Highlights: Mine prestrip, preliminary dump foundations and ramps are complete, and approximately 50,000 tonnes of ore is being placed on the ore pad by end of August for commissioning and initial operations. The following plant areas are substantially complete, and commissioning of the equipment is underway: Primary and secondary crushing circuit
[...]