 2010. The earlier 2009 PFS closure cost allowance was $20M, but was considered to be a preliminary estimate. The 2010 estimate was done in more detail with increased accuracy. 


Phase V PFS Capital Cost Estimate

________________________________________________________________
| Area |Unit - C$|Cost Estimate|
|________________________________________|_________|_____________|
|Open Pit Mining Equipment Fleet | M$ | 32.0 |
|________________________________________|_________|_____________|
|Underground Equipment (fixed and mobile)| M$ | 18.3 |
|________________________________________|_________|_____________|
|Underground Development | M$ | 15.8 |
|________________________________________|_________|_____________|
|Process Plant | M$ | 5.0 |
|________________________________________|_________|_____________|
|Contingency | M$ | 3.1 |
|________________________________________|_________|_____________|
|Sustaining Capital | M$ | 1.8 |
|________________________________________|_________|_____________|
|TOTAL CAPITAL COST | M$ | 76.0 |
|________________________________________|_________|_____________|


The method of funding the possible acquisition of open pit mining equipment, which could be by cash, capital lease or other method, will be evaluated once a decision on self-mining has been made. Alternatively, contract mining could continue, if contractors can achieve the objectives set out under 'Operating Cost Estimate' section below, eliminating the need for the open pit mining capital noted above.


Operating Cost Estimate

The direct operating costs for the Phase V PFS were estimated using actual operating data from the Minto Mine using contract mining and from various planned optimizations related to the Phase V expansion and Underground Mining.


Phase V PFS Operating Cost Estimate

_________________________________________________________________
| Area |Unit - C$ |Cost Estimate|
|________________________________________|__________|_____________|
|Open Pit Mining* |$/t milled| 13.37 |
|________________________________________|__________|_____________|
|Underground Mining* |$/t milled| 35.17 |
|________________________________________|__________|_____________|
|Total Mining |$/t milled| 20.04 |
|________________________________________|__________|_____________|
|Processing |$/t milled| 12.94 |
|________________________________________|__________|_____________|
|General, administration, camp, royalties|$/t milled| 12.13 |
|________________________________________|__________|_____________|
|Total |$/t milled| 45.11 |
|________________________________________|__________|_____________|

*Of the 12.87 M tonnes in reserves, 2.44 M tonnes are extracted with underground mining methods

The operating cost estimate equates to a life-of-mine average total cash cost, after selling costs and net of by-product credits, of US$1.34 per pound of payable copper. Actual annual average reported costs in Capstone's financial statements could vary from this amount due to treatment of inventory, deferred stripping costs and stockpiles on an annual basis.


Economics

SRK reports that the estimated economic benefit of mining the Minto Phase V deposits is sufficient to proceed with further work such as underground development and, in particular securing the required licence and permit amendments from the various regulatory agencies.
>
The Phase V mine expansion adds economic benefit to the mine, yielding a Base Case 'A' (US$2.75 / lb for non-hedged copper production) pre-tax Net Present Value at a 7.5% discount rate ('NPV7.5%') of $284M. NPV's and copper price assumptions for all three cases used in the study are:


Pre-tax NPV(7.5% After-tax NPV(7.5%)
)

• Case A (Base Case) $284M $206M
(US$2.75/lb Cu):

• Case B (US$2.25/lb $180M $142M
Cu):

• Case C (variable $266M $194M
US$3.60/lb Cu to US$2.25/lb
Cu):


Case B represents the metal price used in the latest mineral reserve estimate.

