• Sonntag, 25 August 2024
  • 09:29 Uhr Frankfurt
  • 08:29 Uhr London
  • 03:29 Uhr New York
  • 03:29 Uhr Toronto
  • 00:29 Uhr Vancouver
  • 17:29 Uhr Sydney

WGR-Wits Gold Completes a Positive Scoping Study on the DBM Project in the southern Free State Goldfield

23.06.2011  |  CNW

JOHANNESBURG, June 23, 2011 /CNW/ --
Witwatersrand Consolidated Gold Resources Limited


(Incorporated in the Republic of South Africa)


Registration Number 2002/031365/06


JSE Code: WGR


ISIN: ZAE000079703


TSX Code: WGR


CUSIP Number: S98297104


('Wits Gold' or 'the Company')


JOHANNESBURG, June 23, 2011 /CNW/ -


Highlights of the Scoping Study


-- Shallow underground mine design comprising a 700 metre vertical
shaft for men and materials and a conveyor decline for rock
transport
-- Based on Indicated Resources of 34.5Mt at 5.3g/t Au (5.9Moz)
The same reefs host Indicated Resources of 17.0Mt at 0.16kg/t
U3O8 (6.1Mlb)
-- First production 32 months after initiating construction
-- Production rate of 80 000 tonnes of ore per month
-- Average recovery of 150 000 oz/yr for the first 10 years of
full production
-- Life of mine 25 years with total production of 2.9Moz Au at an
average grade of 4.4g/t recovered.
-- Peak capital required ZAR1.59 billion (US$227m at ZAR7/US$)
-- Cash costs of production US$569/oz
-- At ZAR275 000/kg Au (US$1 222/oz & ZAR7/US$) pre-tax NPV (10%)
ZAR2.08 billion (US$298 million), IRR 26%, payback 6 years
-- At current gold price of ZAR325 000/kg Au (US$1 444/oz &
ZAR7/US$) pre-tax NPV (10%) ZAR3.54 billion (US$506 million),
IRR 35%, pay back 5 years


INTRODUCTION


Wits Gold is pleased to announce positive scoping study results for its
shallow De Bron - Merriespruit South ('DBM') project situated adjacent
to the Merriespruit Gold Mine, south of Welkom. The study was
undertaken independently by Andrew Pooley (the 'Qualified Person') from
Turgis Consultants with the participation of Chris Jones from Snowden
Mining Industry Consultants. It was completed under the guidelines of
the Canadian National Instrument 43-101 ('NI 43-101') and is based on
an Indicated Resource of 34.5Mt at 5.3g/t Au (5.9Moz) that occurs in
the same reefs as an Indicated Resource of 17.0Mt at 0.16kg/t U3O8
(6.1Mlb). Mineral resources are not mineral reserves and do not have
demonstrated economic viability. The study has also considered the
potential contribution that could be made by the conversion of Inferred
Resources of 25.0Mt at 5.2g/t Au (4.2Moz) and 11.9Mt at 0.14kg/t U3O8
(3.7Mlb), but the Inferred Resources are not included in the economic
model presented below. A NI 43-101 report summarizing the results of
the scoping study will be filed on SEDAR at www.sedar.com within 45
days of this press release.


GEOLOGY AND MINERAL RESOURCES


The mineral resources for the DBM project were estimated for the
Beatrix, Kalkoenkrans, B and Leader Reefs, where these conglomerate
reefs occur at depths of 500 - 1250 metres below surface. These
resources are disclosed in a NI 43-101 technical report entitled
'Witwatersrand Consolidated Gold Resources Limited: Mineral Properties
in the DBM Project, South Africa', prepared by George Gilchrist of
Snowden Mining Industry Consultants dated April,6 2011 which is
available on SEDAR at www.sedar.com. The samples from the DBM drilling
programme were assayed at Anglo American Research and SGS Laboratories,
both of which have ISO accreditation.


