• Dienstag, 23 Juli 2024
  • 18:20 Uhr Frankfurt
  • 17:20 Uhr London
  • 12:20 Uhr New York
  • 12:20 Uhr Toronto
  • 09:20 Uhr Vancouver
  • 02:20 Uhr Sydney

EastCoal Inc. - Wash Plant Construction on Schedule

09.07.2012  |  Marketwire
VANCOUVER, BRITISH COLUMBIA -- (Marketwire - July 9, 2012) - EastCoal Inc. (TSX VENTURE: ECX) (the "Company" or "EastCoal") is pleased to announce that the construction of the new wash plant at the Menzhinsky Coal Mine in Ukraine ("Menzhinsky Mine") is proceeding on schedule with first coal expected to be processed in the current quarter. The foundations for the plant were completed in June and a team of engineers and technicians from Keats Engineering in the UK are on site and assembling the plant, which was built in the UK.

The plant is designed to process 400 tonnes of material an hour and is anticipated to produce 91,000 tonnes of saleable coal in 2012. It is expected to commence generating positive cash flows in the current quarter.

The Chairman of EastCoal, Mr. John Byrne, commented:

"We are very pleased with the progress of the Menzhinsky wash plant and the planned cash generated from this operation will assist in financing the Company's plans in the region."

The Company is filing the Amended Pre-Feasibility Study Report on the Verticalnaya Mine, Lugansk Oblast, Ukraine dated March 2011 as amended June 2012 on SEDAR at www.sedar.com.


By Order of the Board,

John Byrne
Chairman



About EastCoal Inc.

EastCoal Inc. is currently producing coking coal from its 100% owned Menzhinsky mine and developing its 100% owned Verticalnaya anthracite mine.


This press release contains projections and forward-looking information that involve various risks and uncertainties regarding future events. Such forward-looking information can include without limitation statements based on current expectations involving a number of risks and uncertainties and are not guarantees of future performance. There are numerous risks and uncertainties that could cause actual results to differ materially from those expressed in the forward-looking information. These and all subsequent written and oral forward-looking information are based on estimates and opinions on the dates they are made and are expressly qualified in their entirety by this notice. Except as required by law, EastCoal assumes no obligation to update forward-looking information should circumstances or management's estimates or opinions change. Completion of the transaction described herein will be subject to numerous conditions, including the negotiation and execution of definitive agreements. There can be no assurance that the transaction will be completed as proposed or at all.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.




Contact Information

EastCoal Inc.
Abraham Jonker, President
(604) 681-8069

EastCoal Inc.
George Lawton, CFO
(604) 681-8069
(604) 685-4675 (FAX)
www.eastcoal.ca
Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!



Mineninfo
CoTec Holdings Corp.
Bergbau
A3CZB1
CA22165A1021

Copyright © Minenportal.de 2006-2024 | MinenPortal.de ist eine Marke von GoldSeiten.de und Mitglied der GoldSeiten Mediengruppe
Alle Angaben ohne Gewähr! Es wird keinerlei Haftung für die Richtigkeit der Angaben und der Kurse übernommen!
Informationen zur Zeitverzögerung der Kursdaten und Börsenbedingungen. Kursdaten: Data Supplied by BSB-Software.