• Samstag, 23 November 2024
  • 05:54 Uhr Frankfurt
  • 04:54 Uhr London
  • 23:54 Uhr New York
  • 23:54 Uhr Toronto
  • 20:54 Uhr Vancouver
  • 15:54 Uhr Sydney

NovaGold Announces Prefeasibility Study Results for Galore Creek Project

28.07.2011  |  Marketwire

VANCOUVER, BRITISH COLUMBIA -- (Marketwire) -- 07/27/11 -- NovaGold Resources Inc. (TSX: NG)(NYSE Amex: NG) -


All amounts are in Canadian dollars unless otherwise indicated and shown on a 100% Project basis, of which NovaGold and Teck each hold a 50% interest.


NovaGold Resources Inc. announces the results of the Prefeasibility Study ('PFS') for its Galore Creek copper-gold-silver project ('the Project'). The Galore Creek property is owned by a partnership owned equally by subsidiaries of NovaGold and Teck Resources Limited ('Teck') (NovaGold and Teck together 'the Partners') and managed by Galore Creek Mining Corporation ('GCMC'). An independent technical report will be completed by AMEC Americas Limited ('AMEC') and Lemley International ('Lemley') that will be based on the Prefeasibility Study completed by GCMC. NovaGold will host a conference call in relation to this release at 10:30am EDT/7:30am PDT on July 28, 2011. Details are provided later in this release.


The Prefeasibility Study ('PFS' or 'PFS Plan') confirms the technical and economic viability of the Project and shows a significant increase in scale and redesign of the Project from previous configurations. The PFS Plan provides for a mining and operating facility with a nominal 95,000 tonne-per-day capacity. Proven and probable mineral reserves total 528 million tonnes grading 0.6% copper, 0.32 grams per tonne gold and 6.02 grams per tonne silver. The Project is forecast to produce 6.2 billion pounds of copper, 4.0 million ounces of gold and 65.8 million ounces of silver over an approximate 18-year mine life with cash costs averaging $0.80 per pound of copper at Base Price Case assumptions and $0.42 per pound of copper at Current Price Case assumptions(1). If developed on the basis provided for in the Prefeasibility Study, Galore Creek would become one of the largest and lowest-cost copper producers in North America based on industry reports. The Prefeasibility Study configuration separates the mine infrastructure from the mill infrastructure, each located in adjacent valleys thereby increasing flexibility to enable open-pit mine expansion, higher mill throughput and additional exploration.


In reviewing the PFS Plan and opportunities identified, the Partners have determined to move forward with an enhanced project plan ('Enhanced Plan') for the project description required for permitting and to support a feasibility decision. GCMC will complete the engineering required to define the project description before year-end 2011. The Enhanced Plan envisions adding mineral resources that are within an optimized measured, indicated and inferred pit shell but due to comingled inferred mineral resources were excluded from the optimized measured and indicated pit that was the basis for classification of mineral reserves. These mineral resources are considered to have high potential for upgrading of confidence categories with additional drilling(2). The Enhanced Plan also considers the addition of a second Semi-Autogenous Grinding (SAG) mill in the fifth or sixth year of operations to maintain throughput at or above the nominal 95,000 tonne-per-day throughput rate as harder rock types are expected to be encountered as the pit deepens. The Enhanced Plan will also re-evaluate two other areas of the PFS Plan: the use of a pipeline to transport concentrate to the highway; and alternative port facilities. Both issues are important elements for the project description and scope for permitting. Further details on the Enhanced Plan are discussed later in this release.


(1) Cash costs net of by-product credits. Base Price Case utilizes metal prices of US$2.65/lb copper, US$1,100/oz gold and US$18.50/oz silver and a foreign exchange rate of $1.11 CAD/USD. Current Price Case metal prices are closing prices on July 27, 2011 of $4.44/lb Cu, $1,613/oz Au and $40.34/oz Ag respectively and foreign exchange rate of 0.949CAD/USD.


(2) The mineral resources are contained within a conceptual measured, indicated and inferred pit using metal prices for copper, gold and silver of US$2.50/lb, US$1,050/oz and US$16.85/oz respectively. Appropriate mining costs, processing costs, metal recoveries and pit slope angles developed during prefeasibility were used to generate the conceptual pit. Tonnages are assigned based on proportion of the block below topography. The overburden/bedrock boundary has been assigned on a whole block basis.



