• Freitag, 22 November 2024
  • 20:42 Uhr Frankfurt
  • 19:42 Uhr London
  • 14:42 Uhr New York
  • 14:42 Uhr Toronto
  • 11:42 Uhr Vancouver
  • 06:42 Uhr Sydney

Tamerlane Announces 12 Million Tonnes of Additional Reserves as a Result of a NI 43-101 Technical Report on the N-204 Deposit

08.02.2012  |  Marketwire
NOT FOR DISTRIBUTION TO U.S. NEWSWIRE SERVICES OR FOR DISSEMINATION IN THE UNITED STATES. ANY FAILURE TO COMPLY WITH THIS RESTRICTION MAY CONSTITUTE A VIOLATION OF U.S. SECURITIES LAW.

N-204 Lead/Zinc Deposit to Be Mined With Surface Mining Methods, More Than Doubling Current Reserves to 21 Million Tonnes, Extending Pine Point Mine Life

BLAINE, WASHINGTON -- (Marketwire - Feb. 8, 2012) - Tamerlane Ventures Inc. (“Tamerlane“ or the “Company“) (TSX VENTURE: TAM) is pleased to announce the results of its NI 43-101 technical report for the N-204 surface deposit at the Company's Pine Point Project, located in Canada's Northwest Territories. The N-204 deposit is located 60 kilometers to the northeast of the R-190 mill site.

The technical report was undertaken by third party consultants MineTech International Ltd (MineTech). The NI 43-101 report was completed by Mr. Douglas Roy, M.A.Sc., P.Eng., Ian M. Flint, Ph.D., P.Eng., Patrick Hannon M.A.Sc., P.Eng., and Bradford Ernst, P.Eng., Qualified Persons with MineTech International Limited, an Independent mining and geological engineering consulting firm.

The report shows the N-204 deposit at the Pine Point Project is feasible with an internal rate of return (IRR) of 90%, and the Company has already begun the permitting process for this deposit. The cash cost (average over mine life) of zinc production from the N-204 deposit is projected to be $0.47 per pound. The N-204 in-pit mineral resources were converted from Indicated resources to diluted probable reserves. The mineral inventory includes diluted probable reserves of 12.8 million tonnes at a grade of 0.70% lead and 2.60% zinc, and diluted in-pit inferred resources of 1.5 million tonnes at a grade of 0.6% lead and 2.3% zinc, at a cutoff grade of 1.1% combined zinc+lead.

The deposit will be developed using sequential surface panel mining whereby the ore will be taken in panels using conventional surface mining methods and the waste will be backfilled as the panels are mined. A dense media separation (DMS) plant will be constructed at the N-204 site and the DMS pre-concentrated ore will be transported to the already permitted R-190 milling facility. The technical report covers all aspects of infrastructure, development, mining and processing. The basis for the technical report assumes that the N-204 deposit will be mined over a period of 5 years as a stand-alone operation with the DMS concentrate filling the R-190 mill. This deposit may also be mined to provide supplemental ore in parallel with ore from the existing underground reserves in the R-190 area at any time over the first several years of mine life.


Highlights from the N-204 technical report and feasibility study:

Diluted Probable reserves 	12.8 million tonnes (2.6% Zn, 0.7% Pb)
Additional In-pit Inferred resources: 1.5 million tonnes (2.3% Zn, 0.6% Pb)
Capital cost: $32.2 million
Internal rate of return (IRR) 90%
Net present value (after tax) $54.2 million (@ 10% discount rate)
Cash cost zinc production: $0.47/lb.



1. Reserves and Resources

The N-204 deposit will provide an additional 5 years of mine life to the existing 8 years the Pine Point Project has currently, and is considered strategic because it may be mined using surface mining methods. This diversified mining approach will provide a second source of ore for the mill at R-190, significantly de-risking the project from an operational standpoint.

Reserves and resources have been calculated and are shown in Table 1-1.

Table 1-1
Pine Point Current Mineral Inventory
Tonnes
Open Pit (MM) Pb% Zn%
N-204 Diluted Probable Reserve 12.8 0.70 2.60
Diluted In-pit Inferred Resources 1.5 0.60 2.30

Tonnes
Underground (MM) Pb% Zn%
R-190 Area Diluted Proven & Probable Reserves 7.8 3.01 6.16
Measured & Indicated Resources 8.0 1.13 2.26

Tonnes
Remaining Historical Resources* (MM) Pb% Zn%
34.2 1.40 4.40

*The historical estimates presented above are not in accordance with the mineral resources or mineral reserves classifications contained in the CIM Definition Standards on Mineral Resources and Mineral Reserves, as required by National Instrument 43-101 (“NI 43-101“). Accordingly, the company is not treating these historical estimates as current mineral resources or mineral reserves as defined in NI 43-101 and such historical estimates should not be relied upon. A qualified person has not done sufficient work to date to classify the historical estimates as current mineral resources or mineral reserves.

