Reservoir Capital Corp.: Brodarevo Progress Report

10.05.2011  |  Marketwire

VANCOUVER, BRITISH COLUMBIA -- (Marketwire) -- 05/10/11 -- Reservoir Capital Corp. ('Reservoir' or the 'Company') (TSX VENTURE: REO)(FRANKFURT: ROC)(BERLIN: ROC) is pleased to provide a progress report on its 58.4MW Brodarevo Hydroelectric Project on the river Lim in southwest Serbia.The Company has engaged Energoprojekt Hidroinzenjering Co. Ltd. ('Energoprojekt') to prepare Feasibility Studies for both the Brodarevo 1 and Brodarevo 2 dams and power plants. These studies,as well as the various related studies being carried out under Energoprojekt's supervision, are underway and progressing as detailed below.


Topography, sediment, erosion and hydrology studies have already been completed and testwork on the hydrological models (see Company news release of May 3, 2011) is due for completion in June.


Geotechnical drilling for the dam foundations is scheduled for June and July, pending the completion of land purchases for the dam and plant sites and receipt ofthe relevant permits from the municipality.


The design, environmental studies and permitting for the sections of the M-21 road affected by the Brodarevo Project are expected to be completed by Put Inzenjering in late August.


Environmental studies in accordance with Serbian standards and legislation are being conducted in parallel with studies according to World Bank guidelines. Both sets of studies are scheduled for completion in late 2011.


Earlier this year, the Company received a one-year extension of the Brodarevo energy permits through January 2012 from the Serbian Ministry of Mines and Energy. The State Audit Commission has approved the Brodarevo Pre-Feasibility Studies and the Company intends to apply for a Building Permit once the Feasibility Studies are delivered to the relevant authorities.


Quality Control


Deputy Director of the Company's operating subsidiary REV d.o.o., Milan Cusic, M.Sc. Dipl. Eng., a graduate of the Faculty of Mechanical Engineering of the University of Belgrade (1997) and previously Chief Hydro Engineer for Serbian State Utility EPS (2003-2010), is responsible for the preparation of the technical information in this release.


About Reservoir


Reservoir is a renewable energy company that is engaged in the development of a 58.4MW hydroelectric project at Brodarevo in southwest Serbia. Reservoir holds four geothermal exploration licenses in Serbia and has applied for three hydroelectric licenses on the Cehotina River in Bosnia (17.75MW) and one to develop a 32 MW project from an existing reservoir dam at Vrutci in Serbia. The Company also holds a portfolio of 8 precious and base metal exploration properties in Serbia that, subject to approvals, are to be spun-out into a separately listed company. Reservoir's common shares trade on the TSX Venture Exchange (symbol 'REO') and on the Frankfurt and Berlin Exchanges (symbol 'ROC').


Neither the TSX Venture Exchange nor the Investment Industry Regulatory Organization of Canada accepts responsibility for the adequacy or accuracy of this release.

Contacts:

Reservoir Capital Corp.

Chris MacIntyre

VP Corporate Development

381 (11) 3978453 or 1 416 703 0010
info@reservoircapitalcorp.com
www.reservoircapitalcorp.com



Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!



Mineninfo
ReservoirCapital Corp.
Bergbau
-
-

Copyright © Minenportal.de 2006-2024 | MinenPortal.de ist eine Marke von GoldSeiten.de und Mitglied der GoldSeiten Mediengruppe
Alle Angaben ohne Gewähr! Es wird keinerlei Haftung für die Richtigkeit der Angaben und der Kurse übernommen!
Informationen zur Zeitverzögerung der Kursdaten und Börsenbedingungen. Kursdaten: Data Supplied by BSB-Software.