• Donnerstag, 25 Juli 2024
  • 18:38 Uhr Frankfurt
  • 17:38 Uhr London
  • 12:38 Uhr New York
  • 12:38 Uhr Toronto
  • 09:38 Uhr Vancouver
  • 02:38 Uhr Sydney

First Uranium announces financial results for the three and twelve months ended March 31, 2011

06.06.2011  |  CNW

TORONTO AND JOHANNESBURG, June 6, 2011 /CNW/ --
For the Management Discussion & Analysis and Financial Statements please
refer to the Company's website at www.firsturanium.com.


TORONTO AND JOHANNESBURG, June 6, 2011 /CNW/ - First Uranium Corporation (TSX:FIU), (JSE:FUM) (ISIN:CA33744R1029)
('First Uranium' or 'the Company') today announced total gold sales for
its financial year ended March 31, 2011 ('FY 2011') of 142,630 ounces
of gold, which is a significant increase over the 91,657 ounces sold at
the end of March 31, 2010 ('FY 2010'). 


FINANCIAL YEAR ENDED MARCH 31, 2011


The Company's consolidated revenue of $172 million for FY 2011, an
increase of 86% from $93 million in revenue for FY 2010, resulted in
the Company reflecting a $20 million gross profit margin from
operations in FY 2011 compared to a loss of $18 million in FY 2010.
Remembering that First Uranium remains in a capital development and
growth phase, the consolidated pre-tax loss for the year was $76
million, which is a 19% improvement over the pre-tax loss of $94
million in FY 2010.


During FY 2011, Mine Waste Solutions ('MWS'), which is a large tailings
retreatment operation that is currently extracting gold from 15
tailings dams, produced and sold 82,941 (FY 2010: 62,019) ounces of
gold generating $93 million (FY 2010: $61 million) in revenue at an
average Cash Cost* of $483 (FY 2010: $392) per ounce of gold sold. The
34% increase in gold sold for FY 2011 from FY 2010 was mainly
attributable to the additional production from the second gold plant
module, along with the 8% improvement in gold recoveries. The 13.4
million tonnes processed in FY 2011 was 21% higher compared to FY 2010.
The 65% overall increase in costs, year-on-year, was mainly driven by
the increase in production in Q2 2010, combined with the impact of the
stronger South African Rand in FY 2011.


The Ezulwini Mine, which is an underground gold and uranium producer
that is currently in a production build-up phase, produced and sold
59,689 (FY 2010: 29,638) ounces of gold generating $78 million (FY
2010: $31 million) in revenue at an average Cash Cost* of $1,691 (FY
2010: $2,600) per ounce of gold. The 150% increase in revenue reflects
the overall increase in throughput, grade and gold price over the
comparative periods. Although costs increased by 31% year-on-year, the
costs did not increase in direct correlation to the revenue increases,
due to the mine's fixed operating costs being spread over higher
production than the comparative periods, resulting in the decrease in
Cash Cost* compared to FY 2010. Consequently the mine's gross losses in
FY 2011 decreased by 47% compared to FY 2010. Only 20,500 pounds of
uranium was sold in FY 2011, as a result of a failure of two Ion
Exchange ('IX') columns in the uranium plant in August 2010, which
resulted in the manufacturing of two new columns and a $1.5 million
impairment of the two failed columns.  The uranium plant has since been
successfully re-commissioned.


During FY 2011, First Uranium utilized $48 million (FY 2010: $49
million) of its cash resources to fund its operating activities. The
Company spent $103 million (FY 2010:  $215 million) on capital projects
in FY 2011 comprising mainly the construction and successful
commissioning of MWS's third gold plant module, including adjoining
infrastructure ('Phase 2') and its new tailings storage facility
('TSF'). As at March 31, 2011, the Company's remaining cash and cash
equivalents amounted to $50 million.


On April 26, 2010, First Uranium raised $142 million in net proceeds
through a private placement offering of Cdn$150 million in secured
convertible notes due March 31, 2013.


On March 1, 2011, the Company concluded a public offering of 46 million
common shares at a price of Cdn$1.00 per share. The agents to the
offering exercised in full their over-allotment option to acquire an
additional 6 million common shares at the same price, resulting in
First Uranium selling an aggregate of 52 million common shares for
total gross proceeds of $53 million.