---------------------------------------------------------------------------
Base Current
Price Price
Project Economics Units Case(1) Case(2)
---------------------------------------------------------------------------
Pre-tax NPV (7%) $ millions 837 4,707
---------------------------------------------------------------------------
After-tax NPV (7%) $ millions 137 2,753
---------------------------------------------------------------------------
Cumulative (undiscounted) after-tax cash
flow $ millions 5,118 11,488
---------------------------------------------------------------------------
Internal rate of return % 7.4 14.0
---------------------------------------------------------------------------
After-tax payback Years 7.8 3.4
---------------------------------------------------------------------------
Average annual first five years after-tax
cash flow $ millions 740 1,267
---------------------------------------------------------------------------

Notes to Project Economics Table

1. Base Price Case metal prices are US$2.65/lb Cu, US$1,100/oz Au and
US$18.50 Ag and foreign exchange rate of 1.11 CAD/USD.
2. Current Price Case metal prices are closing prices on July 27, 2011 of
US$4.44/lb Cu, $1,613/oz Au and $40.34/oz Ag and foreign exchange rate
of 0.949 CAD/USD.


The results demonstrate that the Project's economics are highly sensitive to commodity prices. The pre-tax and after-tax net present values of the Current Price Case are approximately 5.6 times and 20 times higher than the Base Price Case respectively. The payback under the Current Price Case is approximately 4.4 years less than the Base Price Case.


'The results of the prefeasibility study clearly indicate that Galore Creek is a very valuable asset,' said Rick Van Nieuwenhuyse, President & CEO of NovaGold. 'The Project's scale, long life, low operating costs and exploration upside make Galore Creek a significant value driver for the Company. In an environment of strong copper demand and continued political uncertainty in key copper-producing areas of the world, Galore Creek is well positioned with its safe geopolitical location and low operating costs to take advantage of strong metal price fundamentals. NovaGold and its partner Teck, together with the Tahltan Nation, are aligned in building on the results of the Prefeasibility Study with the Enhanced Plan to increase the Project's value and advance Galore Creek toward a production decision.'


'Our goal is to ensure responsible development of projects in Tahltan Territory, and we are pleased to see completion of a positive prefeasibility study on the Galore Project, supporting the next phase of development,' said Annita McPhee, Tribal Chair of the Tahltan Central Council. 'We look forward to continuing to work cooperatively with the Galore Creek team to ensure Tahltan interests are addressed, potential impacts are managed and benefits from the Project are realized.'


Galore Creek PFS Plan Results


GCMC commissioned a number of engineering firms and expert consultants to determine the engineering and environmental requirements and economic potential of developing the Galore Creek copper-gold-silver project. AMEC reviewed this work, and together with Lemley, who reviewed the tunnel design, is preparing a technical report under National Instrument 43-101 guidelines that will be based on an independent review of the Prefeasibility Study, which NovaGold will file within 45 days on SEDAR at www.sedar.com and on EDGAR at www.sec.gov.



Mineral Reserves

---------------------------------------------------------------------------
Tonnage Diluted Grade Contained Metal
---------------------------------------------------------------------------
Cu Au Ag Cu Au Ag
Category (mt) (%) (g/t) (g/t) (Blbs) (Mozs) (Mozs)
---------------------------------------------------------------------------
Proven 69.0 0.606 0.520 4.94 0.9 1.15 11.0
---------------------------------------------------------------------------
Probable 459.1 0.582 0.291 6.18 5.9 4.30 91.2
---------------------------------------------------------------------------
Total Proven and
Probable 528.0 0.585 0.321 6.02 6.8 5.45 102.1
---------------------------------------------------------------------------

Notes to Mineral Reserves Table

1. Mineral Reserves are contained within Measured and Indicated pit designs
using metal prices for copper, gold and silver of US$2.50/lb,
US$1,050/oz, and US$16.85/oz, respectively.
2. Appropriate mining costs, processing costs, metal recoveries and inter
ramp pit slope angles varing from 42 degrees to 55 degrees were used
to generate the pit phase designs.
3. Mineral Reserves have been calculated using a 'cashflow grade' ($NSR/SAG
mill hr) cut-off which was varied from year to year to optimize NPV. The
net smelter return (NSR) was calculated as follows: NSR = Recoverable
Revenue - TCRC (on a per tonne basis), where: NSR = Net Smelter Return;
TCRC = Transportation and Refining Costs; Recoverable Revenue = Revenue
in Canadian dollars for recoverable copper, recoverable gold, and
recoverable silver using metal prices of US$2.50/lb, US$1,050/oz, and
US$16.85/oz for copper, gold, and silver, respectively, at an exchange
rate of CDN$1.1 to US$1.0; Cu Recovery = Recovery for copper based on
mineral zone and total copper grade; for Mineral Reserves this NSR
calculation includes mining dilution. SAG throughputs were modeled by
correlation with alteration types. Cashflow grades were calculated as
the product of NSR value in $/t and throughput in t/hr.
4. The life-of-mine strip ratio is 2.16.
5. Rounding as required by reporting guidelines may result in apparent
summation differences between tonnes, grade and contained metal content.
6. Tonnage and grade measurements are in metric units. Contained gold and
silver ounces are reported as troy ounces, contained copper pounds as
imperial pounds.