The Mineral Resources are reported in accordance with Canadian National Instrument 43-101 (NI 43-101) and have been estimated in conformity with the generally accepted, “Estimation of Mineral Resource and Mineral Reserves Best Practices guidelines of the Canadian Institute of Mining, Metallurgy and Petroleum.“

See notes at the end of this press release for the primary parameters used by MineTech in calculating N-204 diluted probable reserves and diluted in-pit inferred resources.


2. Concentrate production from N-204

The dense media product will be transported to and processed in the R-190 mill with the same flow sheet as ore from the R-190 deposit. A small regrind circuit may be installed to enhance concentrate grades. The following table shows forecasted concentrate production and grades based on metallurgical work completed to date.

Table 2-1
Anticipated Concentrate Production
Forecast Annual
Concentrate Zn Con. Pb Con. Zinc Lead
Production Tonnes Tonnes Grade Grade
Year 1 93,100 24,200 58.0% 60.0%
Year 2 93,100 21,800 58.0% 60.0%
Year 3 89,500 20,400 58.0% 60.0%
Year 4 83,900 18,800 58.0% 60.0%
Year 5 72,900 16,300 58.0% 60.0%
Total by Year 5 432,500 101,500 58.0% 60.0%



3. N-204 Capital Costs

The total capital cost is estimated to be $32.2 million. The largest capital items are pre-production stripping and mining ($6.4 million) and the DMS plant and building ($6 million). A 20% miscellaneous/contingency factor was included. The study assumes mobile mining equipment will be leased. Mill capital (for the R190 mill site) was not considered when calculating capital costs for N-204 because it is assumed that Tamerlane will have constructed, and will be operating the mill for its other underground deposits.


4. N-204 Operating Costs

The operating costs for the N-204 deposit have been calculated based on actual quotations where possible, and from other similar scale projects in Canada. A summary of operating costs are broken down annually as shown in Tables 4-1.

Table 4-1
Annual Operating Cost Summary
(US$: millions)
Activity Y1 Y2 Y3 Y4 Y5 TOTAL
Mining 26.8 27.3 27.3 27.4 24.4 133.2
Transportation 8.3 8.3 8.3 8.3 8.3 41.5
Processing 15.9 15.9 15.9 15.9 16.1 79.7
Overhead and other 6.4 6.4 6.4 6.4 6.2 31.8
Cost per pound (US$)(zinc and zinc equivalent) $0.43 $0.44 $0.46 $0.49 $0.54 $0.47



5. Financial Analysis

For the base case scenario, the after-tax NPV (@ 10% discount rate) was $54 million. The internal rate of return was 90% and the payback period was less than one year. The profitability of the N-204 deposit is most sensitive to metal prices. Operating costs represent the next-most-sensitive parameter. The following table shows after-tax NPV (@ 10% discount rate) and other discount rates.

Table 5-1
NPV Analysis
Pre-Tax After-Tax
NPV8% $ 98,800,000 $ 58,900,000
NPV10% $ 91,200,000 $ 54,200,000
NPV15% $ 75,300,000 $ 44,100,000
NPV20% $ 62,500,000 $ 36,100,000
IRR 123% 90%


Metals prices of $1.10 zinc, and $1.10 lead were used for baseline calculations. Based on various reports and data from such sources as the International Lead Zinc Study Group (ILZSG), the London Metals Exchange (LME) and the International Monetary Fund (IMF), the Company expects positive movement in metals pricing over the next several years. Indications are that both lead and zinc metal supplies are heading into a deficit position in the near future, due to numerous major producers shutting down because of reserves being exhausted. In addition, worldwide consumption of metals is increasing on an annual basis. Specifically, growth is expected to continue in China, with additional demand due to further urbanization in India. These indications suggest that the Pine Point Project will be entering into the market at a time when both metals produced will be in high demand. Metal prices selected are in the low range of expected metal prices, and allow for upside for the project with expected higher prices for both zinc and lead from 2014 onward.

Mike Willett, CEO, commented, “We are excited to report such positive results for the N-204 deposit. Sequential surface panel mining is a conventional mining method, and is well suited to the deposit shape. This method will also allow the Company to backfill as mining progresses. This is an environmentally friendly approach because the majority of the waste and tailings are put back into the pit. The paved highway between the N-204 and R-190 deposits is cleared year-round and allows for easy transportation between the deposits. We also have the options of mining the N-204 deposit as supplemental material to the underground mining operations, or mining the N-204 as a stand-alone operation upon permitting. This greatly de-risks the existing project and adds another 5 years to the mine life. Environmental background data has already been collected and we will be submitting information necessary for permitting in the near future. We expect that this deposit could be permitted by the time the R-190 mill starts up in 2014.