In view of the close vertical association between the Beatrix and
Kalkoenkrans Reefs, it is assumed that the higher grade Kalkoenkrans
Reef will be selectively mined rather than the overlying Beatrix Reef.
The only exception will occur in areas where these two conglomerates
are directly superimposed, so that they can be exploited in a single
mining cut. Based on an assessment of the rock mechanics, it is
concluded that the Kalkoenkrans, B and Leader Reefs will be exploited
as discrete, separate bodies. All of these reefs dip consistently at
12-18 degrees towards the northwest and have been dissected into a
number of coherent structural domains by syn-Ventersdorp faults.


MINE DESIGN


A combination of the gold grade distribution and a three dimensional
wireframe model provided the basis for a number of different mine
designs for the DBM project. At this preliminary stage, financial
modeling indicated that optimum returns are likely to be achieved by
establishing a shallow underground mine design comprising a 700 metre
vertical shaft served by a 12 degree conveyor decline. The scoping
study anticipates a preliminary production model for the DBM project,
based on similar mining operations in South Africa, using footwall
haulages, cross-cuts to reef at 150 metre intervals and conventional
breast stoping by hand held rock drills and scraper winches. Ore
generated in the stopes will pass via boxholes into cross-cuts from
where it will be loaded by load haul dumpers on to trucks for transfer
to the decline ore pass system. The ore will be transported to surface
by a conveyor feeding a purpose built carbon in leach (CIL) plant for
crushing, milling and gold recovery. The complementary vertical shaft
will be used for men and materials, whilst additional ventilation will
be provided by raise boreholes, drilled from surface.


FINANCIAL MODEL (assuming an exchange rate of ZAR7/US$ and based on the
Indicated Resources only)


This scoping study has been based on a monthly production rate of 80 000
tonnes of ore, provided mainly from the Kalkoenkrans and Leader Reefs,
in addition to 24 000 tonnes of waste material. First production is
scheduled for 32 months from the commencement of site construction,
with an average of 150 000oz Au per year for 10 years following the
achievement of full production. The peak capital required will be
ZAR1.59 billion (US$227 million), whilst operating costs are projected
at ZAR559/tonne with cash costs of US$569/oz. Assuming the exploitation
of the Indicated Resources only, the life of mine (LOM) will be 25
years, during which a total of 2.9Moz Au will be produced.


At a gold price of ZAR275 000/kg (US$1 222/oz at an exchange rate of
ZAR7/US$), the DBM project has a pre-tax NPV (10%) of ZAR2.08 billion
(US$298 million), an IRR of 25.8% and a payback of 6 years. However, at
the current gold price of around ZAR325 000/kg (US$1 444/oz at an
exchange rate of ZAR7/US$), the pre-tax NPV (10%) increases to ZAR3.54
billion (US$506 million) with an IRR of 35.2% and payback of 5 years.


A sensitivity analysis of the major input variables indicates that the
financial model for the DBM project is most sensitive to capital
expenditure, time to production, production rate, gold price and grade.
Consequently, the possibility of reducing the time for mine development
into the shallow higher grade sectors of the orebodies will be
evaluated during the pre-feasibility study that has been recommended by
the Qualified Person.


IMPACT OF CONVERTING INFERRED RESOURCES


By comparison with other Witwatersrand projects on similar tabular
reefs, the DBM project has been densely drilled, with the completion of
88 boreholes over the 15 square km area. However, some 40% of the
resources are currently in the Inferred category, where they occur
mainly in peripheral areas along the subcrop positions of the reefs
with the overlying Karoo Sequence, as well as immediately east of the
De Bron Fault. An integral part of the scoping study was to examine the
financial effect of including these Inferred Resources within the LOM
plan for the DBM project. The results suggest that due to the large
size of the DBM resource, the conversion of the Inferred Resources and
therefore extending the LOM will have a positive impact on the
financial model.  An appropriate drilling programme has been
recommended.