Mineral Resources

---------------------------------------------------------------------------
Tonnage Grade Contained Metal
---------------------------------------------------------------------------
Cu Au Ag
(million (Billion (Million (Million
Category tonnes) Cu (%) Au (g/t) Ag (g/t) pounds) ounces) ounces)
---------------------------------------------------------------------------
Measured 39.5 0.25 0.39 2.58 0.22 0.50 3.27
---------------------------------------------------------------------------
Indicated 247.2 0.34 0.26 3.81 1.85 2.04 30.26
---------------------------------------------------------------------------
Total Measured
and Indicated 286.7 0.33 0.27 3.64 2.07 2.53 33.54
---------------------------------------------------------------------------
Inferred 346.6 0.42 0.24 4.28 3.23 2.70 47.73
---------------------------------------------------------------------------

Notes to Mineral Resources Table

1. Mineral Resources are exclusive of Mineral Reserves. Mineral Resources
that are not Mineral Reserves do not have demonstrated economic
viability. There is no certainty that all or any part of the Mineral
Resources will be converted into Mineral Reserves. See: Cautionary Note
Regarding Reserve and Resource Estimates.
2. Mineral resources are contained within a conceptual Measured, Indicated
and Inferred optimized pit shell using the same economic and technical
parameters as used for Mineral Reserves. Tonnages are assigned based on
proportion of the block below topography. The overburden/bedrock
boundary has been assigned on a whole block basis.
3. Mineral resources have been estimated using a constant NSR cut-off of
C$10.08/t milled. The Net Smelter Return (NSR) was calculated as
follows: NSR = Recoverable Revenue - TCRC (on a per tonne basis), where:
NSR = Diluted Net Smelter Return; TCRC = Transportation and Refining
Costs; Recoverable Revenue = Revenue in Canadian dollars for recoverable
copper, recoverable gold, and recoverable silver using silver using the
economic and technical parameters mentioned above.
4. The mineral resource includes material within the conceptual M&I pit
that is not scheduled for processing in the mine plan but is above
cutoff.
5. Rounding as required by reporting guidelines may result in apparent
summation differences between tonnes, grade and contained metal content
6. Tonnage and grade measurements are in metric units. Contained gold and
silver ounces are reported as troy ounces, contained copper pounds as
imperial pounds.


Project Description


Comprising 118,912 hectares (293,840 acres) within the Tahltan Nation Traditional Territory in Northwestern British Columbia, Canada, Galore Creek is one of the world's largest undeveloped copper-gold-silver porphyry deposits.


Mining of the Galore Creek deposit is planned as a conventional truck-shovel open-pit mining operation with a nominal 95,000 tonne-per-day throughput. Throughput averages approximately 84,000 tonnes per day due to the milling circuit constraining throughput as harder rock is encountered deeper in the open pits. The current 528-million tonne mineral reserve should support a mine life of approximately 18 years. There is potential to extend the mine life with additional infill drilling and exploration. Using a conventional grinding and flotation circuit, the mine would produce a high-quality copper concentrate with significant gold and silver credits.


Mining and waste rock facilities would be located in the Galore Valley with plant and tailings facilities being located in the adjacent West More Valley. A 13.6-kilometer tunnel would be used for conveying ore and equipment movement between the two facilities. The Galore Creek project would be a large-scale open-pit mine which would provide process plant feed at a nominal rate of 95,000 tonnes per day or 34.6 million tonnes per year. Annual mine production of ore and waste would peak at 136 million tonnes per year with a life-of-mine waste/ore stripping ratio of 2.16-to-1. Run-of-mine ore would be fed into a single gyratory crusher in the Galore Valley. Crushed ore would then be transported via conveyor from Galore Valley through the access tunnel and via a road to a single coarse ore stockpile near the proposed mill site in the West More Valley.


The proposed process plant would be a conventional single-line grinding-flotation concentrator. A pipeline would transfer concentrate to a remote filter plant and concentrate truck-loading facility located near Highway 37. Thickened concentrate would be pumped approximately 71 kilometers to the filter plant located near the junction of the mine access road and Highway 37. From the filter plant, the concentrate would be transported by truck to a port facility in the town of Stewart for shipment to various international destinations.


The closest provincial road to the mine site is Highway 37, from which an 87-kilometer mine access road would be constructed. The access road would be used to transport employees to and from the mine site, and to deliver mine capital equipment and mine operating consumables. The road would have controlled access to ensure the health and safety of company personnel and the public, as well as to protect the environment. GCMC has an existing Special Use Permit for the construction of the access road following the route permitted under the existing Environmental Permit. A section of the access road from Highway 37 (Kilometer 0) to approximately Kilometer 40 has already been constructed for mine access and is currently in service. The entire road would require upgrading to meet final design criteria; the first eight kilometers would be upgraded to a dual-lane route to access the filter plant at Kilometer 8 and fuel off-loading facility. The balance of the access road would be single-lane, with occasional pullouts.


