TORONTO, Jan. 24, 2012 /CNW Telbec/ - Caledonia Mining Corporation ('Caledonia')
(NASDAQ-OTCQX: CALVF) (AIM: CMCL) today announces gold production from the Blanket Mine in Zimbabwe during Q4 2011 which ended December 31, 2011.
-- 10,533oz gold produced during Q4 2011, representing an 8.1%
increase on Q3 2011 (9,743oz), and a 69% increase on Q4 2010
(6,227oz)
-- Total 2011 gold production was 35,826oz, a 102% increase over
the annual gold production in 2010 of 17,707oz
-- Targeted 2012 annual gold production of 40,000oz
Blanket Production
The Company is pleased to announce a successful year at the Blanket Mine which produced 35,826oz of gold, an increase of 102% over the previous year.
In accordance with our aim to continuously improve operations at Blanket, the following infrastructure, process and equipment investment programmes were undertaken during the final quarter of 2011:
-- Considerable work on the refurbishment of the 14, 18 and 22
Level underground haulages continued throughout Q4 and this is
expected to be completed by the end of Q1 2012. This programme
is essential to support and sustain our increased underground
production.
-- The installation of an automatic cyanide measuring and dosing
system on the CIL circuit was commissioned. This installation
is providing both better control over, and a detectable
reduction in, cyanide usage per tonne of ore milled.
-- Certain rectification and maintenance work on the 825m deep No4
Shaft was commenced during November 2011. This work is expected
to be completed by the end of February 2012 and once completed
will allow Blanket to increase the speed of the No4 Shaft
Winder, thereby increasing hoisting capacity. As noted in the
Q3 MD&A, this work may have an adverse effect on gold
production in the first quarter of 2012.
-- A Belt Scale was installed on the No1 Conveyor Belt so that all
ore tonnages delivered from various ore sources such as the 14
Level mid-shaft loading station, Lima, and in due course the
satellite properties such as GG and Mascot, can be individually
and accurately measured. The re-programed computerised
recording system is expected to be commissioned during early
February and the system is then expected to facilitate further
metallurgical optimisation.
Outlook
Following a year in which Caledonia has increased production at Blanket by 102% to 35,826oz (2010 gold production was 17,707oz), we are now confident that we will be able to achieve our targeted gold production of 40,000oz for the current financial year. Discussions with the Government of Zimbabwe regarding the indigenisation of the Blanket Mine have continued.
CALEDONIA MINING CORPORATION
CONTACT:
Caledonia Mining Corporation Collins Stewart Europe Limited
Mark Learmonth John Prior or Sebastian Jones
Tel: + 27 11 447 2499 Tel: + 44 20 7523 8350
marklearmonth@caledoniamining.com
Renmark Financial Communications Inc. Collins Stewart LLC
John Dan Mintz
Boidman: jboidman@renmarkfinancial.com Tel: +1 212 389 8022
Nadia DMintz@collinsstewartllc.com
Marks: nmarks@renmarkfinancial.com
Tel.: (514) 939-3989 or (416) 644-2020
www.renmarkfinancial.com
Newgate Threadneedle
Laurence Read/ Beth Harris/Terry
Garrett
Tel: +44 207 653 9850
Further information regarding Caledonia's exploration activities and
operations along with its latest financials and Management Discussion
and Analysis may be found at www.caledoniamining.com