Deon van der Mescht commented, 'This capital raising was concluded
shortly before the devastating series of earthquakes and the
accompanying tsunami that hit the Japanese island of Honshu during
March 2011. The unfolding events at the Fukushima nuclear plant
continue and the impact on physical uranium demand had a destructive
effect on most uranium stocks. While there has been a level of recovery
for most uranium operators, we remain under pressure. This is ironic
when one considers that First Uranium is largely a gold producer,
having only recently recommenced uranium production at the Ezulwini
Mine'.


First Uranium's total gold sales from its two operations for the year
ended March 31, 2012 are forecast to be in the range of 215,000 to
250,000 ounces, whilst anticipated uranium sales are forecast to be in
the range of 250,000 to 300,000 pounds. The uranium plant at MWS is
largely complete. Commissioning of this plant will involve significant
upfront working capital investment in in-process inventory. Management
is considering a temporary deferral in the commissioning of the uranium
plant in light of currently depressed uranium prices and its objectives
of focusing cash resources towards the maturity of the 4.25%
convertible debentures in June 2012 and the ramp up of the Ezulwini
Mine.


FOURTH QUARTER ENDED MARCH 31, 2011


The consolidated revenue from First Uranium's two operations for the
three months ended March 31, 2011 ('Q4 2011') was $43 million, compared
to $29 million for the three months ended March 31, 2010 ('Q4 2010'),
which is a 49% improvement quarter-on-quarter. Gross profits from the
operations were $6 million for Q4 2011 (Q4 2010: loss of $8 million),
while the consolidated pre-tax loss for Q4 2011 of $18 million improved
by 41% compared to the pre-tax loss in the comparative period (Q4 2010:
$31 million).


During Q4 2011, the Company utilized $19 million (Q4 2010: cash inflow
of $0.004 million) of cash resources in its operating activities and
spent $12 million (Q4 2010: $18 million) on capital projects, mainly at
MWS. The cash profits generated by the mining operations during Q4 2011
were not yet sufficient to cover the cash costs related to all of its
mining costs as well as other costs for various corporate activities.
The limited cash outflow along with $20.6 million in value added tax
and income tax refunds received by the Company towards the end of Q4
2010, resulted in the small cash inflow from operating activities in Q4
2010.


Mine Waste Solutions


MWS successfully commissioned the final phase of its gold expansion
program (Phase 2 and the new TSF) one month ahead of schedule and also
exceeded its operating guidance for the fifth successive quarter. The
earlier commissioning of the final phase of the expansion program
allowed MWS to operate all three gold plant modules at full capacity as
of May 1, 2011.


First Uranium President and CEO, Deon van der Mescht, commented, 'This
past year has marked the achievement of many key milestones at MWS. We
have advanced significantly over the last eight months to the extent
that the commissioning of Phase 2 commenced on April 1, 2011, while
MWS's new TSF was commissioned during May 2011, with deposition of
tailings material onto the new TSF commencing on April 5, 2011.'


By mid-April 2011 the rate of deposition onto the new TSF increased from
an average of 1.2 million tons per month (mtpm) to 1.8 mtpm. Deposition
of material onto the previously used tailings storage facility (MWS
No.5 tailings dam) was subsequently stopped and that dam is now in the
process of being decommissioned.


During Q4 2011, MWS produced and sold 22,150 (Q4 2010: 18,505) ounces of
gold, generating $26 million in revenue (Q4 2010: $16 million) at an
average Cash Cost* of $471 (Q4 2010: $402) per ounce of gold.  The 61%
increase in revenues is the result of a 20% increase in ounces of gold
sold together with higher gold selling prices compared to Q4 2010. The
20% increase in gold sold is mainly attributable to higher tonnage
throughput quarter-on-quarter. The increase in Q4 2011 costs compared
to the previous quarter was driven by a combination of higher tonnage
throughput, higher labour and power costs as well as the impact of
costs in US dollar terms resulting from the significantly stronger
South African Rand in Q4 2011.


Pursuant to the terms of the MWS Gold Stream Transaction with a company
that is now known as Franco-Nevada (Barbados) Corporation ('FN'),
formally Gold Wheaton (Barbados) Corporation, MWS must satisfy certain
technical completion tests upon the successful completion of
construction of Phase 2 by September 1, 2011. The technical completion
test requires MWS to achieve consistent production over three
consecutive months where the tonnage processed is within 85% of the
1.933 million tonnes of tailings per month in respect of the project
('Steady State'). In addition, MWS must satisfy certain key criteria
with respect to tonnes of material processed, average feed grade to the
plant and gold recovery for a minimum continuous period of 14 days,
either during the Steady State production period or within the 90
period after achieving Steady State production. The testing process
commenced in May 2011 and is scheduled for completion by August 2011. 
Management remains confident that these targets will be achieved.