Power for the Project would be provided from the Northwest Transmission Line ('NTL') currently being constructed by the provincial electrical authority, BC Hydro. A 69-kilometer long, 287kV power line would run to the plant site adjacent to the access road with a further 27-kilometer line providing power to the mining operations.


The Project is anticipated to be constructed over an approximately four-year time period from initial start of tunnel boring until commencement of pre-operational commission activities.


Production Estimates


Galore Creek project has a 95,000 tonne-per-day nominal milling capacity. However, over the approximate 18-year mine life in the PFS Plan, throughput would average approximately 84,000 tonnes per day due to the milling circuit constraining throughput as harder rock is encountered deeper in the open pits.



Galore Creek Mine Production Summary(1)

----------------------------------------
Parameter Unit Mine
----------------------------------------
Tonnes ore mined (000 t) 528,033
----------------------------------------
Strip ratio 2.16:1
----------------------------------------
Grade: Copper % 0.59
Gold g/t 0.32
Silver g/t 6.02
----------------------------------------

1. Figures reflect mine dilution and mine recovery factors.


Galore Creek Mill Production Summary

-----------------------------------------------------------------
Parameter Unit Copper Concentrate
-----------------------------------------------------------------
Life-of-mine concentrate produced t-dry 10,002,384
Moisture content: % 8.0
-----------------------------------------------------------------
Recoveries
Cu: % 91
Gold % 73
Silver % 64
-----------------------------------------------------------------
Concentrate grade:
Copper % 28
Gold g/t 12.4
Silver g/t 205
-----------------------------------------------------------------
Recovered:
Copper M lbs 6,174
Gold 000 oz 3,983
Silver 000 oz 65,829
-----------------------------------------------------------------


Galore Creek Payable Metal Production

----------------------------------------------------
Copper (000 lb) Gold (000 oz) Silver (000 oz)
---------------------------------------------------------------------------
First 5 Years Average 365,414 225 3,381
---------------------------------------------------------------------------
Life-of-mine Average 321,772 208 3,036
---------------------------------------------------------------------------
Life-of-mine Total 5,947,946 3,848 56,125
---------------------------------------------------------------------------


Capital Cost Estimates


Capital costs are estimated with an accuracy range of 25% / -20% (including contingency) and are consistent with an AACE Class 4 estimate.



Galore Creek Construction Capital Cost Estimate

---------------------------------------------
Description $Millions
---------------------------------------------
Mine 356.7
Plant 835.4
Tunnel 579.5
Infrastructure 697.1
Total Direct Costs 2,468.8
---------------------------------------------
Mine and Pre-production Costs 581.6
Indirect Costs 1315.0
Owner's Costs 111.4
Contingency 678.4
---------------------------------------------
Total Capital 5,155.2
---------------------------------------------

Note: Numbers may not sum due to rounding.


Galore Creek Sustaining Capital Estimate

---------------------------------------------
Description $Millions
---------------------------------------------
Mine 163
Plant 66
Tailings 212
Infrastructure 110
---------------------------------------------
Total 552
---------------------------------------------


Closure costs, incurred at the end of the mine life, have been estimated at $86 million.


Operating Costs



Average Annual Operating Cost

------------------------------------
Description $/tonne milled
------------------------------------
Mine 6.70
Process 5.76
Port 0.16
Site G&A 1.56
Other 0.89
------------------------------------
Total 15.07
------------------------------------


Further Work During Feasibility


In addition to the infill and geotechnical drilling currently underway to confirm parameters for the Enhanced Plan, AMEC's report provided recommendations for work during the feasibility study phase to confirm or improve certain areas within the PFS Plan. The majority of the recommendations detail activities anticipated to be completed as standard scope of increasing project engineering and design through the feasibility study. Significant recommendations are summarized below.


AMEC adjusted the average recovery estimates of GCMC down by 1% for copper, 3% for gold and 7% for silver. AMEC recommended further metallurgical tests be completed to confirm recovery curves to be applied to future economic studies.


AMEC recommended early engagement on certain infrastructure-related issues including negotiations with BC Hydro on the power interconnection, advancement of the access road and selection of the tunnel contractor to ensure an early start to engineering and construction. In addition AMEC recommended commitments to procure equipment and materials with long lead times to secure the project schedule.


AMEC recommended further detailed assessment of geo-hazard risks, site and pit water management and waste dump design and management.