The following table summarizes the three economic scenarios:

Comparison of Phase V PFS Base and Alternate Cases

_____________________________________________________________________
| Item | Unit |Case A|Case B| Case C |
|________________________|_________________|______|______|____________|
| Waste mined | Mt | 58.5 |
|________________________|_________________|__________________________|
| Ore mined | Mt | 11.2 |
|________________________|_________________|__________________________|
| Total mined | Mt | 69.7 |
|________________________|_________________|__________________________|
| Mill Feed* | Kt | 12.9 |
|________________________|_________________|__________________________|
| Copper millhead grade | % Cu | 1.53 |
|________________________|_________________|__________________________|
| Gold millhead grade | g/t Au | 0.60 |
|________________________|_________________|__________________________|
| Silver millhead grade | g/t Ag | 5.2 |
|________________________|_________________|__________________________|
| Copper in cons | Mlb | 400 |
|________________________|_________________|__________________________|
| Gold in cons | Koz | 173 |
|________________________|_________________|__________________________|
| Silver in cons | Koz | 1,674 |
|________________________|_________________|__________________________|
| Concentrate Grade | % Cu | 39 |
|________________________|_________________|__________________________|
| Base Copper Price (ex. | US$/lb | 2.75 | 2.25 |3.60 to 2.25|
| hedging) | | | | |
|________________________|_________________|______|______|____________|
|Ave. Copper Price (inc. | US$/lb | 2.73 | 2.25 | 2.65 |
|hedging) | | | | |
|________________________|_________________|______|______|____________|
| Gold price (inc. | US$/oz | 331 | 324 | 333 |
| hedging) | | | | |
|________________________|_________________|______|______|____________|
| Silver price (inc. | US$/oz | 3.90 | 3.90 | 3.90 |
| hedging) | | | | |
|________________________|_________________|______|______|____________|
| Exchange rate (LOM | C$/US$ | 1.09 | 1.16 | 1.08 |
| average) | | | | |
|________________________|_________________|______|______|____________|
| NSR (inc. royalties) | C$/t milled |84.29 |73.99 | 80.63 |
|________________________|_________________|______|______|____________|
| Unit Total OPEX | $/t milled | 45.11 |
|________________________|_________________|__________________________|
| Unit On-site OPEX |US$/lb Cu payable| 1.50 |
|________________________|_________________|__________________________|
| Unit Off-site OPEX |US$/lb Cu payable| 0.30 | 0.31 | 0.30 |
|________________________|_________________|______|______|____________|
| Unit By-product Credit |US$/lb Cu payable| 0.16 | 0.15 | 0.16 |
|________________________|_________________|______|______|____________|
|Unit OPEX net by-product|US$/lb Cu payable| 1.34 | 1.35 | 1.34 |
|credits | | | | |
|________________________|_________________|______|______|____________|
|Total Capital (initial &| C$M | 76 |
|sustaining) | | |
|________________________|_________________|__________________________|
| Allowance for closure | C$M | 16 |
| cost | | |
|________________________|_________________|__________________________|
| NPV(7.5%) pre-tax | C$M | 284 | 180 | 266 |
|________________________|_________________|______|______|____________|

*Mill Feed includes ore stockpile.


Permitting & Reclamation

In the Yukon, mining projects require an environmental assessment prior to the issuance or amendment of significant operating permits for mining, including a Type A Water Use Licence and a Quartz Mining Licence ('QML'). Elements of the Minto Project have undergone environmental assessment previously. A milling and mining rate increase (2008) and the Phase IV expansion (2010) have recently been assessed by the Yukon Environmental and Socioeconomic Assessment Board ('YESAB').

The major instruments permitting and governing operations for the project include Type A and B Water Use Licences, issued by the Yukon Water Board, and a QML issued by Yukon Government, Energy Mines and Resources.

Water management planning, as expected, is of particular interest to the stakeholders. The amendment to the Type A Water Use Licence is expected to be issued in the first quarter of 2011. The expansion of the Minto Mine in the Phase IV development received an environmental assessment under the Yukon Environmental and Socioeconomic Assessment Act ('YESAA') and will require QML amendments.  The first such QML amendment is anticipated to be issued in the first quarter of 2011, with the remaining necessary QML amendments expected during the second quarter of 2011. Certain components of Phase IV will require another amendment to the Type A Water Use Licence, which may be issued by the end of the third quarter of 2011.

The project is about to enter the YESAA process again for the Phase V expansion project with the assumption that the applicable licence amendments will be issued by the end of 2012.


