Western Potash Corp. Delivers Feasibility Study with After-tax $2.44 B NPV, 18.6% IRR, 5.6 year Payback and Declares Reserves at Milestone
Western Potash Corp. (WPX: TSX) (FSE: AHE) ('the Company?)
is pleased to announce the receipt of a positive Feasibility Study (the
'Study?) from AMEC Americas Limited ('AMEC?) on the Company′s 100% owned
Milestone property in southern Saskatchewan (the 'Project?). The Study
confirms that the asset is of sufficient size and grade to support
primary and secondary potash solution mining for more than forty years
at an ultimate production rate of 2.8Mt/yr. The Study included detailed
CAPEX and OPEX estimates with a production start up in 2016.
The Study reports that the resulting after-tax project Net Present Value
('NPV?) is $2.44B CAD, with an Internal Rate of Return ('IRR?) of 18.6 %
assuming a nominal discount rate of 10%. On a before tax basis, the
Project yields an NPV of $3.6B CAD and an IRR of 21%.
Patricio Varas, President and CEO commented, 'Our Project is in an
enviable, low risk geopolitical and regulatory jurisdiction, which is a
key advantage for developers that look for long-term investment
predictability. The lower capital intensity of the Project combined with
the plant′s efficient operations and high throughput produce a project
with attractive rates of return and significant free cash flow. These
factors, coupled with the detailed scope of project evaluation, the size
and grade of the deposit, and the project development expertise of the
management team, presents a unique opportunity for investors and
developers to secure an economical, reliable and long term supply of
potash.?
Key Highlights of Study
Initial CAPEX1 | ? | $2.91B CAD | |
Deferred CAPEX2 | $0.39B CAD | ||
Contingency and Escalation included in CAPEX | $0.55B CAD | ||
OPEX3 | $62.28 CAD/t at full production capacity | ||
Sustaining CAPEX | Wellfield =$28.49 CAD/t, Plant & Site =$17.99 CAD/t at full production capacity | ||
Rail and Port Cost4 | $59.00 CAD/t | ||
Accuracy of Study | +15% to -10% | ||
After-tax NPV10 | $2.44B CAD | ||
IRR | 18.6% | ||
Payback Period | 5.6 years | ||
Proven and Probable Reserves5 | 137 Mt KCl | ||
1 includes water supply CAPEX. 2 includes all CAPEX required to produce at full 3 includes estimates for labour, maintenance, power, 4 cost includes port operator return on capital 5represents recoverable tonnes KCl |
The economic analysis performed in the Study was based on the following
assumptions:
Base case | ? | 100% equity, 10% discount rate, nominal cash flow | |
Mine life | 40 years | ||
Production rate | 2.8 Mt/yr | ||
Maximum Primary Mining Production | 2.0 Mt/yr | ||
Construction Period | 3.5 years commencing 2013 subject to financing and permitting approval | ||
Mining Start-up | 2016 | ||
Production ramp up period | 2016-2022 | ||
Plant Recovery | 93.5% | ||
Product Specification | K62 (98.1% KCl) | ||
Closure Cost Allowance | 10% of CAPEX included at end of mine | ||
Product Split | 80% granular, 20% standard | ||
Potash Price FOB Vancouver | $450 USD/t for standard grade1, $470 USD/t for granular grade, weighted as per product split | ||
USD:CAD Exchange Rate | 1:1 | ||
Inflation | 2% applied to potash price and costs | ||
Taxes and Royalties | Crown Royalty, Corporate Capital Tax Resource Surcharge, Potash Production Tax, and Income Tax included in model | ||
1 Source: CRU Strategies. 2012 weighted annual average |
The Study includes all facilities required to operate a potash solution
mine, including: cavern and wellfield layout, two-train multiple effect
evaporization-crystallization plant, dry processing plant, product
storage, load out and all other necessary site infrastructure. This
design, which was detailed to a sufficient level to allow the capital
cost estimate to conform to AACE 'Class 3? standard, can accommodate
future production expansion.
Table 1 and 2 evaluate the key economic sensitivities of the Project.
Since the analysis is based on a cash flow estimate, actual financial
results may vary from these predictions.