Galore Creek Enhanced Plan


The Prefeasibility Study identified opportunities to expand the mine life, improve the production profile, and reduce the initial capital requirements of the Galore Creek project. Parameters related to these opportunities have been reviewed in order to outline an Enhanced Plan for consideration during future work.


Open-pit and Mill Expansion Opportunities


Under the PFS Plan approximately 528 million tonnes of proven and probable mineral reserves would be mined over the life of the project. In the PFS Plan, the ore would be processed through a single 95,000 tonne-per-day nominal SAG mill grinding circuit during the full life-of-mine period. As the ore is expected to become harder during the mine life of the Project, throughput would be reduced in the latter years due to grinding circuit limitations yielding an average life-of-mine milling rate of 84,000 tonnes per day over the 18-year mine life.


Mine plan studies have demonstrated that mineral resources in the Bountiful area could become part of the mine plan using long-term price assumptions if comingled inferred mineral resources were drilled to a measured and indicated classification. It is envisioned in the Enhanced Plan that the required infill drilling would convert inferred mineral resources in the Bountiful area to measured and indicated mineral resource categories so that the material may then be used as part of an appropriately engineered mineral reserve pit. Both the infill drilling to convert inferred mineral resources to measured and indicated mineral resources, and a geotechnical drilling to confirm pit slope design in this area are currently on-going and part of the summer program.


The mining of the 528 million tonnes of mineral reserves and the additional mineral resources referred to above would increase the amount of waste rock that would need to be handled, requiring some modification to the waste rock management plan in the Galore Valley. In order to provide sufficient space for waste rock storage, the access causeway and ore conveying systems would need to be relocated from the East Fork area. The Enhanced Plan anticipates the extension of the access tunnel by an additional four kilometers to allow the entire East Fork area to be utilized for waste rock storage. The tunnel extension would increase the initial capital required for the project. Furthermore, a substantial amount of additional potentially acid-generating (PAG) waste rock would need to be re-handled during the mine closure period in order to submerge the additional PAG waste rock for reclamation.


Under the Enhanced Plan the mine life would be lengthened sufficiently that a mill expansion could be undertaken near the fifth or sixth year of operations. The mill expansion would require some additional initial capital in order to design the coarse ore stockpile to eventually feed two SAG mills, and would require additional sustaining capital to install a second SAG mill. The addition of a second SAG mill would lead to an increase in the total site power requirements and annual operating costs, but would reduce the overall unit operating costs. Under the Enhanced Plan, it is anticipated the nominal mill capacity could be sustained throughout the mine life.


Capital Cost Reduction Opportunities


A portion of the capital cost of the PFS Plan is estimated for the construction of a Galore Creek port facility at Stewart. Another major capital component is the concentrate transportation and filtration system, which includes a 70-kilometer slurry and fuel pipeline, filter plant, water treatment plant, 50-person full-service camp, and fuel tank farm. Reconfiguration of this portion of the process and an alternative approach to the port facility could reduce overall capital. The amount of initial capital for these facilities may be reduced under the Enhanced Plan.


Initial study indicated that an alternate port facility in Stewart may be upgraded to meet Galore Creek's concentrate transportation requirements. Under the Enhanced Plan, a capital estimate to complete facility upgrades would be included, as well as an estimate of unit-based concentrate terminal fees. This component of the Enhanced Plan would reduce the initial capital required, which would be partially off-set by an increase in operating costs (terminal charges).


The PFS Plan includes pipelines to transport concentrate and diesel fuel along the access road between the West More mill site and the Kilometer 8 site, located at Highway 37. The Kilometer 8 site would have necessary support facilities, including a camp. Piping concentrate in slurry form requires a water treatment plant to treat filtrate prior to its release. Filtered concentrate would then be trucked from the Kilometer 8 site to Stewart via Highway 37. The Enhanced Plan considers relocating the filter plant to a location adjacent to the mill at the West More site which would eliminate the need for a slurry pipeline and instead utilize truck transport for dry concentrate. Under this scenario, filtrate would be recycled to the processing plant, removing the requirement for a standalone water treatment plant. Filtered concentrate would be trucked from the West More mill site to Stewart, along the Galore Creek access road to Highway 37 and on to Stewart. Fuel would be trucked along the access road to the storage tanks at West More, and potentially through the access tunnel to the Galore Valley. The access road would need to be substantially upgraded from the current design in order to accommodate the increased truck traffic. The Kilometer 8 camp would not be required, and the number of beds at the West More camp would need to be increased to accommodate the additional personnel associated with concentrate filtration and haulage.


It is anticipated that the relocation of the filter plant to the mill site could result in a net reduction in capital cost, partially offset by increased operating costs. The additional costs of trucking fuel and concentrate along the access road would be the primary drivers of the increase in operating costs.