The company has 35 other deposits containing an aggregate historical* resource of 34.2 million tonnes. We expect several of these deposits to also be economic similar to N-204. In a recent news release we announced that we would be drilling several of the near-surface deposits located on our Pine Point property. The W-85 deposit, which the Company intends to mine using surface mining methods, has been drilled and assayed, and resource modeling is currently being completed. We expect this resource estimate to be released later this year. With over 13 years of NI 43-101 reserves on our books, and the Pine Point project able to produce some of the finest lead zinc concentrates in the world, Tamerlane has positioned itself to quickly become a mid-tier base metal producer.“

The information in this press release was prepared under the guidance of Mr. Ross F. Burns, P.Geo., LG., who is designated as a Qualified Person with the ability and authority to verify the authenticity and validity of the data and independent technical reports.

Notes
Parameters Used by MineTech in the Feasibility Study
1. Current mineral reserve estimate prepared by Doug Roy, M.A.Sc., P.Eng., MineTech International Limited, using the digital block model that Pincock, Allen and Holt (PAH) created for their March, 2011 mineral resource estimate.
2. PAH (2011) used top-cut values of 25% for zinc and 6.5% for lead during block grade estimation of mineral resources.
3. PAH (2011) outlined the mineralised zones using a 0.9% zinc-equivalent cut-off grade.
4. PAH (2011) estimated block grades using inverse distance weighting (power of two).
5. For the current mineral reserve study, one pound of lead was determined to be equivalent to 1.12 pounds of zinc using the following parameters:

Parameter 	Zinc 	Lead
Price ($US per lb) $1.10 $1.10
Overall Milling Recovery 78.2% 72.5%
Concentrate Grade 58% 60%
Smelter Treatment Charges (per lb) $0.16 $0.12
Concentrate Shipping and Handling (per lb) $0.12 $0.13
Smelter Return 85% 95%

6. The SG values were calculated for each block based on the metal content and the estimated void content.
7. Dilution and mining recovery were estimated to be 15% and 95%, respectively.
8. The diluted stripping ratio, by volume, was 5:1.
9. All figures were rounded to reflect the accuracy of the estimates.


About Tamerlane Ventures Inc.

Tamerlane Ventures Inc. is an exploration and development mining company with advanced base metal development projects in Canada and Peru. The Company's immediate focus is bringing the 100%-owned Pine Point Project to production. The Company is currently in the financing phase and expects to commence construction following financing. Tamerlane plans to sell the well-known, Pine Point Concentrates to various smelting facilities around the world. The Company also plans to develop its Los Pinos heap leach copper project in Peru.


Michael A. Willett
Chief Executive Officer



Caution Concerning Forward-Looking Information

This press release contains forward-looking information within the meaning of applicable securities laws. We use words such as “may“, “will“, “should“, “anticipate“, “plan“, “expect“, “believe“, “estimate“ and similar terminology to identify forward-looking information. It is based on assumptions, estimates, opinions and analysis made by management in light of its experience, current conditions and its expectations of future developments as well as other factors which it believes to be reasonable and relevant. Forward-looking information involves known and unknown risks, uncertainties and other factors that may cause our actual results to differ materially from those expressed or implied in the forward-looking statements and, accordingly, readers should not place undue reliance on those statements. Risks and uncertainties that may cause actual results to vary include but are not limited to the speculative nature of mineral exploration and development, including the uncertainty of reserve and resource estimates; operational and technical difficulties; the availability to the Company of suitable financing alternatives; fluctuations in zinc, lead and other resource prices; changes to and compliance with applicable laws and regulations, including environmental laws and obtaining requisite permits; political, economic and other risks arising from our activities; fluctuations in foreign exchange rates; as well as other risks and uncertainties which are more fully described in our annual and quarterly Management's Discussion and Analysis and in other filings made by us with Canadian securities regulatory authorities and available at www.sedar.com.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.




Contact Information

Tamerlane Ventures Inc.
Brent Jones
Director of Corporate Communications and Investor Relations
(360) 332-4636
(360) 332-5025 (FAX)
bjones@tamerlaneventures.com
www.tamerlaneventures.com
Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!



Mineninfo
Tamerlane Ventures Inc.
Bergbau
-
-
Copyright © Minenportal.de 2006-2024 | MinenPortal.de ist eine Marke von GoldSeiten.de und Mitglied der GoldSeiten Mediengruppe
Alle Angaben ohne Gewähr! Es wird keinerlei Haftung für die Richtigkeit der Angaben und der Kurse übernommen!
Informationen zur Zeitverzögerung der Kursdaten und Börsenbedingungen. Kursdaten: Data Supplied by BSB-Software.