• Samstag, 23 November 2024
  • 04:42 Uhr Frankfurt
  • 03:42 Uhr London
  • 22:42 Uhr New York
  • 22:42 Uhr Toronto
  • 19:42 Uhr Vancouver
  • 14:42 Uhr Sydney

Dutwa progress and development

07.11.2011  |  Globenewswire Europe
7 November 2011

African Eagle Resources plc

AFRICAN EAGLE ADOPTS AN ENHANCED DUTWA DEVELOPMENT PROGRAMME

African Eagle Resources plc ("African Eagle" or the "Company"; AIM: AFE; AltX:
AEA) announces that it has adopted a streamlined development programme for its
Dutwa nickel project in Tanzania.

* Main phase of resource upgrade drilling complete
* Favourable new nickel metallurgical results received
* Neutralising limestone source identified and preliminary testing completed
* Use of Dutwa neutralising wastes offers potential cost advantages
* Limestone supply studies commenced
* Social and environmental impact assessment studies underway

Since joining the board of African Eagle in September 2011, CEO designate Trevor
Moss has undertaken a review of the Dutwa project and the development programme
previously defined by the Company. Moss has now proposed a streamlined
development programme to focus all efforts directly on the timely completion of
the Dutwa bankable feasibility study (the "BFS") which the Board has adopted.

Mr Moss comments: "African Eagle's prior studies have confirmed the viability of
Dutwa and recent analyses have identified various opportunities for project
optimisation which are currently being tested and are exhibiting favourable
preliminary results. To derive the maximum benefit from these studies and to
ensure the overall project timeline, it is important that we ensure Dutwa
progresses in a controlled way that results in an integrated and comprehensive
BFS. Any other approach would run the risk of extending the development
timetable and increasing the overall development cost. This programme negates
the need for the previously planned formal pre-feasibility study report and all
of the on-going studies will be fed directly into the BFS. We aim to complete
the BFS around the end of 2012 but may revise the timetable, if appropriate, to
ensure we take full advantage of opportunities to add value to the project. We
will update the market as key milestones are achieved"

Since the discovery of the Dutwa nickel deposit in 2008, the project has
developed rapidly. The current tasks supporting the BFS are advancing apace and
include: drilling to upgrade the JORC mineral resource from indicated to
inferred and to define its geology better; a definitive metallurgical test
programme designed to achieve the early definition of the optimal process plant;
the extension of the logistics studies; and the development of a full social and
environmental impact assessment (the "SEIA"). In addition, the Company will soon
add further internal project management skills via a dedicated and experienced
professional who will drive the completion of the BFS, and the subsequent
construction of the project.

Resource drilling

The current phase of resource upgrade reverse circulation ("RC") drilling at
Ngasamo is being completed this week. This drilling is directed towards
upgrading the existing JORC Inferred Resource to Indicated category and
extending the resource to the south of the existing resource, an area that was
not previously drilled.

Within the coming week, the drilling will move to the Wamangola deposit for
similar RC infill drilling to upgrade the remaining JORC Inferred Resource to
the Indicated category. On completion of this drilling programme, the Company
expects that all resource drilling necessary for the BFS will be complete,
subject to the results of resource modelling and pit optimisation to be
performed by Snowden of Australia.

Metallurgical test work

A comprehensive metallurgical test work programme is currently underway at
various laboratories in Perth, Australia and Johannesburg, South Africa. The
test work programme includes: ore upgrade and beneficiation studies; single and
dual stage agitated atmospheric tank leach tests; and agglomeration and heap
leach testing, each with associated variability analyses. In addition to run-of-
mine samples, a suite of composite ore samples have been constituted from Bulk
Ore Sample 1 representing the chief characteristic ore types from the Ngasamo
and Wamangola deposits. The test work programme has been designed to
comprehensively model the metallurgical performance of the deposits and evaluate
the available process methods to enable the early definition of the optimal
process plant flowsheet.