The combination of the increase in the overall mining rate over the life-of-mine, milling circuit expansion, and a longer tunnel, described as the Enhanced Plan, are expected to have a positive impact on project economics. However, further analysis is required to support this conclusion including mineral resource definition, engineering and cost estimating. Prior to inclusion of the Enhanced Plan components into the Galore Creek project development configuration, further work will be completed before the end of 2011.


2011 Work Program


The Partners have approved a $30.5-million budget to carry out further work on the Project during the remainder of 2011. Planned work includes infill drilling to convert targeted inferred mineral resources to measured and indicated categories, geotechnical drilling on the tunnel alignment and geotechnical drilling to confirm open-pit slopes in areas targeted for conversion of inferred mineral resources.


GCMC will also complete further environmental and engineering work in preparation for feasibility level studies. This work will be completed in parallel with feasibility planning activities including selection of the prime consultant for the feasibility study. A statement of work for the Feasibility Study has been issued with requests for proposals from sub-consultants expected to be issued in October. A number of purchase orders have been issued for geotechnical and geochemistry work which is being completed through the summer and early fall to support the Feasibility Study.


Permitting


The Galore Creek project received an Environmental Assessment (EA) Certificate under the British Columbia Environmental Assessment Act in February 2007 and approval under the federal Canadian Environmental Assessment Act in June 2007. The new design and project configuration is different from what was permitted under the original EA Certificate.


While NovaGold considers the new configuration an improvement, with reduced risks, it is anticipated that further EA review will be requested by the regulators. This EA review may take the form of an amendment to the existing EA Certificate or a new EA process. This process is expected to involve parallel, harmonized, reviews by both the BC Environmental Assessment Office and the Canadian Environmental Assessment Agency. It is expected that the entire EA review process would take approximately two years from submission of a project description to issuance of new provincial and federal approvals.


Upon completion of the Enhanced Plan engineering, GCMC will be preparing the project description for submission concurrent with appropriate Partner approvals prior to the end of 2011.


Exploration Potential


The majority of proven and probable mineral reserves are hosted within the main Central Zone. As discussed in the Enhanced Plan, additional inferred mineral resources that would be economic at long-term metal price assumptions, but not drilled to sufficient confidence to be included in the PFS Plan, exist in extensions to the southeast, an area known as the Bountiful Zone. With additional infill drilling these resources are targeted to be upgraded to measured and indicated classification for inclusion in the Enhanced Plan.


Additional reported mineral resources occur at depth in the Central Zone and in four adjacent satellite deposits on the property: Junction, Southwest, West Fork and Bountiful. Mineralization has been identified on other prospects, including the Butte, West Rim, North Junction, North Rim and Saddle areas, but sufficient drilling has not occurred to define mineral resources.


Additional mineralization that can be identified through step-out and infill drilling in the existing deposits and prospects has significant potential to support estimation of additional mineral resources, and may support mineral resource conversion to mineral reserves thus adding material to the mine plan. Exploration potential also lies beyond those areas identified in the Enhanced Plan as exploration occurs during the course of the proposed mining operation. Additionally, any upward variation in commodity prices that result in a reduction in cut-off grades could support estimation of additional tonnages and grades by extending limits of the pit shells. Please refer to the footnotes in the Mineral Reserves and Mineral Resources sections regarding parameters used to determine mineral resources and reserves.


The Copper Canyon deposit is located mid-way up the east fork of Galore Creek, approximately two kilometers from the Central Zone and hosts an inferred mineral resource and multiple high-quality target areas. NovaGold recently acquired Copper Canyon Resources to consolidate the land position. NovaGold has offered the Copper Canyon lands to Teck for inclusion in the Galore Creek Partnership Agreement.


Community Engagement


In February 2006, NovaGold entered into a comprehensive Participation Agreement with the Tahltan Nation, ensuring collaboration between both parties for mine planning, mine operation and environmental protection. GCMC, NovaGold and Teck continue to work closely with the Tahltan Nation, and the project has received a high level of support from local communities.


NovaGold believes that mining projects can be developed in a manner that brings tangible benefits to all stakeholders. NovaGold, Teck and GCMC are committed to respecting and protecting the culture of Galore Creek's community partners and using traditional knowledge to enhance project development. GCMC is committed to open and transparent communications with the communities in which it works.


Conference Call


NovaGold will be hosting a conference call in relation to the Galore Creek Project Prefeasibility Study at 10:30am EDT (7:30 am PDT) on Thursday July 28, 2011.