POTENTIAL CONTRIBUTION MADE BY URANIUM


Exploration drilling at the DBM project has indicated the presence of
consistently elevated uranium grades in the Leader Reef. However these
are diluted by lower grade Kalkoenkrans and B Reefs, resulting in an
Indicated Resource of 17.0Mt at an average of 0.16kg/t U3O8 (6.1Mlb).
As part of the scoping study, the possible economic contribution of
these uranium resources has been considered. The preliminary results
indicate that there could be some economic benefit by exploiting these
average grades. The pre-feasibility study will investigate the benefit
of handling and treating the Leader Reef separately.


COMMENTS


In response to the results of the scoping study, the CEO of Wits Gold Dr
Marc Watchorn said, 'We are delighted with the extremely positive
outcome of the Turgis study, which justifies our earlier statements
that DBM is likely to be South Africa's next shallow gold mine. We
intend proceeding immediately with a pre-feasibility study in the
anticipation of further optimising the mine design and financial
returns. We appreciate the patience of our shareholders, but realise
that the time is now right to investigate any opportunity to extract
maximum value from this world class resource'.


FORWARD LOOKING STATEMENTS


Certain statements in this news release may constitute forward-looking
information within the meaning of securities laws.  In some cases,
forward-looking information can be identified by use of terms such as
'may', 'will', 'should', 'expect', 'believe', 'plan', 'scheduled',
'intend', 'estimate', 'forecast', 'predict', 'potential', 'continue',
'likely', 'anticipate' or other similar expressions concerning matters
that are not historical facts.  Forward-looking information may relate
to management's future outlook and anticipated events or results, and
may include statements or information regarding the future plans or
prospects of the Company.  Without limitation, statements about the
development of the mine at the DBM project, the required capital
expenditures, the time required for the mine at the DBM project to
enter production, the length of time the mine at the DBM project will
operate at full production, the annual production of gold at the DBM
mine and other related statements are forward-looking information.


Forward-looking information involves known and unknown risks,
uncertainties and other important factors that could cause the actual
results, performance or achievements of the Company to be materially
different from the future results, performance or achievements
expressed or implied by such forward looking information.  Such risks,
uncertainties and other important factors include among others:
economic, business and political conditions in South Africa; decreases
in the market price of gold; hazards associated with underground and
surface gold mining; the ability to attract and retain qualified
personnel; labor disruptions; changes in laws and government
regulations, particularly environmental regulations and mineral rights
legislation including risks relating to the acquisition of the
necessary licences and permits; changes in exchange rates; currency
devaluations and inflation and other macro-economic factors; risk of
changes in capital and operating costs, financing, capitalization and
liquidity risks, including the risk that the financing required to fund
all currently planned exploration and related activities may not be
available on satisfactory terms, or at all; the ability to maximize the
value of any economic resources.  These forward-looking statements
speak only as of the date of this document.


You should not place undue importance on forward-looking information and
should not rely upon this information as of any other date.  The
Company undertakes no obligation to update publicly or release any
revisions to these forward-looking statements to reflect events or
circumstances after the date of this document or to reflect the
occurrence of unanticipated events except where required by applicable
laws.


Sponsor


PricewaterhouseCoopers Corporate Finance (Pty) Ltd




 

To view this news release in HTML formatting, please use the following URL: http://www.newswire.ca/en/releases/archive/June2011/23/c8725.html

Dr. Marc Watchorn
Chief Executive Officer
marcw@witsgold.com
Tel: 27 11 832 1749

Mr. Hethen Hira
Investor Relations
hethenh@witsgold.com
Tel: 27 11 832 1749

www.witsgold.com



Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!



Mineninfo
Wits Gold Ltd.
Bergbau
-
-

Copyright © Minenportal.de 2006-2024 | MinenPortal.de ist eine Marke von GoldSeiten.de und Mitglied der GoldSeiten Mediengruppe
Alle Angaben ohne Gewähr! Es wird keinerlei Haftung für die Richtigkeit der Angaben und der Kurse übernommen!
Informationen zur Zeitverzögerung der Kursdaten und Börsenbedingungen. Kursdaten: Data Supplied by BSB-Software.