At MWS, production levels are expected to continue increasing and
management expects the annualized gold production of 110,000 to 125,000
ounces and annualized uranium sales of 140,000 to 170,000 pounds.


Ezulwini Mine


During Q4 2011, the Ezulwini Mine produced and sold 11,393 (Q4 2010:
10,898) ounces of gold, generating $16 million (Q4 2010: $12 million)
in revenue at a Cash Cost* of $2,178 (Q4 2010: $2,276) per ounce of
gold.  Revenue increased by 33%, reflecting the overall increase in
throughput and gold price over the comparative periods. The average
Cash Cost* decreased by 4% as a result of the mine's fixed operating
costs being spread over higher production in Q4 2011 compared to Q4
2010.


Gold production for Q4 2011 was severely constrained by the impact of
the shaft maintenance program that commenced towards the end of Q3
2011. The Ezulwini Mine's shaft hoisting capacity was restricted due to
lateral pressures being placed on the shaft sidewall, creating pinch
points along the hanging tower structure. The Company immediately
implemented a program to moil (clear) the pinch points, which resulted
in the hoisting capacity of the mine being temporarily constrained.


During the shaft maintenance programme, Room and Pillar mining, a mining
method that requires less logistical support, was initiated. The
strategy proved successful, in that approximately 30% of production was
derived from the Room and Pillar sections prior to a tragic fatality on
March 12, 2011 with subsequent loss in production from requisite safety
stoppages.


The successful completion of the moiling program at the end of April
2011 has unconstrained the hoisting capacity of the shaft, particularly
with respect to the man and material handling capacity. The winding
speeds of the man and material conveyances were reduced to between 2.5
and 4.0 meters per second during December 2010 due to the pinch points
which reduced the amount of material that could be conveyed down the
shaft per day as well as having a negative impact on the travelling
time of the underground workforce to their working places. The winding
speeds of the man and material conveyances have been increased to 7
meters per second as of the beginning of May 2011 which has increased
the material handling capacity of the shaft by at least 23% as well as
reducing the travelling time of the underground workforce resulting in
a minimum of an additional 45 minutes spent at the 'rock face' per
shift. The hoisting capacity of the shaft is currently 97,000 tons per
month and capable of meeting the current production requirements. The
remaining engineering work in the shaft can comfortably be concluded in
parallel with the mine ramp-up requirements.


During Q4 2011, the Ezulwini Mine replaced the two new IX columns that
failed in August 2010; consequently no uranium was produced during the
last quarter. The uranium plant was successfully re-commissioned in
March 2011 at a cost of $1.5 million, enabling the Company to return to
uranium production. During the shutdown period, several elements of the
plant were upgraded and re-designed to improve performance and recovery
rates. At the end of Q4 2011, the mine had 31,000 pounds of uranium in
stock which was calcined from ammonium diurinate that had been produced
at the mine before the failure of the IX columns. The uranium was
shipped and sold during April 2011.


Deon van der Mescht added, 'Following the two fatal accidents that
occurred over the financial year, and the subsequent Section 54
suspension notices served on the mine, as well as the various other
events which impacted production in the last quarter, Ezulwini is now
showing progressive improvement in its fundamentals with underground
mining development and metres advanced returning to planned levels. In
particular, the increase in winding speeds in key conveyances has
impacted positively on production volumes in the month of May 2011 with
record throughput levels of 62,992 tonnes achieved. The increased speed
of key conveyances is expected to continue to impact positively on the
ramp up of Ezulwini Mine.'


While production levels at Ezulwini for Q1 2012 are expected to be lower
than the planned quarterly average production for FY 2012, management
still expects annualized gold production of 105,000 to 125,000 ounces
and annualized uranium sales of 110,000 to 130,000 pounds.


Deon van der Mescht concluded, 'Ezulwini may have encountered some
challenges over the last few months, however these challenges are now
better understood, manageable and considered to be short-term.
Fundamentally the long-term value of the operation remains as was
confirmed by an independent technical review completed in January 2011.
At MWS, we can look forward to a new chapter in the year ahead with the
conclusion of the technical completion test anticipated in Q2 2012.  I
am convinced that an already impressive project will graduate to its
full potential'.