Following on from the studies undertaken by Professor Richard Herrington of the
National History Museum in London, initial results from beneficiation tests on
raw ore and composite samples indicate favourable performance with the potential
for run-of-mine ore to be pre-treated by way of a simple mechanical process to
enable an upgrading of plant head grade, thereby reducing the net processing
plant throughput rate with resulting capital and operating cost efficiencies.
Further testing will be undertaken to confirm these initial conclusions.

Results from the agitated atmospheric tank leaching continue to exhibit rapid
overall leach kinetics and confirm the overall favourable performance of the
Dutwa ores with good recoveries being achieved from relatively low acid
addition. Tests to examine integrated dual stage leaching to lower overall acid
consumption and maximise utilisation of the ore resource are well advanced.
Likewise, the heap leach test results to date, exhibit favourable performance
characteristics of low acid addition, low slumping, good percolation and
permeability properties and above average rates of nickel recoveries.

Both tank and heap leach tests at laboratory scale will continue in the short
term and the results from the agitated tank leach will be used to define and
construct a pilot plant, that will be employed in 2012, to confirm the bench
scale results (metal recoveries and reagent consumptions), and to validate the
process design parameters.

Acid neutralisation tests show that available limestone is highly reactive and
suitable for acid neutralisation and also that certain Dutwa saprolite ores
(which are relatively high in magnesium) can be partially substituted for
limestone, offering the potential to minimise external reagent requirements and
reduce operating costs.

Limestone Studies

Simulus of Perth, Australia has been commissioned to conduct a limestone supply
and transport study and the Company has undertaken the detailed assessment of a
limestone resource recently identified as suitable for neutralisation. This work
is ongoing.

Social and Environmental Studies

The Company recently engaged Citrus Partners LLP, a UK based speciality
consultancy, to manage the preparation of the SEIA for Dutwa. Citrus is deeply
experienced in the development of international SEIAs and has completed its
initial site visit. Working with Tanzanian consultants, Citrus will develop the
SEIA in full compliance with Tanzanian regulations and the Equator Principles.
The SEIA will be completed concurrent with the BFS.

Qualified Person

Information in this report relating to metallurgical test results is based on
data reviewed by Dr. Chad Czerny PhD, Project Manager, Metallurgy for African
Eagle Resources, who is a Member of the Australasian Institute of Mining and
Metallurgy, has more than 20 years' relevant experience in the mining and
metallurgical industry, and is a Qualified Person under AIM guidelines. Dr
Czerny consents to the inclusion of the information in the form and context in
which it appears.

Technical terms

A glossary of technical terms used by African Eagle in this announcement and
other published material may be found at www.africaneagle.co.uk/p/glossary.asp

For further information please see the Company's web site at
www.africaneagle.co.uk or contact one of the following:

African Eagle Resources plc
Trevor A. Moss (Chief Executive Officer) 1 925 577 1078
Mark Parker (Director) 44 207 248 6059

Canaccord Genuity Limited
Andrew Chubb 44 207 050 6500
Bhavesh Patel

Ocean Equities Limited
Guy Wilkes 44 207 786 4370

Russell & Associates, Johannesburg
Charmane Russell 27 11 880 3924
Marion Brower







This announcement is distributed by Thomson Reuters on behalf of
Thomson Reuters clients. The owner of this announcement warrants that:
(i) the releases contained herein are protected by copyright and
other applicable laws; and
(ii) they are solely responsible for the content, accuracy and
originality of the information contained therein.

Source: African Eagle Resources PLC via Thomson Reuters ONE

[HUG#1561119]


Unternehmen: African Eagle Resources PLC - ISIN: GB0003394813
Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!



Mineninfo
African Eagle Resources plc
Bergbau
-
-
Copyright © Minenportal.de 2006-2024 | MinenPortal.de ist eine Marke von GoldSeiten.de und Mitglied der GoldSeiten Mediengruppe
Alle Angaben ohne Gewähr! Es wird keinerlei Haftung für die Richtigkeit der Angaben und der Kurse übernommen!
Informationen zur Zeitverzögerung der Kursdaten und Börsenbedingungen. Kursdaten: Data Supplied by BSB-Software.