The process plant throughput was 6% above budget at 1,702,574 tonnes at 1.04g/t (June Qtr 1,728,751 tonnes at 1.05g/t). The process plant continues to operate in a steady state and above expectations. Gold production was 47,646 oz (June Qtr 50,817oz) at a recovery of 83.3% (June Qtr 83.3%). Plant availability remained good at 93.8% (June Qtr 93.4%) with all areas of the plant performing well. The SAG mill continued
[...]