Webcast details: www.novagold.net or www.meetview.com/novagold
Conference call details: 1-866-212-4491 (North America) / 416-800-1066
(International)
Password: NovaGold
Conference call replay
details: 1-866-583-1035 / PIN: 2851565#


PFS Contributions and Qualified Persons


Under the direction and supervision of GCMC, the following consultants acted as the principal engineers for their areas of expertise for the PFS:



---------------------------------------------------------------------------
Area of Responsibility in Pre-
Consulting Firm or Entity feasibility Study Document
---------------------------------------------------------------------------
---------------------------------------------------------------------------
GCMC Third-party Consultant Plant infrastructure, capital and
operating cost estimates,
execution plan and schedule
GCMC Third-party Consultant Tunnel
GCMC Third-party Consultant Concentrate pipeline
WorleyParsons Ltd Port
Knight Piesold Ltd Transmission line
Tahltan-Allnorth Limited Partnership Access road
AMEC E&E Services Inc. Tailings, waste rock and water
management, geochemistry
Brodie Consulting Ltd Closure plan
Lorax Environmental Services Ltd. Water quality modeling
G &T Metallurgical Services Ltd Metallurgical services and
metallurgical testwork
Rescan Tahltan Environmental Consultants Ongoing baseline studies
---------------------------------------------------------------------------

Note: The consulting firm or entity noted as 'GCMC Third-party Consultant'
is unable to be identified due to their contract terms with GCMC.


The Mineral Reserve and Mineral Resource estimates have been prepared in accordance with the 2010 CIM Definition Standards for Mineral Resources and Mineral Reserves as incorporated by reference in National Instrument 43-101 of the Canadian Securities Administrators. The AMEC Qualified Persons for the estimates are Greg Kulla, P.Geo. for Mineral Resources, and Jay Melnyk, P.Eng., for the Mineral Reserves.


The NI 43-101 technical report will be authored by Robert Gill, P.Eng., Jay Melnyk, P.Eng., Greg Kulla, P.Geo. and Gregory Wortman, P.Eng. of AMEC Americas Limited and Dana Rogers, P.Eng. of Lemley International. The Qualified Persons will be responsible for preparation of the technical report that will be based on the GCMC pre-feasibility study. These Qualified Persons have verified the data in the news release.


The technical information contained in this press release was reviewed by Kevin Francis, P.Geo., VP, Resources for NovaGold and a Qualified Person as defined by NI 43-101.


Readers are cautioned that the conclusions, projections and estimates set out in this press release are subject to important qualifications, assumptions and exclusions, all of which are detailed in the PFS and technical report. To fully understand the summary information set out above, the technical report that will be filed on SEDAR at www.sedar.com and on EDGAR at www.sec.gov should be read in its entirety.


About NovaGold


NovaGold is a precious metals company engaged in the exploration and development of mineral properties located principally in Alaska, U.S.A. and British Columbia, Canada. The Company is focused on advancing its two core properties, Donlin Gold and Galore Creek, with the objective of becoming a low-cost, million-ounce-a-year gold producer, and offers superior leverage to gold and copper with one of the largest mineral reserve and mineral resource bases of any junior or mid-tier gold company. NovaGold has a strong track record of expanding deposits through exploration success and forging collaborative partnerships, both with local communities and with major mining companies. The Donlin Gold project in Alaska, one of the world's largest undeveloped gold deposits, is held by a limited liability company owned equally by wholly-owned subsidiaries of NovaGold and Barrick Gold Corporation. The Galore Creek project in British Columbia, a large copper-gold-silver deposit, is held by a partnership owned equally by wholly-owned subsidiaries of NovaGold and Teck Resources Limited. NovaGold also owns a 100% interest in the high-grade Ambler copper-zinc-lead-gold-silver deposit in northern Alaska and has other earlier-stage exploration properties. NovaGold trades on the TSX and NYSE-AMEX under the symbol NG. More information is available at www.novagold.net or by emailing info@novagold.net.


Cautionary Note Regarding Forward-Looking Statements


This press release includes certain 'forward-looking statements' within the meaning of the United States Private Securities Litigation Reform Act of 1995. All statements, other than statements of historical fact, included herein including, without limitation, statements relating to NovaGold's future operating or financial performance, are forward-looking statements. Specifically the information included under Project Economics and Production Estimates in this news release contain forward-looking information. Forward-looking statements are frequently, but not always, identified by words such as 'expects', 'anticipates', 'believes', 'intends', 'estimates', 'potential', 'possible', and similar expressions, or statements that events, conditions, or results 'will', 'may', 'could', or 'should' occur or be achieved. These forward-looking statements may include statements regarding perceived merit of properties; exploration results and budgets; mineral reserves and resource estimates; work programs; capital expenditures; timelines; strategic plans; completion of transactions; market prices for precious and base metals; or other statements that are not statements of fact. Forward-looking statements involve various risks and uncertainties.