Table 1. Project Potash Price, OPEX, and CAPEX Sensitivities
? | NPV10 ($CAD billions) | ? | IRR (%) | ||
Base Case Discounted Nominal Cash Flow Model | 2.44 | 18.6 | |||
10% Increase/Decrease in Potash Price | 3.09/1.79 | 20.5/16.5 | |||
10% Increase in OPEX | 2.34 | 18.2 | |||
10% Increase in CAPEX | 2.25 | 17.3 |
Table 2. Project Discount Rate Sensitivities
? | NPV9 | ? | NPV10 | ? | NPV11 | ||
Nominal After-tax NPV ($CAD billions) | 3.09 | 2.44 | 1.91 |
The Project has excellent access to all infrastructure, utilities,
services, and is supported by a world class potash Reserve. Power,
natural gas, water, and existing rail connections are readily available
near the Project. All major technical and execution project risks have
now been mitigated. Non-technical project risks, such as environment and
political concerns, remain low.
The Study was intended to provide a high degree of project definition,
building on the Prefeasibility Study completed in September 2011. The
Study included a solid set of engineering deliverables from AMEC, and
consolidated input from other expert consultants including Whiting
Equipment Canada Ltd (Process Design), Agapito Associates Inc. (Geology
and Solution Mining), Impact Oilfield Management (Wellfield), Golder
Associates (Environment and TMA), and KGS Group (Water Treatment). The
Company was assisted by Novopro Projects Inc. who provided engineering
oversight.
AMEC is a leading international engineering and project management
company that currently manages multiple potash development and expansion
projects in Saskatchewan with a capital value of several billion
dollars. AMEC was chosen to carry out the Study because of their
technical expertise as engineers and EPCM contractors, as well as their
experience in potash mine construction, potash processing and their
expertise in producing potash feasibility studies.
Summary of Reserve and Resource Update
The Company is pleased to further announce that as a result of the mine
plan and favorable economic results developed and presented in the
Study, a portion of the previously reported Measured and Indicated
Resources have been upgraded to Proven and Probable Reserves
respectively.
A summary of the results for Proven and Probable Reserves, and Measured,
Indicated, and Inferred Resources within Crown and Leased Freehold Areas
are presented in Tables 3 and 4.
A detailed break-down of the Reserves and Resources will be included
with the NI 43-101 report to be filed as required by Canadian securities
regulators. Agapito Associates Inc. ('AAI?) have made estimates of the
Resources and Reserves based on a Radius of Influence (ROI) similar to
that applied by mine operators and peer group explorers working on
solution mining properties in the region. The Resource and Reserve
estimate was prepared in accordance with the requirements of NI 43-101
of the Canadian securities regulators. Mineral resources that are not
mineral reserves do not have demonstrated economic viability.
Table 3. Proven and Probable Reserves within Crown and Leased Freehold
Areas*
Reserve Category | KCl Reserve (Mt) |
Proven Reserves | 35.84 |
Probable Reserves | 101.44 |
Total | 137.28 |
* Search Radius of 800 m used for Proven and 1.6 km outside radius, 2.5
km inner radius (between drill holes) used for Probable; Mt = million
tonnes; K2O cut-off grade = 15%; Density = 2.08 t/m3, KCl =
1.58303 K2O. Accounts for known geologic anomalies, unknown geologic
anomalies (5% for Proven, 9% for Probable), and recoverable tonnages of
KCl contained in caverns within the search radius. Accounts for 87.3%
cavern, and 93.5% plant KCl recoveries.
Table 4. Measured, Indicated and Inferred Mineral Resource (exclusive of
Reserves) within Crown and Leased Freehold Areas.*
Resource Category | ? | Average KCl Grade (%) | ? | In-Place Tonnage (Mt) | ? | In-Place KCl Tonnage (Mt) | ? | KCl Resource (Mt)** | |
Measured Resource | 21.11 | 226.37 | 47.79 | 15.71 | |||||
Indicated Resource | 21.66 | 529.97 | 114.77 | 36.84 | |||||
Inferred Resource | 25.96 | 10,513.16 | 2,729.00 | 708.18 | |||||
|
The total Proven and Probable Reserves are sufficient to support mining
at an annual rate of 2.8 Mt of KCl for 49 years, well beyond the mine
plan contemplated in the Study. As commercial mining is initiated, the
geological information from the ongoing wellfield drilling will be used
to further define and expand the mineral Reserves and Resources. The
Project Reserves and Resources have the potential to support an ongoing
mining operation well into the next century.