*Cash Costs are costs directly related to the physical activities of producing gold
and uranium and include mining, processing and other plant costs;
third-party refining and smelting costs; marketing expense, on-site
general and administrative costs; royalties; on-mine drilling
expenditures that are related to production and other direct costs.
Sales of by-product metals such as uranium and silver are deducted from
the above in computing cash costs. Cash costs exclude depreciation,
depletion and amortization, corporate general and administrative
expense, exploration, interest, and pre-feasibility costs and accruals
for mine reclamation. Cash costs are calculated and presented using the
'Gold Institute Production Cost Standard' applied consistently for all
periods presented. The Gold Institute was a non-profit industry
association comprised of leading gold producers, refiners, bullion
suppliers and manufacturers. This institute has now been incorporated
into the National Mining Association. The guidance was first issued in
1996 and revised in November 1999. Total cash costs per ounce is a non-GAAP measurement and investors are cautioned not to place undue reliance on it and are
advised to read all GAAP accounting disclosures presented in the
Company's Financial Statements.


Conference Call


First Uranium will conduct a conference call with investors to discuss
the information in this news release at 08:30a.m local Toronto time and 2:30pm local Johannesburg time on
Monday, June 6, 2011.


Conference Call Numbers:


Canada & USA Toll Free Dial In: 1-800-319-4610


South Africa Toll Free Dial In:  0800-981-705


Other International Locations Dial In: 1-604-638-5340


Callers should dial in 5 - 10 min prior to the scheduled start time and
simply ask to join the First Uranium call.


Conference Call Replay Numbers:


Canada & USA Toll Free: 1-800-319-6413


Outside Canada & USA Call: 1-604-638-9010


Code:    2128, followed by the # sign


Duration:  Available for 30 days


About First Uranium Corporation


First Uranium Corporation (TSX:FIU, JSE:FUM) is focused on its goal of
becoming a low-cost producer of gold and uranium through the expansion
of the underground development to feed the new uranium and gold plants
at the Ezulwini mine and through the expansion of the plant capacity of
the Mine Waste Solutions (MWS) tailings recovery facility, both
operations situated in South Africa.  First Uranium also plans to grow
production by pursuing value-enhancing acquisition and joint venture
opportunities in South Africa and elsewhere.


Cautionary Language Regarding Forward-Looking Information


This news release contains and refers to forward-looking information
based on current expectations. All other statements other than
statements of historical fact included in this release are
forward-looking statements (or forward-looking information). The
Company's plans involve various estimates and assumptions and its
business and operations are subject to various risks and uncertainties,
including without limitation, the outcome of the appeal of the Water
Use License by FSE. For more details on these estimates, assumptions,
risks and uncertainties, see the Company's most recent Annual
Information Form and most recent Management Discussion and Analysis on
file with the Canadian provincial securities regulatory authorities on
SEDAR at www.sedar.com. These forward-looking statements are made as of the date hereof and
there can be no assurance that such statements will prove to be
accurate, such statements are subject to significant risks and
uncertainties, and actual results and future events could differ
materially from those anticipated in such statements. Accordingly,
readers should not place undue reliance on forward-looking statements
that are included herein, except in accordance with applicable
securities laws.

www.firsturanium.com


Non-GAAP Measures


The Company believes that in addition to conventional measures prepared
in accordance with Canadian GAAP, the Company and certain investors and
analysts use certain other non-GAAP financial measures to evaluate the
Company's performance including its ability to generate cash flow and
profits from its operations. The Company has included certain non-GAAP
measures in this document. Non-GAAP measures do not have any
standardized meaning prescribed under Canadian GAAP, and therefore they
may not be comparable to similar measures employed by other companies.
The data is intended to provide additional information and should not
be considered in isolation or as a substitute for measures of
performance prepared in accordance with Canadian GAAP. Readers are
advised to read all GAAP accounting disclosures presented in the
Company's financial statements for more detail.



To view this news release in HTML formatting, please use the following URL: http://www.newswire.ca/en/releases/archive/June2011/06/c2929.html

Julian Gwillim, julian@aprio.co.za, or Gail Strauss, gailstrauss@mweb.co.za



Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!



Mineninfo
First Uranium Corp.
Bergbau
-
-

Copyright © Minenportal.de 2006-2024 | MinenPortal.de ist eine Marke von GoldSeiten.de und Mitglied der GoldSeiten Mediengruppe
Alle Angaben ohne Gewähr! Es wird keinerlei Haftung für die Richtigkeit der Angaben und der Kurse übernommen!
Informationen zur Zeitverzögerung der Kursdaten und Börsenbedingungen. Kursdaten: Data Supplied by BSB-Software.