There can be no assurance that such statements will prove to be accurate, and actual results and future events could differ materially from those anticipated in such statements. Important factors that could cause actual results to differ materially from NovaGold's expectations include the uncertainties involving the need for additional financing to explore and develop properties and availability of financing in the debt and capital markets; uncertainties involved in the interpretation of drilling results and geological tests and the estimation of reserves and resources; the need for continued cooperation with Teck Resources and the Tahltan Nation for development of the Galore Creek property; the need for cooperation of government agencies and native groups in the development and operation of properties; the need to obtain permits and governmental approvals;; risks of construction and mining projects such as accidents, equipment breakdowns, bad weather, non-compliance with environmental and permit requirements, unanticipated variation in geological structures, ore grades or recovery rates; unexpected cost increases, which could include significant increases in the capital and operating costs estimated in the prefeasibility study; fluctuations in metal prices and currency exchange rates; uncertainties and risks regarding the cost estimates and completion schedule for the proposed access tunnel and other risk and uncertainties disclosed in NovaGold's Annual Information Form for the year-ended November 30, 2010, filed with the Canadian securities regulatory authorities, and NovaGold's annual report on Form 40-F filed with the United States Securities and Exchange Commission and in other NovaGold reports and documents filed with applicable securities regulatory authorities from time to time. NovaGold's forward-looking statements reflect the beliefs, opinions and projections on the date the statements are made. NovaGold assumes no obligation to update the forward-looking statements of beliefs, opinions, projections, or other factors, should they change.


Cautionary Note Regarding Reserve and Resource Estimates


This press release has been prepared in accordance with the requirements of the securities laws in effect in Canada, which differ from the requirements of U.S. securities laws. Unless otherwise indicated, all resource and reserve estimates included in this press release have been prepared in accordance with National Instrument 43-101 Standards of Disclosure for Mineral Projects ('NI 43-101') and the Canadian Institute of Mining, Metallurgy, and Petroleum Definition Standards on Mineral Resources and Mineral Reserves. NI 43-101 is a rule developed by the Canadian Securities Administrators which establishes standards for all public disclosure an issuer makes of scientific and technical information concerning mineral projects. Canadian standards, including NI 43-101, differ significantly from the requirements of the United States Securities and Exchange Commission ('SEC'), and resource and reserve information contained herein may not be comparable to similar information disclosed by U.S. companies. In particular, and without limiting the generality of the foregoing, the term 'resource' does not equate to the term 'reserves'.


Under U.S. standards, mineralization may not be classified as a 'reserve' unless the determination has been made that the mineralization could be economically and legally produced or extracted at the time the reserve determination is made. The SEC's disclosure standards normally do not permit the inclusion of information concerning 'measured mineral resources', 'indicated mineral resources' or 'inferred mineral resources' or other descriptions of the amount of mineralization in mineral deposits that do not constitute 'reserves' by U.S. standards in documents filed with the SEC. U.S. investors should also understand that 'inferred mineral resources' have a great amount of uncertainty as to their existence and great uncertainty as to their economic and legal feasibility. It cannot be assumed that all or any part of an 'inferred mineral resource' will ever be upgraded to a higher category. Under Canadian rules, estimated 'inferred mineral resources' may not form the basis of feasibility or pre-feasibility studies except in rare cases. Investors are cautioned not to assume that all or any part of an 'inferred mineral resource' exists or is economically or legally mineable. Disclosure of 'contained ounces' in a resource is permitted disclosure under Canadian regulations; however, the SEC normally only permits issuers to report mineralization that does not constitute 'reserves' by SEC standards as in-place tonnage and grade without reference to unit measures. The requirements of NI 43-101 for identification of 'reserves' are also not the same as those of the SEC, and reserves reported by the Company in compliance with NI 43-101 may not qualify as 'reserves' under SEC standards. Accordingly, information concerning mineral deposits set forth herein may not be comparable with information made public by companies that report in accordance with U.S. standards.


To view the Appendix - Reserve & Resource Table, please click on the following link: http://media3.marketwire.com/docs/ng727t.pdf

Contacts:

NovaGold Resources Inc.

Greg Martin

Vice President Business Development & Treasurer

604-669-6227 or 1-866-669-6227
info@novagold.net
www.novagold.net



Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!



Mineninfo
NovaGold Resources Inc.
Bergbau
905542
CA66987E2069
Copyright © Minenportal.de 2006-2024 | MinenPortal.de ist eine Marke von GoldSeiten.de und Mitglied der GoldSeiten Mediengruppe
Alle Angaben ohne Gewähr! Es wird keinerlei Haftung für die Richtigkeit der Angaben und der Kurse übernommen!
Informationen zur Zeitverzögerung der Kursdaten und Börsenbedingungen. Kursdaten: Data Supplied by BSB-Software.