The updated Resource and Reserve estimate was prepared by AAI of Grand
Junction, Colorado. AAI′s experience includes work for Intrepid Potash
Inc. in the US, Rio Tinto and Vale at the PRC project in Argentina, and
work for several prospective potash projects located in Saskatchewan.The
Qualified persons for the Resource and Reserve Estimate were Dr. Michael
P. Hardy, P.E (US), P.Eng. (SK), and Dr. Douglas F. Hambley, P.E. (US),
P.Eng. (SK), P.G. (US).
The Company will file an updated NI 43-101 Technical Report with
Canadian securities regulators within 45 days of this release and will
be available on SEDAR at www.sedar.com,
and also on the Company's website at www.westernpotash.com.
EIS Update
Further to the news release issued on September 5, 2012, the Company
wishes to provide an update on its Environmental Impact Statement
('EIS?) for the Project. The EIS was prepared and submitted to the
Saskatchewan Ministry of Environment ('MOE?) in conformance with the
Government of Saskatchewan′s 'Environmental Assessment Act.? A review
process of the EIS by the regulatory agencies is ongoing. Following a
satisfactory technical review, the EIS will be posted on the MOE′s
website and available for public review. The Company anticipates
Environmental Assessment approval in the first quarter of 2013.
About Western Potash Corp.
Western Potash Corp. is a development company engaged in the evaluation,
exploration and development of potash mineral properties in Western
Canada. The Company intends to develop a world-class potash deposit in
an ecologically sustainable, economically efficient and socially
responsible manner.
The in-house qualified persons for the purposes of NI 43-101 guidelines
are J. Patricio Varas, P. Geo and Dean Pekeski, P. Geo, both of whom
have reviewed and approved the contents of this news release.
For more information on Western Potash Corp.′s projects, please visit
the Company′s website at: www.westernpotash.com
ON BEHALF OF THE BOARD OF DIRECTORS
'J. Patricio Varas?
J. Patricio Varas
President and CEO
Forward-Looking Statement
This news release includes certain statements and information that
may contain forward-looking information within the meaning of applicable
Canadian securities laws. All statements in this news release, other
than statements of historical facts, including the likelihood of
commercial mining, securing a strategic partner and financing
requirements and the ability to fund future mine development are
forward-looking statements. Such forward-looking statements and
forward-looking information specifically include, but are not limited
to, statements concerning: Company plans at the Milestone Project;
Company ability to fund the Milestone Project; the timing of granting of
key permits; approval of the EIS; from the Study: the estimated potash
production and the timing thereto, economic analyses, capital and
operating costs, mine development programs, future potash prices, cash
flow estimates, and economic indicators derived from the foregoing.
Generally, forward-looking information can be identified by the use
of forward-looking terminology such as 'intends? or 'anticipates?, or
variations of such words and phrases or statements that certain actions,
events or results 'may?, 'could?, 'should?, 'would? or 'occur?.Forward-looking
statements are based on the opinions and estimates of management as of
the date such statements are made and they are subject to known and
unknown risks, uncertainties and other factors that may cause the actual
results, level of activity, performance or achievements of Western
Potash to be materially different from those expressed or implied by
such forward-looking statements or forward-looking information,
including: the receipt of all necessary approvals; the ability to
conclude a transaction; uncertainty of future production, capital
expenditures and other costs; financing and additional capital
requirements; the receipt in a timely fashion of any further permitting
for the Milestone Project; legislative, political, social or economic
developments in the jurisdictions in which Western Potash carries on
business; operating or technical difficulties in connection with mining
or development activities; and the risks normally involved in the
exploration, development and mining business.Although management
of Western Potash has attempted to identify important factors that could
cause actual results to differ materially from those contained in
forward-looking statements or forward-looking information, there may be
other factors that cause results not to be as anticipated, estimated or
intended.There can be no assurance that such statements will
prove to be accurate, as actual results and future events could differ
materially from those anticipated in such statements.Accordingly,
readers should not place undue reliance on forward-looking statements
and forward looking information.Western Potash does not
undertake to update any forward-looking statements or forward-looking
information that are incorporated by reference herein, except in
accordance with applicable securities laws.
For more information please contact John Costigan, VP Corporate
Development, at (604) 689-9378.
Western Potash Corp.
John Costigan, VP Corporate Development
(604)
689-9378