• Dienstag, 23 Juli 2024
  • 00:26 Uhr Frankfurt
  • 23:26 Uhr London
  • 18:26 Uhr New York
  • 18:26 Uhr Toronto
  • 15:26 Uhr Vancouver
  • 08:26 Uhr Sydney

Kipoi Copper Project Stage 1 Construction Update

17.03.2011  |  CNW

PERTH, Western Australia, March 17 /CNW/ --
On track for April 2011 commencement of production


PERTH, Western Australia, March 17 /CNW/ - Tiger Resources Limited
(ASX:TGS) (TSX:TGS) is pleased to advise that construction has
continued to proceed safely and on budget during February for the Stage
1 development at the Kipoi Copper Project in the Democratic Republic of
Congo (DRC).


Tiger expects to complete plant construction and commence commissioning
during March 2011, with commercial production commencing in April 2011.
The Company expects to produce approximately 35,000 tonnes per annum of
copper for three years from the first stage of the development at
Kipoi.


The development team has achieved 353,852 man-hours without lost-time
injury to the end of February 2011.


Contractor's Group Five and DRA now have more than 70 technical
personnel at site to complete the piping installation and electrical
wiring, along with the owner's commissioning team. The process facility
is estimated to be 95% complete. The primary crusher and the three
generators have recently been delivered to site with installation and
commissioning of this equipment planned. DRA has scheduled 19 days for
commissioning of the HMS plant allowing first production of copper
concentrate to occur during April.


BACKGROUND


The Kipoi Project covers an area of 55 square kms and is located 75km
north‐north‐west of the city of Lubumbashi in the Katanga Province of
the DRC. The project contains a 12km sequence of mineralised Roan
sediments that host at least five known deposits: Kipoi Central, Kipoi
North, Kileba, Judeira and Kaminafitwe.


The Company has reported JORC-standard resources at three of the
deposits. The principle deposit is Kipoi Central which contains a zone
of high grade copper mineralisation within a much larger lower grade
global resource.


The Company proposes a staged development at the Kipoi Project. The high
grade zone of mineralisation at Kipoi Central is proposed to be
exploited during the Stage 1 development. During the three year life of
Stage 1 a total of 900,000tpa of 7% Cu is planned to be processed
through an HMS plant to produce the equivalent of 35,000tpa of copper.


The Company is currently undertaking a feasibility study to evaluate the
economic viability of constructing an SXEW plant (Stage 2) targeted to
come on stream within three years of the start of the HMS operation. It
is envisaged that ore from Kipoi Central, Kipoi North and Kileba South
and the other deposits within the Kipoi Project and within the nearby
Lupoto Project would be processed at the Stage 2 phase.


Caution Regarding Forward Looking Statements: The forward-looking
statements made in this news release are based on assumptions and
judgments of management regarding future events and results. Such
forward-looking statements involve known and unknown risks,
uncertainties, and other factors which may cause the actual results,
performance or achievements of the Company to be materially different
from any anticipated future results, performance or achievements
expressed or implied by such forward-looking statements. Such factors
include, among others, the actual market prices of copper, cobalt and
silver, the actual results of current exploration, the actual results
of future mining, processing and development activities, changes in
project parameters as plans continue to be evaluated, as well as those
factors disclosed in the Company's filed documents.


/NOTE TO PHOTO EDITORS: A photo accompanying this release is available
at http://photos.newswire.ca. Images are free to accredited members of the media/



To view this news release in HTML formatting, please use the following URL: http://www.newswire.ca/en/releases/archive/March2011/17/c3333.html

For further information in respect of the Company's activities, please contact:

Brad Marwood Stephen Hills Nathan Ryan
Managing Director Chief Financial Officer Investor Relations
Tel: ( 61 8) 9240 1933 Tel: ( 61 8) 9240 1933 Tel: ( 61 0)420 582 887
Email: bmarwood@tigerez.com Email: shills@tigerez.com Email: nryan@tigerez.com

Company website:www.tigerresources.com.au



Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!



Mineninfo
Tiger Resources Ltd.
Bergbau
A0CAJF
AU000000TGS2

Copyright © Minenportal.de 2006-2024 | MinenPortal.de ist eine Marke von GoldSeiten.de und Mitglied der GoldSeiten Mediengruppe
Alle Angaben ohne Gewähr! Es wird keinerlei Haftung für die Richtigkeit der Angaben und der Kurse übernommen!
Informationen zur Zeitverzögerung der Kursdaten und Börsenbedingungen. Kursdaten: Data Supplied by BSB-Software.