Risks & Opportunities

The major risk areas identified in this study are:

1. Timing and approval of Phase IV and Phase V mine permit revisions;
2. Exchange rates, metal prices and external influences;
3. The ability to develop the underground mine as per the mining schedule;
4. The ability to transform open pit mining operations to an owner-operated fleet; and
5. The ability to maintain minimum dilution through effective grade control practices.


The most important opportunities to improve the project are:

1. Optimization of mine plan;
2. Discovering new mineral resources and converting them to mineral reserves; and
3. Plant capacity expansion potential.


Looking Forward

With the Phase V PFS in hand, MintoEx can now proceed towards submission of the Phase V permit, developing an underground access decline and constructing supporting infrastructure such as surface ventilation systems.


Technical Report

The full Phase V PFS, prepared as a NI 43-101 compliant Technical Report, will be filed under Capstone's profile on SEDAR at www.sedar.com within 45 days.


Quality Assurance

The technical information in this news release has been prepared in accordance with Canadian regulatory requirements set out in National Instrument 43-101 and reviewed by John Sagman, P. Eng, Manager of Projects, Capstone Mining Corp. Gordon Doerksen, P.Eng. of SRK has reviewed this news release for accuracy to the Phase V PFS report. Exploration activities at the Minto Mine are carried out under the supervision of Brad Mercer, P. Geol., VP, Exploration of Capstone Mining Corp.



Forward-Looking Statements

This document may contain "forward-looking information" within the meaning of Canadian securities legislation and "forward-looking statements" within the meaning of the United States Private Securities Litigation Reform Act of 1995 (collectively, "forward-looking statements"). These forward-looking statements are made as of the date of this document and Capstone Mining Corp. (the "Company") does not intend, and does not assume any obligation, to update these forward-looking statements.

Forward-looking statements relate to future events or future performance and reflect Company management's expectations or beliefs regarding future events and include, but are not limited to, statements with respect to the estimation of mineral reserves and mineral resources, the realization of mineral reserve estimates, the timing and amount of estimated future production, costs of production, capital expenditures, success of mining operations, environmental risks, unanticipated reclamation expenses, title disputes or claims and limitations on insurance coverage. In certain cases, forward-looking statements can be identified by the use of words such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or variations of such words and phrases or statements that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved" or the negative of these terms or comparable terminology. By their very nature forward-looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements. Such factors include, among others, risks related to actual results of current exploration activities; changes in project parameters as plans continue to be refined; future prices of resources; possible variations in ore reserves, grade or recovery rates; accidents, labour disputes and other risks of the mining industry; delays in obtaining governmental approvals or financing or in the completion of development or construction activities; as well as those factors detailed from time to time in the Company's interim and annual financial statements and management's discussion and analysis of those statements, all of which are filed and available for review on SEDAR at www.sedar.com. Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward-looking statements, there may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. The Company provides no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements.

Accordingly, readers should not place undue reliance on forward-looking statements.


* Non-GAAP Performance Measures

"Total Cash Costs" and "Unit Total Operating Costs" are Non-GAAP Performance Measures. These performance measures are included because these statistics are key performance measures that management uses to monitor performance. Management uses these statistics to assess how the Company is performing to plan and to assess the overall effectiveness and efficiency of mining operations. These performance measures do not have a meaning within GAAP and, therefore, amounts presented may not be comparable to similar data presented by other mining companies. These performance measures should not be considered in isolation as a substitute for measures of performance in accordance with GAAP.



For further information:

Capstone Mining Corp.
Cindy Burnett, VP Investor Relations
Telephone: 604-637-8157
Email: cburnett@capstonemining.com
Website: www.capstonemining.com
Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!



Mineninfo
Capstone Copper Corp.
Bergbau
A3DH8D
CA14071L1085

Copyright © Minenportal.de 2006-2024 | MinenPortal.de ist eine Marke von GoldSeiten.de und Mitglied der GoldSeiten Mediengruppe
Alle Angaben ohne Gewähr! Es wird keinerlei Haftung für die Richtigkeit der Angaben und der Kurse übernommen!
Informationen zur Zeitverzögerung der Kursdaten und Börsenbedingungen. Kursdaten: Data Supplied by BSB-Software.